UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, O.C. 20555-0001 July 2, 2018 Mr. Steven Capps Senior Vice President Nuclear Corporate Duke Energy Corporation 526 South Church Street, EC-07H Charlotte, NC 28202

SUBJECT:

BRUNSWICK STEAM ELECTRIC PLANT, UNITS 1 AND 2 AND SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1 -AUDIT PLAN RE: APPLICATION TO ADOPT 10 CFR 50.69, "RISK-INFORMED CATEGORIZATION AND TREATMENT OF STRUCTURES, SYSTEMS, AND COMPONENTS FOR NUCLEAR POWER REACTORS" (EPID L-2018-LLA-0008 AND L-2018-LLA-0034)

Dear Mr. Capps:

By letters dated January 10 and February 1, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML 1801 OA344 and ML18033B768, respectively), Duke Energy Progress, LLC (Duke Energy) submitted license amendment requests for Brunswick Steam Electric Plant, Units 1 and 2, and Shearon Harris Nuclear Power Plant, Unit 1. The proposed amendments would modify the licensing basis to allow for the implementation of the provisions of Section 50.69, "Risk-informed categorization and treatment of structures, systems, and components for nuclear power plants," of Title 10 of the Code of Federal Regulations ( 10 CFR).

The U.S. Nuclear Regulatory Commission (NRC) staff will conduct a regulatory audit to support its review of the proposed license amendments. The audit will be conducted at Duke Energy's corporate office in Charlotte, North Carolina, on July 17-19, 2018. The NRC staff's audit plan is enclosed. The audit plan may be supplemented with audit questions at a later time.

S. Capps If you have any questions, please contact me at 301-415-2760 or Martha.Barillas@nrc.gov.

Sincerely, Martha Barillas, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-325, 50-324, and 50-400

Enclosure:

Regulatory Audit Plan cc: Mr. William R. Gideon Vice President Brunswick Steam Electric Plant Duke Energy Progress, LLC 8470 River Road, SE (M/C BNP001)

Southport, NC 28461 Ms. Tanya Hamilton Site Vice President Shearon Harris Nuclear Power Plant, Unit 1 5413 Shearon Harris Road, M/C HNP01 New Hill, NC 27562-0165 Listserv

REGULATORY AUDIT PLAN BY THE OFFICE OF NUCLEAR REACTOR REGULATION TO SUPPORT THE REVIEW OF LICENSE AMENDMENT REQUESTS FOR BRUNSWICK STEAM ELECTRIC PLANT, UNITS 1 AND 2 AND SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1 TO ADOPT 10 CFR 50.69, "RISK-INFORMED CATEGORIZATION AND TREATMENT OF STRUCTURES, SYSTEMS AND COMPONENTS FOR NUCLEAR POWER REACTORS DOCKET NOS. 50-325, 50-324, AND 50-400

1.0 BACKGROUND

By letters dated January 10 and February 1, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML18010A344 and ML180338768, respectively), Duke Energy Progress, LLC (Duke Energy) submitted license amendment requests (LARs) for Brunswick Steam Electric Plant, Units 1 and 2 (BSEP), and Shearon Harris Nuclear Power Plant, Unit 1 (HNP). The proposed amendments would modify the licensing basis to allow for the implementation of the provisions of Title 10 of the Code of Federal Regulations (10 CFR), Section 50.69, "Risk-informed categorization and treatment of structures, systems, and components for nuclear power plants," and provide the ability to use probabilistic risk assessment (PRA) models, the internal events PRA (IEPRA), internal flooding PRA (IFPRA), and internal fire PRA (FPRA) for the proposed 10 CFR 50.69 categorization process.

The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed Duke Energy's submittals and determined that a regulatory audit of the BSEP and HNP IEPRA, IFPRA, and FPRA models and overall 10 CFR 50.69 categorization process would assist in the timely completion of the subject LAR review process. An audit is determined to be the most efficient approach to ensure a timely resolution of issues associated with this LAR review. This audit should minimize the potential for multiple rounds of requests for additional information (RAls) and ensure no unnecessary burden will be imposed by requiring the licensee to address issues that are no longer necessary to make a safety determination.

2.0 REGULATORY AUDIT BASIS A regulatory audit is a planned license or regulation-related activity that includes the examination and evaluation of primarily non-docketed information. A regulatory audit is conducted with the intent to gain understanding, to verify information, and/or to identify information that will require docketing to support the basis of a licensing or regulatory decision.

Performing a regulatory audit of the licensee's information is expected to assist the staff in efficiently conducting its review or gain insights on the licensee's processes or procedures.

Information that the NRC staff relies upon to make the safety determination must be submitted on the docket. However, the NRC staff may review supporting information retained as records under 10 CFR 50. 71 and 10 CFR 54.37, which although not required to be submitted as part of the licensing action, would help the staff better understand the licensee's submitted information.

Enclosure

3.0 REGULATORY AUDIT SCOPE OR METHOD The audit will be performed consistent with the NRC's Office of Nuclear Reactor Regulation (NRR) Office Instruction LIC-111, "Regulatory Audits," dated December 16, 2008 (ADAMS Accession No. ML082900195). The purpose of this audit is to gain a more detailed understanding of Duke Energy's 10 CFR 50.69 categorization process by verifying conformance of categorization process with NRG-endorsed guidance and Duke Energy's implementation of the endorsed categorization process.

To accomplish these objectives, the NRC audit team will be:

  • validating PRA quality is adequate for use in the BSEP and HNP applications;
  • identifying new information that is needed in order for staff to reach a licensing or regulatory decision; and
  • discussing audit questions with Duke Energy.

Upon completion of the audit, the NRC audit team will determine its need for any RAls to ensure any information needed to make its regulatory determination is available on BSEP's and HNP's dockets. Audit questions will likely be sent prior to the audit.

4.0 INFORMATION AND OTHER MATERIAL NECESSARY FOR THE AUDIT The NRC audit team will require access to personnel knowledgeable in all aspects of Duke Energy's 10 CFR 50.69 applications for BSEP and HNP. At a minimum, a hard copy and electronic copy of the following documentation should be available to the audit team on the first day of the audit. In addition, presentations and specific discussion topics provided below may be requested.

Documents:

  • Internal events and fire PRA documentation should be available on a computer with licensee support
  • Internal events and fire PRA peer review reports and findings and observations (F&O) closure reports
  • Documentation of changes to the PRA models with justification of upgrades/updates
  • Documentation of preliminary categorization results, if available

Presentations:

  • 50.69 process presentation
  • Walk-through categorization results Discussions:
  • Discussions of audit questions related to:
a. F&Os
b. PRA updates/upgrades, focused-scope peer reviews and F&O closure 5.0 TEAM ASSIGNMENTS The audit will be conducted by NRC staff from NRR's Division of Risk Assessment, PRA Licensing, and NRC contractors from the Pacific Northwest National Laboratories (PNNL) in support of the technical audit team members. Staff knowledgeable in 10 CFR 50.69 and risk-informed licensing reviews will comprise the audit team. Observers at the audit may include NRR technical reviewers and project managers (PMs).

The NRC Audit Team Leader will be Leslie Fields (PM) with Michael Levine as the NRC BSEP Technical Lead, and Brandon Hartle as the NRC HNP Technical Lead. The audit team leader will conduct daily briefings on the status of the review and coordinate audit activities while on site. The tables below show (1) the audit milestones and schedule, and (2) the planned audit team composition and their assigned areas for review during the audit.

Regulatory Audit Plan Review Areas and Assignments BSEP/HNP Lead Support 1 Categorization Process Team NRC QA/Contractor 2 PRA Technical Adequacy M. Levine/B. Hartle S. Dinsmore/ PNNL 2.a Peer Reviews M. Levine/B. Hartle S. Dinsmore/ PNNL 2.b Facts and Observations M. Levine/B. Hartle S. Dinsmore/ PNNL 2.c PRA updates/upgrades M. Levine/B. Hartle S. Dinsmore/ PNNL 3 External Hazards M. Reisi-Fard/S Vasavada S. Dinsmore/ PNNL 4 Integrated Decision-making Panel M. Levine/B. Hartle S. Dinsmore/ PNNL 5 Documentation, Configuration Control, Quality L. Fields Team Audit Team Roster NRC Staff Title Leslie Fields NRC Team Leader Michael Levine NRC Brunswick Technical Lead Brandon Hartle NRC Harris Technical Lead Stephen Dinsmore NRCQA Mark Wilk PNNL Garill Coles PNNL

6.0 LOGISTICS The regulatory audit will begin the morning of July 17, 2018, and will last approximately 3 days, concluding on the afternoon of July 191h. The NRC staff will schedule a conference call prior to the audit to discuss the details of the generic audit plan. The dates in the milestone chart below are subject to change based on mutual agreement between the licensee and the NRC. An entrance meeting for this audit will be held on the first day at 9:00 a.m. and an exit meeting will be held the final day at 4:00 p.m. (earlier/later) based on a mutually agreed-upon time. The NRC audit team leader will provide daily progress briefings to licensee personnel on the first and second day of the audit.

The audit will take place at a location agreed upon by the licensee and NRC audit team leader where (1) the necessary reference material and (2) appropriate Duke Energy staff should be available to support the review. Visitor access will be requested for the entire audit team for the duration of the audit. We recommend that security paperwork and processing be handled prior to the first day of the audit, if possible.

Audit Milestones and Schedule Activity Time Frame Comments Logistics/Clarification Teleconference from NRC Headquarters to discuss July 12, 2018 Call logistics and any Duke Energy questions.

NRC staff will present a brief team introduction and Onsite Audit Kick-Off discuss the scope of the audit. The licensee should July 17, 2018 Meeting introduce team members and give logistics for the week.

Meet with licensee to provide a summary of any End of Day Summary July 17-18, 2018 significant findings and requests for additional Briefings assistance.

Provide Rooms for Facilitate discussions between site and staff Focused Topic July 17-18, 2018 technical areas. Provide 1-2 breakout areas, if Discussions possible, for smaller discussions.

Onsite Audit Exit NRC staff will hold a brief exit meeting, with July 19, 2018 Meeting licensee staff to conclude audit activities.

Audit Summary (see 90 days after exit To document the audit.

Section 8.0 below) 7.0 SPECIAL REQUESTS The regulatory audit team will require the following to support the regulatory audit:

  • Two computers with internet access and printing capability in the NRC room, access to the site portal, and wired or wireless guest internet access for all team members.
  • 1 main conference room with 1 additional private area for conference calling capability should be made available. The main NRC conference room should be set up for 6 to 8 NRC staff and contractors.
  • Access to licensee personnel knowledgeable in the categorization process, plant design, operation and the plant PRA. In addition, Duke Energy staff who participated in preparing the LAR submittal should be available for discussion.

8.0 DELIVERABLES A regulatory audit summary will be issued within 90 days of the completion of the audit. If information evaluated during the audit is needed to support a regulatory decision, the NRC staff will identify it in an RAI. The NRC staff will provide the RAI in separate docketed correspondence.