MONTHYEARIR 05000285/20230062023-12-21021 December 2023 NRC Inspection Report 05000285/2023006 IR 05000285/20230052023-11-0202 November 2023 NRC Inspection Room 05000285/2023005 IR 05000285/20230042023-09-13013 September 2023 NRC Inspection Report 05000285/2023-004 IR 05000285/20230032023-07-10010 July 2023 NRC Inspection Report 05000285/2023003 IR 05000285/20230022023-06-0505 June 2023 NRC Inspection Report 05000285/2023002 IR 05000285/20230012023-02-24024 February 2023 NRC Inspection Report 05000285/2023001 IR 05000285/20220062023-01-0505 January 2023 NRC Inspection Report 05000285/2022-006 IR 05000285/20220052022-10-26026 October 2022 NRC Inspection Report 05000285/2022-005 IR 05000285/20220042022-09-14014 September 2022 NRC Inspection Report 05000285/2022004 IR 05000285/20220032022-06-15015 June 2022 NRC Inspection Report 05000285/2022003 IR 05000285/20220022022-04-28028 April 2022 NRC Inspection Report 050-00285/2022-002 IR 05000285/20220012022-02-25025 February 2022 NRC Inspection Report 050-00285/2022-001 IR 05000285/20210042021-11-18018 November 2021 NRC Inspection Report 050-00285/2021-004 IR 05000285/20210032021-08-11011 August 2021 NRC Inspection Report 050-00285/2021-003 (Public) IR 05000285/20210022021-05-0707 May 2021 NRC Inspection Report 05000285/2021002 IR 05000285/20210012021-02-17017 February 2021 NRC Inspection Report 05000285/2021001 IR 07200054/20204012020-10-29029 October 2020 Independent Spent Fuel Storage Installation Physical Security Requirements for Independent Spent Fuel Storage Installations Inspection Report 07200054/2020401 IR 05000285/20200022020-09-22022 September 2020 NRC Inspection Report 05000285/2020002 IR 05000285/20190052020-03-12012 March 2020 Independent Spent Fuel Storage Installation (ISFSI) - NRC Inspection Report 050-00285/2019-005 and 072-00054/2019-001 IR 05000206/20190042020-02-20020 February 2020 Independent Spent Fuel Storage Installation (ISFSI) - NRC Inspection Report 05000206/2019 004; 05000361/2019 007; 05000362/2019 007; and 07200054/2019-002 IR 05000285/20190042019-11-26026 November 2019 Inspection Report 050-00285/2019-004 IR 05000285/20190032019-09-13013 September 2019 NRC Inspection Report 050-00285/2019-003 IR 05000285/20190022019-07-23023 July 2019 NRC Inspection Report 05000285/2019002 IR 05000285/20194042019-07-11011 July 2019 NRC Security Baseline Inspection Report 05000285/2019404 IR 05000285/20194032019-06-0404 June 2019 NRC Security Baseline Inspection Report 05000285/2019403 IR 05000285/20190012019-02-12012 February 2019 NRC Inspection Report 050-00285/2019-001 IR 05000285/20180042018-11-19019 November 2018 Omaha Public Power District; Fort Calhoun Station - NRC Inspection Report 05000285/2018-004 IR 05000285/20180032018-09-27027 September 2018 NRC Inspection Report 05000285/2018003 IR 05000285/20184032018-05-17017 May 2018 NRC Physical Security Inspection Report 05000285/2018403 IR 05000285/20184102018-05-17017 May 2018 NRC Security Baseline Inspection Report 05000285/2018410 IR 05000285/20180012018-04-13013 April 2018 NRC Inspection Report 05000285/2018001 IR 05000285/20174032018-04-10010 April 2018 Cancellation of NRC Inspection Report 05000285/2017403 IR 05000285/20170112018-02-0101 February 2018 NRC Inspection Report 05000285/2017-011 IR 05000285/20170022017-11-0909 November 2017 NRC Inspection Reports 05000285/2017002 Through 05000285/2017007 IR 05000285/20170122017-11-0808 November 2017 NRC Inspection Report 05000285/2017-012 IR 05000285/20160062017-09-18018 September 2017 NRC Inspection Report 05000285/2016006 IR 05000285/20170092017-08-0404 August 2017 NRC Inspection Report 05000285/2017-009 IR 05000285/20174062017-06-26026 June 2017 NRC Security Baseline Inspection Report 05000285/2017406 IR 05000285/20174052017-06-26026 June 2017 NRC Security Inspection Report 05000285/2017405 and NRC Investigation Report 4-2015-030 IR 05000285/20170102017-06-15015 June 2017 Independent Spent Fuel Storage Installation Inspection Report 05000285/2017010 and 07200054/2017001 IR 05000285/20170012017-05-0808 May 2017 NRC Inspection Report 05000285/2017001 and 05000285/2017008 IR 05000285/20160042017-01-18018 January 2017 NRC Integrated Inspection Report 05000285/2016004 IR 05000285/20165012017-01-17017 January 2017 NRC Emergency Preparedness Annual Inspection Report 05000285/2016501 IR 05000285/20160032016-11-0808 November 2016 NRC Integrated Inspection Report Number 05000285/2016003 IR 05000285/20164042016-10-28028 October 2016 NRC Security Baseline Inspection Report 05000285/2016404 IR 05000285/20160082016-09-22022 September 2016 NRC Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications Baseline Inspection Report 05000285/2016008 IR 05000285/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for Fort Calhoun Station (Report 05000285/2016005) IR 05000285/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for Calhoun Station (NRC Physical Security Inspection Report Number 05000285/2016401) ML16237A0382016-08-31031 August 2016 Mid-Cycle Assessment Letter for Fort Calhoun Station (Report 05000285/2016005) IR 05000285/20160022016-08-0505 August 2016 NRC Integrated Inspection Report 05000285/2016002, April 1, 2016 Through June 30, 2016 2023-09-13
[Table view] Category:Letter
MONTHYEARML24019A1672024-01-31031 January 2024 Issuance of Amendment to Renewed Facility License to Add License Condition to Include License Termination Plan Requirements IR 05000285/20230062023-12-21021 December 2023 NRC Inspection Report 05000285/2023006 LIC-23-0007, Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements Request for Additional Information2023-12-0606 December 2023 Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements Request for Additional Information IR 05000285/20230052023-11-0202 November 2023 NRC Inspection Room 05000285/2023005 ML23276A0042023-09-28028 September 2023 U.S. EPA Response Letter to NRC Letter on Consultation and Finality on Decommissioning and Decontamination of Contaminated Sites MOU - Fort Calhoun Station, Unit 1 (License No. DPR-40, Docket No. 50-285) IR 05000285/20230042023-09-13013 September 2023 NRC Inspection Report 05000285/2023-004 LIC-23-0005, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 20232023-08-24024 August 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 ML23234A2412023-08-18018 August 2023 Email - Letter to M Porath Re Ft Calhoun Unit 1 LTP EA Section 7 Informal Consultation Request ML23234A2392023-08-18018 August 2023 Letter to B Harisis Re Ft Calhoun Unit 1 LTP EA State of Nebraska Comment Request.Pdf IR 05000285/20230032023-07-10010 July 2023 NRC Inspection Report 05000285/2023003 ML23082A2202023-06-26026 June 2023 Consultation on the Decommissioning of the Fort Calhoun Station Unit 1 Pressurized Water Reactor in Fort Calhoun, Nebraska ML23151A0032023-06-0505 June 2023 Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 IR 05000285/20230022023-06-0505 June 2023 NRC Inspection Report 05000285/2023002 LIC-23-0004, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2023-04-20020 April 2023 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-23-0003, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2023-03-15015 March 2023 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-23-0001, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information2023-02-27027 February 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information IR 05000285/20230012023-02-24024 February 2023 NRC Inspection Report 05000285/2023001 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities LIC-23-0002, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2023-02-20020 February 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report ML23020A0462023-01-19019 January 2023 Threatened and Endangered Species List: Nebraska Ecological Services Field Office IR 05000285/20220062023-01-0505 January 2023 NRC Inspection Report 05000285/2022-006 ML22357A0662022-12-30030 December 2022 Technical RAI Submittal Letter on License Amendment Request for Approval of License Termination Plan IR 05000285/20220052022-10-26026 October 2022 NRC Inspection Report 05000285/2022-005 ML22276A1052022-09-30030 September 2022 Conclusion of Consultation Under Section 106 NHPA for Ft. Calhoun Station LTP ML22258A2732022-09-29029 September 2022 Letter to John Swigart, Shpo; Re., Conclusion of Consultation Under Section 106 Hnpa Fort Calhoun Station Unit 1 ML22265A0262022-09-26026 September 2022 U.S. Nuclear Regulatory Commission'S Analysis of Omaha Public Power District'S Decommissioning Status Report (License No. DPR-40, Docket No. 50-285) IR 05000285/20220042022-09-14014 September 2022 NRC Inspection Report 05000285/2022004 ML22138A1252022-08-0303 August 2022 Letter to Mr. Timothy Rhodd, Chairperson, Iowa Tribe of Kansas and Nebraska, Re., Ft Calhoun LTP Section 106 ML22138A1262022-08-0303 August 2022 Letter to Roger Trudell, Chairman, Santee Sioux Nation, Nebraska, Re., Ft Calhoun LTP Section 106 ML22101A1092022-08-0303 August 2022 Letter to Mr. Durell Cooper, Chairman, Apache Tribe of Oklahoma; Re., Ft Calhoun LTP Section 106 ML22138A1242022-08-0303 August 2022 Letter to Mr. Reggie Wassana, Governor, Cheyenne and Arapaho Tribes, Oklahoma, Re., Ft Calhoun LTP Section 106 ML22138A1292022-08-0303 August 2022 Letter to Tiauna Carnes, Chairperson, Sac and Fox Nation of Missouri in Kansas, Re., Ft Calhoun LTP Section 106 ML22138A1212022-08-0303 August 2022 Letter to Mr. Edgar Kent, Chairman, Iowa Tribe of Oklahoma, Re., Ft Calhoun LTP Section 106 ML22138A1282022-08-0303 August 2022 Letter to Victoria Kitcheyan, Chairwoman, Winnebago Tribe of Nebraska, Re., Ft Calhoun LTP Section 106 ML22138A1232022-08-0303 August 2022 Letter to Mr. Leander Merrick, Chairperson, Omaha Tribe of Nebraska, Re., Ft Calhoun LTP Section 106 ML22138A1222022-08-0303 August 2022 Letter to Mr. John Shotton, Chairman, Otoe-Missouria Tribe of Indians, Oklahoma, Re., Ft Calhoun LTP Section 106 ML22138A1272022-08-0303 August 2022 Letter to Vern Jefferson, Chairman, Sac and Fox Tribe of the Mississippi in Iowa, Re., Ft Calhoun LTP Section 106 ML22214A0922022-08-0303 August 2022 Letter to Stacy Laravie, Thpo, Ponca Tribe of Nebraska, Re., Ft Calhoun LTP Section 106 ML22138A1302022-08-0303 August 2022 Letter to Justin Wood, Principal Chief, Sac and Fox Nation, Oklahoma, Re., Ft Calhoun LTP Section 106 ML22159A2152022-06-28028 June 2022 Letter Forwarding FRN on Public Meeting and Request for Comment on License Termination Plan LIC-22-0010, Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information2022-06-15015 June 2022 Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information IR 05000285/20220032022-06-15015 June 2022 NRC Inspection Report 05000285/2022003 ML22119A2472022-05-0303 May 2022 Review of Amendment Request to Add a LC to Include LTP Requirements, RAI for Environmental Review IR 05000285/20220022022-04-28028 April 2022 NRC Inspection Report 050-00285/2022-002 LIC-22-0005, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2022-04-20020 April 2022 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-22-0009, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2022-03-30030 March 2022 Annual Decommissioning Funding / Irradiated Fuel Management Status Report 2024-01-31
[Table view] |
Text
October 29, 2020
SUBJECT:
FORT CALHOUN STATION - INDEPENDENT SPENT FUEL STORAGE INSTALLATION, PHYSICAL SECURITY REQUIREMENTS FOR INDEPENDENT SPENT FUEL STORAGE INSTALLATIONS INSPECTION REPORT 07200054/2020401
Dear Ms. Fisher:
On October 8, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Fort Calhoun Station independent spent fuel storage facility. The NRC inspector discussed the results of this inspection with Mr. T. Uehling, Sr., Director Decommissioning, and other members of your staff. The results of this inspection are documented in the enclosed report.
No violations of significance were noted and no response to this letter is required.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's
"Rules of Practice and Procedure," a copy of this letter, its enclosure and your response, if you choose to provide one, will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). To the extent possible, your response, if you choose to provide one, should not include any security related, personal privacy, or proprietary information so that it can be made available to the public without redaction.
Sincerely, Ray L. Digitally signed by Ray L. Kellar Kellar Date: 2020.10.29 14:51:13 -05'00'
Ray L. Kellar, P.E., Chief Plant Support Branch 1 Division of Reactor Safety Docket No. 07200054
Enclosure:
As stated
Inspection Report
Docket Number: 07200054 License Number: DPR-40 Report Number: 07200054/2020401 Enterprise Identifier: I-2020-401-0007 Licensee: Omaha Public Power District Facility: Fort Calhoun Station Location: Blair, NE Inspection Dates: October 5, 2020 to October 8, 2020 Inspectors: D. Holman, Senior Physical Security Inspector Approved By: Ray L. Kellar, P.E., Chief Plant Support Branch 1 Division of Reactor Safety Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Baseline Security Inspection at the Fort Calhoun Station, in accordance with Inspection Procedure 81311, Physical Security Requirements for Independent Spent Fuel Storage Installations.
List of Violations No violations of more than minor significance were identified.
INSPECTION SCOPES
Inspections were conducted using Inspection Procedure 81311, Physical Security Requirements for Independent Spent Fuel Storage Installations, and review of general license requirements contained in the approved safety evaluation report (SER), the approved physical security plan (PSP), and applicable ISFSI security orders. The inspector reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
81311 - Physical Security Requirements for Independent Spent Fuel Storage Installations 1. Inspection Scope
- The inspector verified that spent nuclear fuel (SNF) is stored only within a protected area (PA). (72.212(9))
- The inspector verified that only individuals who are authorized to enter the PA are granted access to the PA. (72.212(9), SER/PSP)
- The inspector verified that the licensee is in compliance with site-specific security orders (e.g., additional security measures) for access authorization and fingerprinting; and that a log of authorized individuals is maintained. (SER/PSP)
- The inspector verified that the licensee can detect and assess penetrations through the isolation zone. (72.212(9))
- The inspector verified that the licensee can provide timely communication to the designated response force whenever necessary. (72.212(9), SER/PSP)
- The inspector verified that the physical protection system is designed to protect against loss of control of the facility that could be sufficient to cause a radiation exposure exceeding the dose described in 10 CFR 72.106(b). (SER/PSP)
- The inspector verified that the licensee has retained a copy of the physical protection plan for a period of three years or until termination of the license. (72.212(9), SER/PSP)
- The inspector verified that the licensee complies with the provisions for physical protection systems, components, and procedures that meet the performance capabilities of 72.212(9), the SER, and the PSP.
- The inspector verified that the licensees SNF and high-level radioactive waste are stored only within a PA so that access to this material requires passage through or penetration of two physical barriers. One barrier at the perimeter of the PA and one barrier offering substantial penetration resistance. (SER/PSP)
- The inspector verified that the licensee provides illumination sufficient to permit adequate assessment of unauthorized penetrations of or activities within the PA. (72.212(9), SER/PSP)
- The inspector verified that the licensees perimeter of the PA allows for continual surveillance and is protected by an active intrusion alarm system that is capable of detecting penetrations through the isolation zone and that is monitored in a continually staffed primary alarm station and in one additional continually staffed location. (72.212(9), SER/PSP)
- The inspector verified that the primary alarm station is located within the PA, that it has bullet-resisting walls, doors, ceiling and floor; and the interior of the station is not be visible from outside the PA. A timely means for assessment of alarms is provided. The redundant alarm monitoring location provides a summary indication that an alarm has been generated. (SER/PSP)
- The inspector verified the licensees PA is monitored by daily random patrols. (72.212(9), SER/PSP)
- The inspector verified that the licensees security organization has written procedures that provide for sufficient personnel per shift to ensure the monitoring of detection systems and the conduct of surveillance, assessment, access control, and communications to assure adequate response. The inspector verified that members of the security organization are trained, equipped, qualified, and requalified to perform assigned job duties in accordance with the approved Training and Qualification Plan. (72.212(9), SER/PSP)
- The inspector verified that the licensee has documented liaison with a designated response force or local law enforcement agency (LLEA) to permit a timely response to unauthorized penetration or activities. (72.212(9), SER/PSP)
- The inspector verified that the licensee has a personnel identification system and a controlled lock system that limits access to only authorized individuals. (72.212(9),
SER/PSP)
- The inspector verified that the licensee has redundant communications capability between onsite security force members and designated response force or LLEA. (72.212(9), SER/PSP)
- The inspector verified that all licensee individuals, vehicles, and hand-carried packages entering the PA must be checked for proper authorization and visually searched for explosives before entry. (72.212(9), SER/PSP)
- The inspector verified that the licensees written response procedures have been established and maintained for addressing unauthorized penetration of or activities within, the PA. (72.212(9), SER/PSP)
- The inspector verified that all the licensees detection systems and supporting subsystems include a tamper indicating system with line supervision. The system, as well as surveillance/assessment and illumination systems, must be maintained in operable condition. (72.212(b)(9))
- The inspector verified that the licensees physical protection program is reviewed once every 24 months by individuals independent of both physical protection program management and personnel who have direct responsibility for implementation of the physical protection program. The physical protection program review must include an evaluation of the effectiveness of the physical protection system and a verification of the liaison established with the designated response force or LLEA. (72.212(9), SER/PSP)
- The inspector verified that the licensee has retained the following documentation as a record for three years after the record is made or until termination of the license. Any duplicate records required under 10 CFR 72.180 and 10 CFR 73.71 of this part need not be retained under the requirements of this section: a log of individuals granted access to the PA; screening records of members of the security organization; a log of all patrols; a record of each alarm received, identifying the type of alarm, location, date and time when received, and disposition of the alarm; and the physical protection program review reports. (72.212(9), SER/PSP)
- The inspector verified that, in accordance with any applicable security requirements and/or security orders, the licensee has implemented measure and process for vehicle control measures into protected areas. (72.212(9), SER/PSP)
- The inspector verified that, in accordance with any applicable security requirements and/or security orders, the licensee has implemented an insider mitigation program.
(SER/PSP)
- The inspector verified that the licensee has developed offsite response coordination with LLEA as applicable to physical security requirements and/or security orders. (72.212(9),
SER/PSP)
INSPECTION RESULTS
No violations were identified.
EXIT MEETINGS AND DEBRIEFS
The inspector verified no proprietary information was retained or documented in this report.
- On October 8, 2020, the inspector presented the security baseline inspection results to Mr. T. Uehling, Sr., Director Decommissioning, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
81311 Corrective Action CR 2020-00567, 2020-00569, 2020-00570, 2020-00571
Documents
Resulting from
Inspection
Miscellaneous Lesson ID: 1108 Use of Force Continuum 3/31/20
Lesson ID: 2106 Security Respirator Training, Escape Hood 3/13/20
NRC Order EA- ISFSI Order For Interim Safeguards and Security 2004
04-185 Compensatory Measures
NRC Order EA- ISFSI Order For Implementation of Additional Security 2004
04-187 Measures Associated With Access Authorization
Plan Physical Security Plan, Training Plan, Contingency Plan Revision 0
SER NRC Security Evaluation Report; L-2019-LLA-0058 2019
Docket No. 50-285 and 72-054
Procedures 6 OPPD Corporate Central Station Remote Monitoring Station - Version 1
FCS ISFSI CAS
FCSI-SY-101 ISFSI Personnel Access Control Revision 1
FCSI-SY-102 ISFSI Vehicle Control Revision 1
FCSI-SY-103 Security Patrols Revision 1
FCSI-SY-110 Access Authorization Program Revision 1
FCSI-SY-112 Lock and Key Control Revision 0
FCSI-SY-116 ISFSI Communications Revision 1
FCSI-SY-117 Testing and Maintenance of Security Equipment Revision 1
FCSI-SY-200 Control/Classification of Safeguards Information ... Revision 1
Work Orders PS GAT/VB/MOD Perform Monthly Maintenance
PM4
6