Assessment Follow-Up Letter - St. Lucie, Unit 1
ML101200565
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 04/30/2010
From: Reyes L A
Region 2 Administrator
To: Nazar M
Florida Power & Light Co
References
Download: ML101200565 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 April 30, 2010 Mr. Mano Nazar Executive Vice President Nuclear and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, FL 33408-0420

SUBJECT:

ASSESSMENT FOLLOW-UP LETTER - ST. LUCIE NUCLEAR PLANT UNIT 1

Dear Mr. Nazar:

On April 19, 2010, the NRC issued the final significance determination of an inspection finding and a Notice of Violation related to air intrusion into the Component Cooling Water (CCW) system (ML101090509). The NRC has concluded that this violation involving the failure to identify and correct the source of the air in-leakage into the CCW system was characterized as Yellow, i.e., a finding of substantial significance with regard to safety, requiring additional NRC inspections. This Yellow finding was in the Initiating Events cornerstone.

As a result of our review, we have assessed St. Lucie Unit 1 performance to be in the Degraded Cornerstone column of the NRC

=s Action Matrix as of the 4 th quarter of calendar year (CY) 2009. On April 28, 2010, we were notified by your staff of the status of your readiness for the NRC to conduct a supplemental inspection to review the actions taken to address the failure to identify and correct the source of the air in-leakage into the CCW system. Accordingly, we plan to conduct a supplemental inspection in accordance with Inspection Procedure 95002 in September 2010.

This inspection is conducted to provide assurance that the root and contributing causes for the individual and collective risk significant performance issues are understood, to independently assess the extent of condition, to provide assurance that the corrective actions are sufficient to prevent recurrence, and to independently determine if safety culture components caused or significantly contributed to the individual risk significant performance issues.

In accordance with 10 CFR 2.390 of the NRC

=s ARules of Practice,@ a copy of this letter will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

FP&L 2 Please contact Marvin Sykes at 404-997-4629 with any questions you may have regarding this letter. Sincerely,

/RA By Victor McCree For/

Luis A. Reyes Regional Administrator Docket No. 50-335 License No. DPR-67 cc: (See next page)

_________________________ X SUNSI REVIEW COMPLETE OFFICE RII:DRP RII:DRP RII:DRS RII:ORA RII:ORA SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA By VMcCree for/ NAME MSykes LWert BDesai VMcCree LReyes DATE 4/28/10 4/30/10 4/28/10 4/30/10 4/30/10 5/ /2010 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES N O

FP&L 3 cc: Richard L. Anderson Site Vice President St. Lucie Nuclear Plant Electronic Mail Distribution

Robert J. Hughes Plant General Manager St. Lucie Nuclear Plant Electronic Mail Distribution

Gene St. Pierre Vice President, Fleet Support Florida Power & Light Company Electronic Mail Distribution Ronnie Lingle Operations Manager St. Lucie Nuclear Plant Electronic Mail Distribution Eric Katzman Licensing Manager St. Lucie Nuclear Plant Electronic Mail Distribution Larry Nicholson Director Licensing Florida Power & Light Company Electronic Mail Distribution Alison Brown Nuclear Licensing Florida Power & Light Company Electronic Mail Distribution Mitch S. Ross Vice President and Associate General Counsel Florida Power & Light Company Electronic Mail Distribution Marjan Mashhadi Senior Attorney Florida Power & Light Company Electronic Mail Distribution

William A. Passetti Chief Florida Bureau of Radiation Control Department of Health Electronic Mail Distribution

Ruben D. Almaguer Director Division of Emergency Preparedness Department of Community Affairs Electronic Mail Distribution J. Kammel Radiological Emergency Planning Administrator Department of Public Safety Electronic Mail Distribution

Mano Nazar Executive Vice President and Chief Nuclear Officer Florida Power & Light Company P. O. Box 14000 Juno Beach, FL 33408 Senior Resident Inspector St. Lucie Nuclear Plant U.S. Nuclear Regulatory Commission P.O. Box 6090 Jensen Beach, FL 34957-2010 Seth B. Duston Training Manager St. Lucie Nuclear Plant Electronic Mail Distribution Faye Outlaw County Administrator St. Lucie County Electronic Mail Distribution Jack Southard Director Public Safety Department St. Lucie County Electronic Mail Distribution FP&L 4 Letter to Mano Nazar from Luis A. Reyes dated April 30, 2010

SUBJECT:

ASSESSMENT FOLLOW-UP LETTER - ST. LUCIE NUCLEAR PLANT UNIT 1 Distribution:

C. Evans, RII L. Slack, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMStLucie Resource