[7590-01-P]

NUCLEAR REGULATORY COMMISSION

[Docket No. 50-400; NRC-2020-0080]

Duke Energy Progress, LLC; Shearon Harris Nuclear Power Plant, Unit 1 AGENCY: Nuclear Regulatory Commission.

ACTION: License amendment application; opportunity to comment, request a hearing, and petition for leave to intervene; order.

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) is considering issuance of an amendment to Facility Operating License No. NFP-63, issued to Duke Energy Progress, LLC, for operation of the Shearon Harris Nuclear Power Plant, Unit 1. The proposed amendment would revise the Technical Specifications (TSs) to include the NRC-approved topical report, ANP-10341P-A, The ORFEO-GAIA and ORFEO-NMGRID Critical Heat Flux Correlations, and add Appendix J to DPC-NE-2005-P, Thermal-Hydraulic Statistical Core Design Methodology. TSs would be revised to add the departure from nucleate boiling ratio safety limit for a fuel assembly design with characteristics similar to the GAIA fuel design using the ORFEO-GAIA correlation methodology. The TSs would also be revised with minor formatting editorial adjustments to the impacted pages. For this amendment request, the NRC proposes to determine that it involves no significant hazards consideration. Because this amendment request contains sensitive unclassified non-safeguards information (SUNSI), an order imposes procedures to obtain access to SUNSI for contention preparation.

DATES: Submit comments by April 29, 2020. Requests for a hearing or petition for leave to intervene must be filed by May 29, 2020. Any potential party as defined in § 2.4

of title 10 of the Code of Federal Regulations (10 CFR), who believes access to SUNSI is necessary to respond to this notice must request document access by April 9, 2020.

ADDRESSES: You may submit comments by any of the following methods

  • Federal Rulemaking Web Site: Go to https://www.regulations.gov and search for Docket ID NRC-2020-0080. Address questions about NRC dockets IDs in Regulations.gov to Jennifer Borges; telephone: 301-287-9127; e-mail:

Jennifer.Borges@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document.

  • Mail comments to: Office of Administration, Mail Stop: TWFN-7-A60M, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, ATTN: Program Management, Announcements and Editing Staff.

For additional direction on obtaining information and submitting comments, see Obtaining Information and Submitting Comments in the SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT: Tanya E. Hood, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington DC 20555-0001; telephone: 301-415-1387, e-mail: Tanya.Hood@nrc.gov.

SUPPLEMENTARY INFORMATION:

I. Obtaining Information and Submitting Comments A. Obtaining Information Please refer to Docket ID NRC-2020-0080 when contacting the NRC about the availability of information for this action. You may obtain publicly-available information related to this action by any of the following methods:

2

  • NRCs Agencywide Documents Access and Management System (ADAMS): You may obtain publicly-available documents online in the ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select Begin Web-based ADAMS Search. For problems with ADAMS, please contact the NRCs Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by e-mail to pdr.resource@nrc.gov. The application dated April 10, 2019, as supplemented by letters dated June 6, 2019 and December 20, 2019 are available in ADAMS under Accession Nos. ML19100A442, ML19157A036, and ML19354B380 respectively.
  • NRCs PDR: You may examine and purchase copies of public documents at the NRCs PDR, Room O1-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.

B. Submitting Comments Please include Docket ID NRC-2020-0080 in your comment submission.

The NRC cautions you not to include identifying or contact information that you do not want to be publicly disclosed in your comment submission. The NRC will post all comment submissions at https://www.regulations.gov as well as enter the comment submissions into ADAMS. The NRC does not routinely edit comment submissions to remove identifying or contact information.

If you are requesting or aggregating comments from other persons for submission to the NRC, then you should inform those persons not to include identifying or contact information that they do not want to be publicly disclosed in their comment submission. Your request should state that the NRC does not routinely edit comment submissions to remove such information before making the comment submissions available to the public or entering the comment into ADAMS.

3

II. Introduction The NRC is considering issuance of an amendment to Facility Operating License No. NFP-63, issued to Duke Energy Progress, LLC, for operation of the Shearon Harris Nuclear Power Plant (Harris), Unit 1, located in Wake and Chatham Counties, North Carolina. The proposed amendment would revise the Harris TSs to include the NRC-approved topical report, ANP-10341P-A, for the correlation associated with the fuel design transition from the high thermal performance fuel to a fuel assembly design with characteristics similar to the GAIA fuel design.

The amendment would also add Appendix J to DPC-NE-2005-P to address the applicability of the ORFEO-GAIA critical heat flux correlation methodology to a fuel assembly design with characteristics similar to the GAIA fuel design at Harris. In addition, the TSs would be revised to add the departure from nucleate boiling ratio safety limit for a fuel assembly design with characteristics similar to the GAIA fuel design using the ORFEO-GAIA correlation methodology. The TSs would also be revised with minor formatting editorial adjustments to the impacted pages.

Before any issuance of the proposed license amendment, the NRC will need to make the findings required by the Atomic Energy Act of 1954, as amended (the Act), and NRC's regulations.

The NRC has made a proposed determination that the license amendment request involves no significant hazards consideration. Under the NRCs regulations in 10 CFR 50.92, this means that operation of the facility in accordance with the proposed amendment would not (1) involve a significant increase in the probability or consequences of an accident previously evaluated; or (2) create the possibility of a new or different kind of accident from any accident previously evaluated; or (3) involve a significant reduction in a margin of safety. As required by 10 CFR 50.91(a), the licensee 4

has provided its analysis of the issue of no significant hazards consideration, which is presented below, along with NRC edits in square brackets:

1. Does the proposed change involve a significant increase in the probability or consequences of an accident previously evaluated?

[Response: No.]

The proposed change incorporates into [Harris] TS a limit on the departure from nucleate boiling ratio (DNBR) safety limit for [a fuel assembly design with characteristics similar to the GAIA fuel design] that is based on a NRC reviewed and approved correlation, and does not require a physical change to plant systems, structures or components. Plant operations and analysis will continue to be in accordance with the [Harris] licensing basis.

This change does not impact any of the accident initiators. The departure from nucleate boiling ratio is the basis for protecting the fuel and is consistent with the safety analysis. The DNBR setpoint continues to ensure automatic protective action is initiated to prevent exceeding the proposed DNBR safety limit.

The proposed safety limit ensures that fuel integrity will be maintained during normal operations and anticipated operational transients. The core operating limits report will be developed in accordance with the approved methodology. The proposed safety limit value and proposed Appendix J to the DPC-NE-2005-P methodology report do not affect the performance of any equipment used to mitigate the consequences of an analyzed accident. There is no impact on the source term or pathways assumed in accidents previously assumed. No analysis assumptions are violated and there are no adverse effects on the factors that contribute to offsite or onsite dose as the result of an accident.

The proposed change also adds a topical report for a NRC reviewed and approved critical heat flux (CHF) correlation to the list of topical reports in the [Harris] TS, which is administrative in nature and has no impact on a plant configuration or system performance relied upon to mitigate the consequences of an accident. The list of topical reports in the TS used to develop the core operating limits does not impact either the initiation of an accident or the mitigation of its consequences. Additionally, the editorial change to remove the excess spacing between subitems in TS 6.9.1.6.2 is strictly administrative and has no impact on the technical content.

Therefore, the proposed change does not involve a significant increase in the probability or consequences of an accident previously evaluated.

5

2. Does the proposed change create the possibility of a new or different kind of accident from any previously evaluated?

[Response: No.]

The proposed change does not require a physical change to plant systems, structures or components. The proposed change extends the use of DPC-NE-2005-P-A by [Harris] for [a fuel assembly design with characteristics similar to the GAIA fuel design] and adds a limit on DNBR for [a fuel assembly design with characteristics similar to the GAIA fuel design] to the [Harris] TS that is based on the NRC reviewed and approved ORFEO-GAIA CHF correlation, ensuring that the fuel design limits are met.

Operations and analyses will continue to be in compliance with NRC regulations. The addition of a new DNBR limit does not affect any accident initiators that would create a new accident.

The proposed safety limit value does not change the methods governing normal plant operation, nor are the methods utilized to respond to plant transients altered. The CHF correlation is not an accident/event initiator. No new initiating events or transients result from the use of the ORFEO/GAIA CHF correlation or the related safety limit change.

The proposed change also adds a topical report for a NRC reviewed and approved CHF correlation to the list of topical reports in the [Harris] TS, which is administrative in nature and has no impact on a plant configuration or system performance.

The proposed change updates the list of NRC-approved topical reports used to develop the core operating limits. There is no change in the parameters within which the plant is normally operated. Additionally, the editorial change to remove the excess spacing between sub-items in TS 6.9.1.6.2 is strictly administrative and has no impact on the technical content. The possibility of a new of different kind of accident is not created.

Therefore, the proposed change does not create the possibility of a new or different kind of accident from any accident previously evaluated.

3. Does the proposed change involve a significant reduction in a margin of safety?

[Response: No.]

The proposed safety limit value has been established in accordance with the methodology for the ORFEO-GAIA CHF correlation to ensure that the applicable margin of safety is maintained (i.e., there is at least 95% probability at a 95%

6

confidence level that the hot fuel rod does not experience DNB

[departure from nucleate boiling]). The other reactor core safety limits will continue to be met by analyzing the reload using NRC-approved methods and incorporation of resultant operating limits into the Core Operating Limits Report (COLR). Consistent with the existing methodology, the use of the proposed Appendix J to the methodology will continue to ensure that all applicable design and safety limits are satisfied such that the fission product barriers will continue to perform their design functions.

Therefore, the proposed change does not involve a significant reduction in a margin of safety.

The NRC staff has reviewed the licensee's analysis and, based on this review, it appears that the three standards of 10 CFR 50.92(c) are satisfied. Therefore, the NRC staff proposes to determine that the license amendment request involves no significant hazards consideration.

The NRC is seeking public comments on this proposed determination that the license amendment request involves no significant hazards consideration. Any comments received within 30 days after the date of publication of this notice will be considered in making any final determination.

Normally, the Commission will not issue the amendment until the expiration of 60 days after the date of publication of this notice. The Commission may issue the license amendment before expiration of the 60-day notice period if the Commission concludes the amendment involves no significant hazards consideration. In addition, the Commission may issue the amendment prior to the expiration of the 30-day comment period if circumstances change during the 30-day comment period such that failure to act in a timely way would result, for example, in derating or shutdown of the facility. If the Commission takes action prior to the expiration of either the comment period or the notice period, it will publish in the Federal Register a notice of issuance. If the Commission makes a final no significant hazards consideration determination, any 7

hearing will take place after issuance. The Commission expects that the need to take this action will occur very infrequently.

III. Opportunity to Request a Hearing and Petition for Leave to Intervene Within 60 days after the date of publication of this notice, any persons (petitioner) whose interest may be affected by this action may file a request for a hearing and petition for leave to intervene (petition) with respect to the action. Petitions shall be filed in accordance with the Commissions Agency Rules of Practice and Procedure in 10 CFR part 2. Interested persons should consult a current copy of 10 CFR 2.309. The NRCs regulations are accessible electronically from the NRC Library on the NRCs Web site at https://www.nrc.gov/reading-rm/doc-collections/cfr/. Alternatively, a copy of the regulations is available at the NRCs Public Document Room, located at One White Flint North, Room O1-F21, 11555 Rockville Pike (first floor), Rockville, Maryland 20852. If a petition is filed, the Commission or a presiding officer will rule on the petition and, if appropriate, a notice of a hearing will be issued.

As required by 10 CFR 2.309(d) the petition should specifically explain the reasons why intervention should be permitted with particular reference to the following general requirements for standing: (1) the name, address, and telephone number of the petitioner; (2) the nature of the petitioners right to be made a party to the proceeding; (3) the nature and extent of the petitioners property, financial, or other interest in the proceeding; and (4) the possible effect of any decision or order which may be entered in the proceeding on the petitioners interest.

In accordance with 10 CFR 2.309(f), the petition must also set forth the specific contentions which the petitioner seeks to have litigated in the proceeding. Each contention must consist of a specific statement of the issue of law or fact to be raised or controverted. In addition, the petitioner must provide a brief explanation of the bases for 8

the contention and a concise statement of the alleged facts or expert opinion which support the contention and on which the petitioner intends to rely in proving the contention at the hearing. The petitioner must also provide references to the specific sources and documents on which the petitioner intends to rely to support its position on the issue. The petition must include sufficient information to show that a genuine dispute exists with the applicant or licensee on a material issue of law or fact. Contentions must be limited to matters within the scope of the proceeding. The contention must be one which, if proven, would entitle the petitioner to relief. A petitioner who fails to satisfy the requirements at 10 CFR 2.309(f) with respect to at least one contention will not be permitted to participate as a party.

Those permitted to intervene become parties to the proceeding, subject to any limitations in the order granting leave to intervene. Parties have the opportunity to participate fully in the conduct of the hearing with respect to resolution of that partys admitted contentions, including the opportunity to present evidence, consistent with the NRCs regulations, policies, and procedures.

Petitions must be filed no later than 60 days from the date of publication of this notice. Petitions and motions for leave to file new or amended contentions that are filed after the deadline will not be entertained absent a determination by the presiding officer that the filing demonstrates good cause by satisfying the three factors in 10 CFR 2.309(c)(1)(i) through (iii). The petition must be filed in accordance with the filing instructions in the Electronic Submissions (E-Filing) section of this document.

If a hearing is requested, and the Commission has not made a final determination on the issue of no significant hazards consideration, the Commission will make a final determination on the issue of no significant hazards consideration. The final determination will serve to establish when the hearing is held. If the final 9

determination is that the amendment request involves no significant hazards consideration, the Commission may issue the amendment and make it immediately effective, notwithstanding the request for a hearing. Any hearing would take place after issuance of the amendment. If the final determination is that the amendment request involves a significant hazards consideration, then any hearing held would take place before the issuance of the amendment unless the Commission finds an imminent danger to the health or safety of the public, in which case it will issue an appropriate order or rule under 10 CFR part 2.

A State, local governmental body, Federally-recognized Indian Tribe, or agency thereof, may submit a petition to the Commission to participate as a party under 10 CFR 2.309(h)(1). The petition should state the nature and extent of the petitioners interest in the proceeding. The petition should be submitted to the Commission no later than 60 days from the date of publication of this notice. The petition must be filed in accordance with the filing instructions in the Electronic Submissions (E-Filing) section of this document, and should meet the requirements for petitions set forth in this section, except that under 10 CFR 2.309(h)(2) a State, local governmental body, or Federally-recognized Indian Tribe, or agency thereof does not need to address the standing requirements in 10 CFR 2.309(d) if the facility is located within its boundaries.

Alternatively, a State, local governmental body, Federally-recognized Indian Tribe, or agency thereof may participate as a non-party under 10 CFR 2.315(c).

If a hearing is granted, any person who is not a party to the proceeding and is not affiliated with or represented by a party may, at the discretion of the presiding officer, be permitted to make a limited appearance pursuant to the provisions of 10 CFR 2.315(a).

A person making a limited appearance may make an oral or written statement of his or her position on the issues but may not otherwise participate in the proceeding. A limited 10

appearance may be made at any session of the hearing or at any prehearing conference, subject to the limits and conditions as may be imposed by the presiding officer. Details regarding the opportunity to make a limited appearance will be provided by the presiding officer if such sessions are scheduled.

IV. Electronic Submissions (E-Filing)

All documents filed in NRC adjudicatory proceedings, including a request for hearing and petition for leave to intervene (petition), any motion or other document filed in the proceeding prior to the submission of a request for hearing or petition to intervene, and documents filed by interested governmental entities that request to participate under 10 CFR 2.315(c), must be filed in accordance with the NRCs E-Filing rule (72 FR 49139; August 28, 2007, as amended at 77 FR 46562; August 3, 2012). The E-Filing process requires participants to submit and serve all adjudicatory documents over the internet, or in some cases to mail copies on electronic storage media. Detailed guidance on making electronic submissions may be found in the Guidance for Electronic Submissions to the NRC and on the NRC Web site at https://www.nrc.gov/site-help/e-submittals.html. Participants may not submit paper copies of their filings unless they seek an exemption in accordance with the procedures described below.

To comply with the procedural requirements of E-Filing, at least 10 days prior to the filing deadline, the participant should contact the Office of the Secretary by e-mail at hearing.docket@nrc.gov, or by telephone at 301-415-1677, to (1) request a digital identification (ID) certificate, which allows the participant (or its counsel or representative) to digitally sign submissions and access the E-Filing system for any proceeding in which it is participating; and (2) advise the Secretary that the participant will be submitting a petition or other adjudicatory document (even in instances in which the participant, or its counsel or representative, already holds an NRC-issued digital ID 11

certificate). Based upon this information, the Secretary will establish an electronic docket for the hearing in this proceeding if the Secretary has not already established an electronic docket.

Information about applying for a digital ID certificate is available on the NRCs public Web site at https://www.nrc.gov/site-help/e-submittals/getting-started.html. Once a participant has obtained a digital ID certificate and a docket has been created, the participant can then submit adjudicatory documents. Submissions must be in Portable Document Format (PDF). Additional guidance on PDF submissions is available on the NRCs public Web site at https://www.nrc.gov/site-help/electronic-sub-ref-mat.html. A filing is considered complete at the time the document is submitted through the NRCs E-Filing system. To be timely, an electronic filing must be submitted to the E-Filing system no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of a transmission, the E-Filing system time-stamps the document and sends the submitter an e-mail notice confirming receipt of the document. The E-Filing system also distributes an e-mail notice that provides access to the document to the NRCs Office of the General Counsel and any others who have advised the Office of the Secretary that they wish to participate in the proceeding, so that the filer need not serve the document on those participants separately. Therefore, applicants and other participants (or their counsel or representative) must apply for and receive a digital ID certificate before adjudicatory documents are filed so that they can obtain access to the documents via the E-Filing system.

A person filing electronically using the NRCs adjudicatory E-Filing system may seek assistance by contacting the NRCs Electronic Filing Help Desk through the Contact Us link located on the NRCs public Web site at https://www.nrc.gov/site-help/e-submittals.html, by e-mail to MSHD.Resource@nrc.gov, or by a toll-free call at 12

1-866-672-7640. The NRC Electronic Filing Help Desk is available between 9 a.m. and 6 p.m., Eastern Time, Monday through Friday, excluding government holidays.

Participants who believe that they have a good cause for not submitting documents electronically must file an exemption request, in accordance with 10 CFR 2.302(g), with their initial paper filing stating why there is good cause for not filing electronically and requesting authorization to continue to submit documents in paper format. Such filings must be submitted by: (1) first class mail addressed to the Office of the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention: Rulemaking and Adjudications Staff; or (2) courier, express mail, or expedited delivery service to the Office of the Secretary, 11555 Rockville Pike, Rockville, Maryland 20852, Attention: Rulemaking and Adjudications Staff. Participants filing adjudicatory documents in this manner are responsible for serving the document on all other participants. Filing is considered complete by first-class mail as of the time of deposit in the mail, or by courier, express mail, or expedited delivery service upon depositing the document with the provider of the service. A presiding officer, having granted an exemption request from using E-Filing, may require a participant or party to use E-Filing if the presiding officer subsequently determines that the reason for granting the exemption from use of E-Filing no longer exists.

Documents submitted in adjudicatory proceedings will appear in the NRCs electronic hearing docket which is available to the public at https://adams.nrc.gov/ehd, unless excluded pursuant to an order of the Commission or the presiding officer. If you do not have an NRC-issued digital ID certificate as described above, click cancel when the link requests certificates and you will be automatically directed to the NRCs electronic hearing dockets where you will be able to access any publicly available 13

documents in a particular hearing docket. Participants are requested not to include personal privacy information, such as social security numbers, home addresses, or personal phone numbers in their filings, unless an NRC regulation or other law requires submission of such information. For example, in some instances, individuals provide home addresses in order to demonstrate proximity to a facility or site. With respect to copyrighted works, except for limited excerpts that serve the purpose of the adjudicatory filings and would constitute a Fair Use application, participants are requested not to include copyrighted materials in their submission.

For further details with respect to this action, see the application for license amendment dated April 10, 2019, as supplemented by letters dated June 6, 2019 and December 20, 2019.

Attorney for licensee: David Cummings, Associate General Counsel, Duke Energy Corporation, Mail Code DEC45, 550 South Tryon St., Charlotte, NC 28202.

NRC Branch Chief: Undine Shoop.

V. Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information for Contention Preparation A. This Order contains instructions regarding how potential parties to this proceeding may request access to documents containing Sensitive Unclassified Non-Safeguards Information (SUNSI).

B. Within 10 days after publication of this notice of hearing and opportunity to petition for leave to intervene, any potential party who believes access to SUNSI is necessary to respond to this notice may request access to SUNSI. A potential party is any person who intends to participate as a party by demonstrating standing and filing an admissible contention under 10 CFR 2.309. Requests for access to SUNSI submitted later than 10 days after publication of this notice will not be considered absent a showing 14

of good cause for the late filing, addressing why the request could not have been filed earlier.

C. The requester shall submit a letter requesting permission to access SUNSI to the Office of the Secretary, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention: Rulemakings and Adjudications Staff, and provide a copy to the Deputy General Counsel for Hearings and Administration, Office of the General Counsel, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001. The expedited delivery or courier mail address for both offices is: U.S. Nuclear Regulatory Commission, 11555 Rockville Pike, Rockville, Maryland 20852. The e-mail address for the Office of the Secretary and the Office of the General Counsel are Hearing.Docket@nrc.gov and RidsOgcMailCenter.Resource@nrc.gov, respectively.1 The request must include the following information:

(1) A description of the licensing action with a citation to this Federal Register notice; (2) The name and address of the potential party and a description of the potential partys particularized interest that could be harmed by the action identified in C.(1); and (3) The identity of the individual or entity requesting access to SUNSI and the requesters basis for the need for the information in order to meaningfully participate in this adjudicatory proceeding. In particular, the request must explain why publicly available versions of the information requested would not be sufficient to provide the basis and specificity for a proffered contention.

1 While a request for hearing or petition to intervene in this proceeding must comply with the filing requirements of the NRCs E-Filing Rule, the initial request to access SUNSI under these procedures should be submitted as described in this paragraph.

15

D. Based on an evaluation of the information submitted under paragraph C.(3) the NRC staff will determine within 10 days of receipt of the request whether:

(1) There is a reasonable basis to believe the petitioner is likely to establish standing to participate in this NRC proceeding; and (2) The requestor has established a legitimate need for access to SUNSI.

E. If the NRC staff determines that the requestor satisfies both D.(1) and D.(2) above, the NRC staff will notify the requestor in writing that access to SUNSI has been granted. The written notification will contain instructions on how the requestor may obtain copies of the requested documents, and any other conditions that may apply to access to those documents. These conditions may include, but are not limited to, the signing of a Non-Disclosure Agreement or Affidavit, or Protective Order2 setting forth terms and conditions to prevent the unauthorized or inadvertent disclosure of SUNSI by each individual who will be granted access to SUNSI.

F. Filing of Contentions. Any contentions in these proceedings that are based upon the information received as a result of the request made for SUNSI must be filed by the requestor no later than 25 days after receipt of (or access to) that information. However, if more than 25 days remain between the petitioners receipt of (or access to) the information and the deadline for filing all other contentions (as established in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI contentions by that later deadline.

2 Any motion for Protective Order or draft Non-Disclosure Affidavit or Agreement for SUNSI must be filed with the presiding officer or the Chief Administrative Judge if the presiding officer has not yet been designated, within 30 days of the deadline for the receipt of the written access request.

16

G. Review of Denials of Access.

(1) If the request for access to SUNSI is denied by the NRC staff after a determination on standing and requisite need, the NRC staff shall immediately notify the requestor in writing, briefly stating the reason or reasons for the denial.

(2) The requester may challenge the NRC staffs adverse determination by filing a challenge within 5 days of receipt of that determination with: (a) the presiding officer designated in this proceeding; (b) if no presiding officer has been appointed, the Chief Administrative Judge, or if he or she is unavailable, another administrative judge, or an Administrative Law Judge with jurisdiction pursuant to 10 CFR 2.318(a); or (c) if another officer has been designated to rule on information access issues, with that officer.

(3) Further appeals of decisions under this paragraph must be made pursuant to 10 CFR 2.311.

H. Review of Grants of Access. A party other than the requester may challenge an NRC staff determination granting access to SUNSI whose release would harm that partys interest independent of the proceeding. Such a challenge must be filed within 5 days of the notification by the NRC staff of its grant of access and must be filed with: (a) the presiding officer designated in this proceeding; (b) if no presiding officer has been appointed, the Chief Administrative Judge, or if he or she is unavailable, another administrative judge, or an Administrative Law Judge with jurisdiction pursuant to 10 CFR 2.318(a); or (c) if another officer has been designated to rule on information access issues, with that officer.

If challenges to the NRC staff determinations are filed, these procedures give way to the normal process for litigating disputes concerning access to information. The 17

availability of interlocutory review by the Commission of orders ruling on such NRC staff determinations (whether granting or denying access) is governed by 10 CFR 2.311.3 I. The Commission expects that the NRC staff and presiding officers (and any other reviewing officers) will consider and resolve requests for access to SUNSI, and motions for protective orders, in a timely fashion in order to minimize any unnecessary delays in identifying those petitioners who have standing and who have propounded contentions meeting the specificity and basis requirements in 10 CFR part 2. The attachment to this Order summarizes the general target schedule for processing and resolving requests under these procedures.

IT IS SO ORDERED.

Dated at Rockville, Maryland, this 24th of March, 2020.

For the Nuclear Regulatory Commission.

/RA/

Annette L. Vietti-Cook, Secretary of the Commission.

3 Requesters should note that the filing requirements of the NRCs E-Filing Rule (72 FR 49139; August 28, 2007, as amended at 77 FR 46562; August 3, 2012) apply to appeals of NRC staff determinations (because they must be served on a presiding officer or the Commission, as applicable), but not to the initial SUNSI request submitted to the NRC staff under these procedures.

18

ATTACHMENT 1--General Target Schedule for Processing and Resolving Requests for Access to Sensitive Unclassified Non-Safeguards Information in this Proceeding Day Event/Activity 0 Publication of Federal Register notice of hearing and opportunity to petition for leave to intervene, including order with instructions for access requests.

10 Deadline for submitting requests for access to Sensitive Unclassified Non-Safeguards Information (SUNSI) with information: supporting the standing of a potential party identified by name and address; describing the need for the information in order for the potential party to participate meaningfully in an adjudicatory proceeding.

60 Deadline for submitting petition for intervention containing: (i) demonstration of standing; and (ii) all contentions whose formulation does not require access to SUNSI (+25 Answers to petition for intervention; +7 petitioner/requestor reply).

20 U.S. Nuclear Regulatory Commission (NRC) staff informs the requester of the staffs determination whether the request for access provides a reasonable basis to believe standing can be established and shows need for SUNSI.

(NRC staff also informs any party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information.) If NRC staff makes the finding of need for SUNSI and likelihood of standing, NRC staff begins document processing (preparation of redactions or review of redacted documents).

25 If NRC staff finds no need or no likelihood of standing, the deadline for petitioner/requester to file a motion seeking a ruling to reverse the NRC staffs denial of access; NRC staff files copy of access determination with the presiding officer (or Chief Administrative Judge or other designated officer, as appropriate). If NRC staff finds need for SUNSI, the deadline for any party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information to file a motion seeking a ruling to reverse the NRC staffs grant of access.

30 Deadline for NRC staff reply to motions to reverse NRC staff determination(s).

40 (Receipt +30) If NRC staff finds standing and need for SUNSI, deadline for NRC staff to complete information processing and file motion for Protective Order and draft Non-Disclosure Affidavit. Deadline for applicant/licensee to file Non-Disclosure Agreement for SUNSI.

A If access granted: issuance of presiding officer or other designated officer decision on motion for protective order for access to sensitive information 19

Day Event/Activity (including schedule for providing access and submission of contentions) or decision reversing a final adverse determination by the NRC staff.

A+3 Deadline for filing executed Non-Disclosure Affidavits. Access provided to SUNSI consistent with decision issuing the protective order.

A + 28 Deadline for submission of contentions whose development depends upon access to SUNSI. However, if more than 25 days remain between the petitioners receipt of (or access to) the information and the deadline for filing all other contentions (as established in the notice of opportunity to request a hearing and petition for leave to intervene), the petitioner may file its SUNSI contentions by that later deadline.

A + 53 (Contention receipt +25) Answers to contentions whose development depends upon access to SUNSI.

A + 60 (Answer receipt +7) Petitioner/Intervenor reply to answers.

>A + 60 Decision on contention admission.

20