 QuarterSiteTitleTopic
05000416/FIN-2018002-042018Q2Grand GulfHigh Radiation Area Boundary ViolationHigh Radiation Area
05000416/FIN-2017007-022017Q4Grand GulfFailure to Correct Standby Diesel Generator TripCondition Adverse to Quality
05000445/FIN-2017003-022017Q3Comanche PeakProgrammatic Failures to Control Transient Combustible Material in Accordance with a Fire Protection ProcedureSafe Shutdown
Significance Determination Process
Fire Protection Program
05000458/FIN-2017009-012017Q2River BendFailure to Obtain Prior NRC Approval for a Change in Reactor Core Isolation Cooling Injection Point
05000482/FIN-2017404-012017Q2Wolf CreekSecurity
05000313/FIN-2017008-022017Q2Arkansas NuclearInadequate FLEX ProceduresFLEX
Significance Determination Process
Spent Fuel Pool Instrumentation
05000458/FIN-2016404-052016Q4River BendSecurity
05000382/FIN-2016002-022016Q2WaterfordFailure to Properly Assess and Manage Risk When Performing Dry Cooling Tower MaintenanceUltimate heat sink
Probabilistic Risk Assessment
Significance Determination Process
05000382/FIN-2016001-012016Q1WaterfordFailure to Assess and Manage the Increase in Risk from Emergent Maintenance ActivitiesProbabilistic Risk Assessment
Significance Determination Process
05000498/FIN-2016007-082016Q1South TexasFailure to Ensure Sufficient Capacity and Capability of Mitigating Systems during a Station Blackout EventSignificance Determination Process
Battery sizing
05000458/FIN-2015004-012015Q4River BendFailure to Ensure Work Hours are Within Work Hour LimitsFitness for Duty
Significance Determination Process
05000458/FIN-2015004-062015Q4River BendFailure to Restore Main Steam Positive Leakage Control System to Operable Prior to Changing Modes
05000416/FIN-2015007-042015Q4Grand GulfFailure to Identify and Address Impacts of Revised Calculation Output DataSignificance Determination Process
05000416/FIN-2015301-012015Q4Grand GulfInadequate Plant Operating Procedures with Eight ExamplesSignificance Determination Process
Maintenance Rule Program
05000445/FIN-2015005-022015Q4Comanche PeakFailure to Take Appropriate Maintenance Rule Corrective Actions for the 6.9 kV AC SystemSignificance Determination Process
Maintenance Rule Program
05000498/FIN-2015004-012015Q4South TexasFailure to Track and Incorporate Actual Plant Data into Simulator Operability TestingSignificance Determination Process
05000458/FIN-2015009-062015Q2River BendFailure to Identify and Classify Operator Workarounds that Impacted Scram Recovery ActionsSignificance Determination Process
Maintenance Rule Program
05000298/FIN-2015008-032015Q2CooperMain Steam Isolation Valve Scram Closure condition Prohibited By Technical SpecificationsSignificance Determination Process
05000285/FIN-2015008-032015Q1Fort CalhounFailure to Promptly Identify and Correct a Condition Adverse to QualityBoric Acid
Condition Adverse to Quality
05000397/FIN-2015001-012015Q1ColumbiaFailure to Comply with ECCS Technical SpecificationsInternal Flooding
05000416/FIN-2015001-052015Q1Grand GulfFailure to Establish, Implement, and Maintain Appropriate Changes to the Offsite Dose Calculation Manual For REMP Airborne SamplingOffsite Dose Calculation Manual
Significance Determination Process
05000382/FIN-2014007-052015Q1WaterfordFailure to Identify and Correct Through Wall Corrosion on Emergency Diesel Generator A and B Day Tank VentsCondition Adverse to Quality
Significance Determination Process
Large early release frequency
05000458/FIN-2014005-012014Q4River BendFailure to Retain Scenario-Based Testing DocumentationSignificance Determination Process
05000483/FIN-2014004-012014Q3CallawayFailure to Perform Nondestructive Testing on Essential Service Water Piping in Accordance with ProceduresSignificance Determination Process
Through-Wall Leak
05000445/FIN-2014004-012014Q3Comanche PeakFailure to Establish Goals and Monitor the Performance of the Uninterruptible Power Supply Air Conditioning System
05000313/FIN-2014003-082014Q2Arkansas NuclearFailure to Establish, Implement, and Maintain Appropriate Changes to the Offsite Dose Dose Caculation Manual Fort Airborne SamplingOffsite Dose Calculation Manual
Significance Determination Process
05000298/FIN-2014002-012014Q1CooperFailure to Implement Risk Management Actions for Maintenance ActivitiesInternal Flooding
Significance Determination Process
05000285/FIN-2013013-072014Q1Fort CalhounProgrammatic Failure to Evaluate Safety Impact of Degraded Conditions During Use of Interim Operability CriteriaSignificance Determination Process
Maintenance Rule Program
05000416/FIN-2014002-022014Q1Grand GulfFailure to Control a Locked High Radiation Area Due to Unsecured Highly Radioactive Materials Stored in the PoolHigh Radiation Area
Locked High Radiation Area
Significance Determination Process
Substantial potential for an overexposure
05000298/FIN-2013005-022013Q4CooperFailure to Implement Risk Management Actions for Proposed Maintenance ActivitiesSignificance Determination Process
05000445/FIN-2013008-012013Q4Comanche PeakFailure to Perform Cause Evaluations for Maintenance Preventable Functional FailuresSignificance Determination Process
Maintenance Rule Program
05000482/FIN-2013008-092013Q3Wolf CreekFailure to Properly Assess Problems with Component Cooling Water Valve EGHV102
05000298/FIN-2013004-012013Q3CooperFailure to Maintain Design Control of the Control Room Emergency Filter System Safety-related Air Operated ValveStroke time
Significance Determination Process
Maintenance Rule Program
05000298/FIN-2013004-022013Q3CooperFailure to Establish Goals and Monitor for the Roof Drain SystemsSignificance Determination Process
Maintenance Rule Program
05000397/FIN-2013008-012013Q3ColumbiaProgrammatic Failure to Promptly Evaluate Safety Impact of Degraded Conditions
05000416/FIN-2013004-072013Q3Grand GulfFailure to Follow Alarm Response Steps to Restore the TSE Following MaintenanceSignificance Determination Process
05000482/FIN-2013003-022013Q2Wolf CreekFailure to Identify Leakage at Refuel Pool CavityBoric Acid
Condition Adverse to Quality
05000298/FIN-2013003-012013Q2CooperFailure to Adequately Assess Risk and Implement Risk Management Actions for Proposed MaintenanceInternal Flooding
Significance Determination Process
05000285/FIN-2013008-132013Q2Fort CalhounFailure to Establish and Document Basis for Test Acceptance CriteriaTime to boil
Significance Determination Process
05000416/FIN-2013002-082013Q1Grand GulfFailure to Revise the Scram Procedure After Temporary ModificationTemporary Modification
Significance Determination Process
05000397/FIN-2012404-032013Q1ColumbiaSecurity
05000275/FIN-2013002-012013Q1Diablo CanyonFailure to Provide Adequate Guidance to Address General Welding Standard RequirementsSignificance Determination Process
05000445/FIN-2013002-022013Q1Comanche PeakFailure to Have Instructions When Performing ActivitiesSignificance Determination Process
05000416/FIN-2012005-022012Q4Grand GulfFailure to Adequately Monitor the Condition of the Auxiliary Building Water Intrusion BarrierSignificance Determination Process
Maintenance Rule Program
05000498/FIN-2012005-022012Q4South TexasFailure to Follow Procedure for the Control of Tools for Use on Stainless Steel
05000458/FIN-2012012-012012Q4River BendFailure to Identify and Correct a Condition Adverse to QualityCondition Adverse to Quality
Significance Determination Process
Maintenance Rule Program
05000416/FIN-2012005-062012Q4Grand GulfFailure to Evaluate the Risk Significances and Develop Action Plans to Address Equipment Identified During Extent of Condition Review for a Post Scram Root Cause AnalysisSignificance Determination Process
05000382/FIN-2012008-052012Q3WaterfordFailure to Develop Effective Corrective Actions to Preclude RepetitionCondition Adverse to Quality
Significance Determination Process
05000382/FIN-2012008-042012Q3WaterfordFailue to Ensure Operator Knowledge of Equipment StatusSignificance Determination Process
05000254/FIN-2012007-012012Q3Quad CitiesCAPR Not Completed