|
---|
Category:Environmental Assessment
MONTHYEARML11313A1632012-02-0606 February 2012 Federal Register Notice, Environmental Assessment and Finding of No Significant Impact ML11313A1622012-02-0606 February 2012 Environmental Assessment and Finding of No Significant Impact ML0935706362010-01-14014 January 2010 FRN: General Notice. Shearon Harris Nuclear Power Plant, Unit 1 - Environmental Assessment and Finding of No Significant Impact ML0935706092010-01-14014 January 2010 Environmental Assessment and Finding of No Significant Impact 2012-02-06
[Table view] Category:Federal Register Notice
MONTHYEARML24170A7312024-07-29029 July 2024 – Exemption from the Requirements of 10 CFR 50.55a(H)(2) Using the Risk-Informed Process for Evaluations Letter ML24170A7342024-07-26026 July 2024 – Exemption from the Requirements of 10 CFR 50.55a(H)(2) Using the Risk-Informed Process for Evaluations ML24170A7352024-07-26026 July 2024 – FRN Exemption from the Requirements of 10 CFR 50.55a(H)(2) Using the Risk-Informed Process for Evaluations ML24067A0372024-03-20020 March 2024 Federal Register Notice - Issuance of Multiple Exemptions Regarding 10 CFR Part 73 - February 2024 ML20177A6452020-07-15015 July 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for June 2020 ML20071F7222020-03-24024 March 2020 Gaia Fuel LAR NSHC FRN with SUNSI or SUNSI and SGI ML20079L2702020-03-18018 March 2020 Notice of Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing and Order Imposing Procedures ML19238A3692019-09-0303 September 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 09/10/2019 ML19168A0842019-06-26026 June 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 07/02/2019 ML18295A7442018-10-25025 October 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 11/06/18 ML18278A2802018-10-10010 October 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 10/23/2018 NRC-2018-0140, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/20182018-07-0505 July 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/2018 ML18180A2182018-07-0505 July 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/2018 NRC-2018-0096, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 20182018-05-14014 May 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 2018 ML18127B7232018-05-14014 May 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 2018 NRC-2017-0238, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 2, 20182017-12-21021 December 2017 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 2, 2018 ML17353A1922017-12-21021 December 2017 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 2, 2018 ML16271A0922016-09-28028 September 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: October 11, 2016 ML16215A2272016-08-0303 August 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 16, 2016 NRC-2016-0161, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 16, 20162016-08-0303 August 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 16, 2016 ML16187A2232016-07-18018 July 2016 Federal Register Notice on Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Au NRC-2016-0143, Federal Register Notice on Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing SUNSI and Order Imposing Procedures for Access to SUNSI2016-07-18018 July 2016 Federal Register Notice on Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Au ML16173A0572016-07-11011 July 2016 Notice of Consideration of Issuance of Amendment to Facility Operating License, No Significant Hazards Consideration Determination, Opportunity for Hearing & Order Imposing Procedures for Document Access to Sensitive Unclassified Non-Safeguards Info ML15356A5992015-12-29029 December 2015 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 5, 2016 ML15328A5502015-11-27027 November 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: December 8, 2015 NRC-2015-0269, Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: December 8, 20152015-11-27027 November 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: December 8, 2015 ML15218A6252015-08-14014 August 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 14, 2015 NRC-2015-0165, Application and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing Sensitive Unclassified Non-Safeguards Information and Order Imposing Procedures for2015-07-23023 July 2015 Application and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing Sensitive Unclassified Non-Safeguards Information and Order Imposing Procedures for Acce ML15188A1632015-07-23023 July 2015 Application and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing Sensitive Unclassified Non-Safeguards Information and Order Imposing Procedures for Acce ML15159A6322015-07-0606 July 2015 Letter Approving Direct Transfer of Control of Licenses and Conforming Amendments ML15042A2322015-04-13013 April 2015 Notice of Consideration of Approval of Transfer of Facility Operating License and Conforming Amendment, Opportunity for Hearing ML15022A6532015-01-26026 January 2015 Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: February 3, 2015 ML14233A2082014-08-22022 August 2014 Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 2, 2014 NRC-2014-0193, Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 2, 20142014-08-22022 August 2014 Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 2, 2014 ML14099A2172014-04-28028 April 2014 FRN on Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing SUNSI and Order Imposing Procedures for Access to SUNSI ML13225A5572013-08-12012 August 2013 Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit ML13164A2012013-06-13013 June 2013 Correction to Bi-weekly Notice ML12056A0442012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status NRC-2012-0067, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status2012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status ML12025A1622012-02-24024 February 2012 Federal Register Notice - Exemption Regarding Use of M5 Alloy Fuel Rod Cladding NRC-2012-0034, Federal Register Notice - Exemption Regarding Use of M5 Alloy Fuel Rod Cladding2012-02-24024 February 2012 Federal Register Notice - Exemption Regarding Use of M5 Alloy Fuel Rod Cladding ML11313A1622012-02-0606 February 2012 Environmental Assessment and Finding of No Significant Impact ML11313A1632012-02-0606 February 2012 Federal Register Notice, Environmental Assessment and Finding of No Significant Impact ML11255A0572011-12-0202 December 2011 Federal Register Notice - Order Approving Indirect License Transfer NRC-2011-0283, Federal Register Notice - Order Approving Indirect License Transfer2011-12-0202 December 2011 Federal Register Notice - Order Approving Indirect License Transfer NRC-2011-0200, Federal Register Notice - Notice of Consideration2011-08-22022 August 2011 Federal Register Notice - Notice of Consideration ML11221A3772011-08-22022 August 2011 Federal Register Notice - Notice of Consideration ML1122302752011-08-11011 August 2011 Biweekly Sholly Report - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations; Fr Publication Date: 8/23/2011 NRC-2011-0187, Biweekly Sholly Report - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations; Fr Publication Date: 8/23/20112011-08-11011 August 2011 Biweekly Sholly Report - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations; Fr Publication Date: 8/23/2011 NRC-2011-0093, Federal Register Notice, Notice of Withdrawal of Application2011-04-20020 April 2011 Federal Register Notice, Notice of Withdrawal of Application 2024-07-29
[Table view] Category:Finding of No Significant Impact
MONTHYEARML11313A1632012-02-0606 February 2012 Federal Register Notice, Environmental Assessment and Finding of No Significant Impact ML0935706362010-01-14014 January 2010 FRN: General Notice. Shearon Harris Nuclear Power Plant, Unit 1 - Environmental Assessment and Finding of No Significant Impact ML0935706092010-01-14014 January 2010 Environmental Assessment and Finding of No Significant Impact 2012-02-06
[Table view] Category:Letter
MONTHYEARML24290A1102024-10-24024 October 2024 Notification of Licensed Operator Initial Examination 05000400/2025301 05000400/LER-2024-001-01, Automatic Reactor Trip Due to Main Generator Lock-Out2024-10-23023 October 2024 Automatic Reactor Trip Due to Main Generator Lock-Out IR 05000400/20240112024-09-10010 September 2024 NRC Inspection Report 05000400/2024011 IR 05000400/20240052024-08-26026 August 2024 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400-2024005) Rev 1 ML24059A4252024-08-14014 August 2024 Issuance of Amendment No. 202 Regarding Alignment of Certain Technical Specifications with Improved Standard Technical Specifications ML24213A0522024-08-0202 August 2024 Issuance of Amendment No. 201 to Extend Completion Time of Inoperable Reactor Coolant System Accumulator Using Consolidated Line Item Improvement Process ML24212A3412024-07-31031 July 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24170A7312024-07-29029 July 2024 – Exemption from the Requirements of 10 CFR 50.55a(H)(2) Using the Risk-Informed Process for Evaluations Letter IR 05000400/20240022024-07-29029 July 2024 – Integrated Inspection Report 05000400/2024002 05000400/LER-2024-001, Automatic Reactor Trip Due to Main Generator Lock-Out2024-07-22022 July 2024 Automatic Reactor Trip Due to Main Generator Lock-Out ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000400/20243022024-06-27027 June 2024 – NRC Operator Licensing Examination Approval 05000400/2024302 IR 05000400/20244012024-06-25025 June 2024 – Security Baseline Inspection Report05000400/2024401 ML24162A1372024-06-24024 June 2024 – Regulatory Audit Summary Related to the Review of Exemption Request from Certain Requirements in 10 CFR 50.55a(h)(2)(EPID L-2024-LLE-00040) ML24136A1382024-05-20020 May 2024 – Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000400/2024011) and Request for Information (RFI) ML24116A2592024-05-14014 May 2024 Staff Evaluation Related to Aging Management Plan and Inspection Plan for Reactor Vessel Internals ML24127A1592024-05-0808 May 2024 – Notification of Licensed Operator Initial Examination 05000400/2024302 IR 05000400/20240012024-05-0505 May 2024 Integrated Inspection Report 05000400/2024001 ML24100A0912024-04-10010 April 2024 Operator License Examination Report ML24058A2462024-03-18018 March 2024 – Supplemental Information Needed for Using the Risk-Informed Process for Evaluations for the Request for Exemption from Certain Requirements in 10 CFR 50.55a(h)(2) IR 05000400/20230062024-02-28028 February 2024 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2023006 ML24032A2632024-02-23023 February 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0044 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000400/20243012024-02-21021 February 2024 – NRC Operator Licensing Examination Approval 05000400/2024301 IR 05000400/20230042024-01-30030 January 2024 Integrated Inspection Report 05000400/2023004 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230032023-11-0909 November 2023 Integrated Inspection Report 05000400/2023003 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23234A1702023-10-0303 October 2023 Issuance of Amendment No. 199 Regarding Administrative Changes to the Renewed Facility Operating License and Technical Specifications ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230052023-08-23023 August 2023 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005) ML23234A2542023-08-22022 August 2023 RQ Inspection Notification Letter IR 05000400/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000400/2023402 IR 05000400/20230022023-07-24024 July 2023 Integrated Inspection Report 05000400/2023002 IR 05000400/20234402023-07-17017 July 2023 Special Inspection Report 05000400/2023440 and Preliminary Greater than Green Finding and Apparent Violation Cover Letter IR 05000400/20230012023-05-10010 May 2023 Integrated Inspection Report 05000400 2023001 IR 05000400/20234042023-05-0404 May 2023 Cyber Security Inspection Report 05000400/2023404 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23118A1392023-04-28028 April 2023 Submittal of Updated Final Safety Analysis Report (Amendment 65), Technical Specification Bases Revision, Report of Changes Pursuant to 10 CFR 50.59 and Summary of Commitment Changes IR 05000400/20234032023-04-0505 April 2023 Security Baseline Inspection Report 05000400/2023403 IR 05000400/20230102023-03-15015 March 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000400/2023010 ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000400/20220062023-03-0101 March 2023 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2022006 ML23033A5272023-02-0808 February 2023 Correction of Typographical Errors Incurred During Issuance of License Amendment No. 196 IR 05000400/20220042023-02-0707 February 2023 Integrated Inspection Report 05000400/2022004 ML23020A1252023-01-23023 January 2023 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000400/2023403) ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 IR 05000400/20220032022-11-10010 November 2022 Integrated Inspection Report 05000400/2022003 IR 05000400/20223012022-11-0202 November 2022 NRC Operator License Examination Report 05000400/2022301 2024-09-10
[Table view] |
Text
UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 January 14, 2010 Chris L. Burton, Vice President Shearon Harris Nuclear Power Plant Carolina Power & Light Company Post Office Box 165, Mail Zone 1 New Hill, North Carolina 27562-0165 SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1 -ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT (TAC NO. ME2827)
Dear Mr. Burton:
Enclosed is a copy of the Environmental Assessment and Finding of No Significant Impact related to your application for exemption dated November 30, 2009, as supplemented by letter dated December 16, 2009. The proposed exemption from specific requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 73, for the Shearon Harris Nuclear Power Plant, Unit 1, would extend the deadline from March 31, 2010, until 30, 2010, and December 15, 2010, for the implementation of certain measures in 10 CFR Part 73. The assessment is being forwarded to the Office of the Federal Register for publication.
vg Marlayna Vaaler. Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-400
Enclosure:
Environmental Assessment cc w/enclosure:
Distribution via ListServ 7590-01-P NUCLEAR REGULATORY COMMISSION CAROLINA POWER & LIGHT COMPANY SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1 DOCKET NO. 50-400 ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT The U.S. Nuclear Regulatory Commission (NRC) is considering issuance of an exemption, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 73.5, "Specific Exemptions," from the implementation date for certain new requirements of 10 CFR Part 73, "Physical Protection of Plants and Materials," for Renewed Facility Operating License No. NPF-63, issued to Carolina Power & Light Company (the licensee), now doing business as Progress Energy Carolinas, Inc. (PEC), for operation of the Shearon Harris Nuclear Power Plant, Unit 1 (HNP), located in New Hill, North Carolina.
In accordance with 10 CFR 51.21, "Criteria for and identification of licensing and regulatory actions requiring environmental assessments," the NRC prepared an environmental assessment documenting its finding. The NRC concluded that the proposed actions will have no significant environmental impact. ENVIRONMENTAL ASSESSMENT Identification of the Proposed Action: The proposed action would exempt HNP from the required implementation date of March 31, 2010, for several new requirements of 10 CFR Part 73. Specifically, HNP would be granted an exemption from being in full compliance with certain new requirements contained in 10 CFR 73.55, "Requirements for physical protection of licensed activities in nuclear power reactors against radiological sabotage," by the March 31, 2010, deadline.
PEC has proposed
-2 an alternate full compliance implementation date of July 30, 2010, for one requirement, and December 15, 2010, for two other requirements, which is approximately four months and eight and a half months, respectively, beyond the date required by 10 CFR Part 73. The proposed action, an extension of the schedule for completion of certain actions required by the revised 10 CFR Part 73, does not involve any physical changes to the reactor, fuel, plant structures, support structures, water, or land at the HNP site. The proposed action is in accordance with the licensee's application dated November 30, 2009, as supplemented by letter dated December 16, 2009. The Need for the Proposed Action: The proposed action is needed to provide the licensee with additional time to perform the required upgrades to the HNP security system due to the need to design, resource, construct, and test three significant physical modifications to the current site security configuration, as well as other factors. Environmental Impacts of the Proposed Action: The NRC has completed its environmental assessment of the proposed exemption.
The staff has concluded that the proposed action to extend the implementation deadline would not significantly affect plant safety and would not have a significant adverse effect on the probability of an accident occurring.
The proposed action would not result in an increased radiological hazard beyond those previously analyzed in the environmental assessment and finding of no significant impact made by the Commission in promulgating its revisions to 10 CFR Part 73 as discussed in a Federal Register (FR) notice dated March 27, 2009 (74 FR 13967). There will be no change to radioactive effluents that affect radiation exposures to plant workers and members of the public. Therefore, no changes or different types of radiological impacts are expected as a result of the proposed exemption.
-3 The proposed action does not result in changes to land use or water use, or result in changes to the quality or quantity of non-radiological effluents.
No changes to the National Pollution Discharge Elimination System permit are needed. No effects on the aquatic or terrestrial habitat in the vicinity of the plant, or to threatened, endangered, or protected species under the Endangered Species Act, or impacts to essential fish habitat covered by the Magnuson-Steven's Act are expected.
There are no impacts to the air or ambient air quality. There are no impacts to historical and cultural resources.
There would be no impact to socioeconomic resources.
Therefore, no changes to or different types of non-radiological environmental impacts are expected as a result of the proposed exemption.
Accordingly, the NRC concludes that there are no significant environmental impacts associated with the proposed action. In addition, in promulgating its revisions to 10 CFR Part 73, the Commission prepared an environmental assessment and published a finding of no significant impact (Part 73, Power Reactor Security Requirements, 74 FR 13926 through 13967, dated March 27,2009).
The NRC staff's safety evaluation will be provided in the exemption that will be issued as part of the letter to the licensee approving the exemption to the regulation, if granted. Environmental Impacts of the Alternatives to the Proposed Action: As an alternative to the proposed actions, the NRC staff considered denial of the proposed actions (I.e., the "no-action" alternative).
If the proposed action was denied, the licensee would have to comply with the March 31, 2010, implementation deadline.
Denial of the exemption request would result in no change in current environmental impacts. Therefore, the environmental impacts of the proposed exemption and the "no action" alternative are similar.
-4 Alternative Use of Resources:
The action does not involve the use of any different resources than those considered in the Final Environmental Statement for HNP, NUREG-0972, dated October 31, 1983, as supplemented through the "Generic Environmental Impact Statement for License Renewal of Nuclear Plants: Regarding Shearon Harris Nuclear Power Plant, Unit 1 -Final Report (NUREG-1437, Supplement 33)." Agencies and Persons Consulted:
In accordance with its stated policy, on December 18, 2009, the NRC staff consulted with the North Carolina State official, Ms. Beverly Hall of the Division of Radiation Protection, with the North Carolina Department of Environment and Natural Resources, regarding the environmental impact of the proposed action. The State official had no comments.
FINDING OF NO SIGNIFICANT IMPACT On the basis of the environmental assessment, the NRC concludes that the proposed action will not have a significant effect on the quality of the human environment.
Accordingly, the NRC has determined not to prepare an environmental impact statement for the proposed action. For further details with respect to the proposed action, see the licensee's letter dated November 30,2009, as supplemented by letter dated December 16, 2009. Attachment 1 to the licensee's November 30, 2009, letter, as well as the December 16, 2009, letter in its entirety contain security-related information and, accordingly, are not available to the public. Other parts of these documents may be examined, and/or copied for a fee, at the NRC's Public Document Room (PDR), located at One White Flint North, Public File Area 0-1 F21, 11555 Rockville Pike (first floor), Rockville, Maryland 20852. Publicly available records will be accessible electronically from the Agencywide Document Access and Management System (ADAMS)
-5 Public Electronic Reading Room on the Internet at the NRC Website: http://www.nrc.gov/reading-rm/adams.html.
Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS should contact the NRC PDR Reference staff by telephone at 1-800-397-4209 or 301-415-4737, or send an e-mail to pdr.resource@nrc.gov.
Dated at Rockville, Maryland, this 14th day of January 2010. FOR REGULATORY CO ISSION Marlayna Vaaler, Project Manager Plant Licensing Branch 2-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation January 14, 2010 Chris L. Burton, Vice President Shearon Harris Nuclear Power Plant Carolina Power & Light Company Post Office Box 165, Mail Zone 1 New Hill, North Carolina 27562-0165 SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1 -ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT (TAC NO. ME2827)
Dear Mr. Burton:
Enclosed is a copy of the Environmental Assessment and Finding of No Significant Impact related to your application for exemption dated November 30,2009, as supplemented by letter dated December 16, 2009. The proposed exemption from specific requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 73, for the Shearon Harris Nuclear Power Plant, Unit 1, would extend the deadline from March 31, 2010, until July 30, 2010, and December 15, 2010, for the implementation of certain measures in 10 CFR Part 73. The assessment is being forwarded to the Office of the Federal Register for publica)ion.
Sincerely, IRA! Marlayna Vaaler, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-400
Enclosure:
Environmental Assessment cc w/enclosure:
Distribution via ListServ DISTRIBUTION:
PUBLIC RidsNrrLACSola LPL2-2 RlF RidsNrrPMShearonHarris RidsAcrsAcnw
_MailCTR RidsOgcRp RidsNrrDlrRerb RidsRgn2MailCenter RidsNrrDorlLpl2-2 SKlementowicz ADAMS Accession Nos. L TR ML093570609 EA FRN (NRR-042)
ML093570636 OFFICE DORULPL2-2/PM DORULPL2-2/LA DLRlRERB/BC OGC NLO w/comment DORL/LPL2-2/BC NAME MVaaler CSoia Almboden MSpencer TBoyce DATE 12/30/09 12/30/09 01/05/10 01/14/10 01/14/10 OFFICIAL RECORD COPY