2010/10/12 Diablo Canyon Lr - Telecon Summaries
ML102850083
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 10/12/2010
From:
Office of Nuclear Reactor Regulation
To:
Division of License Renewal
References
Download: ML102850083 (14)


Text

1 DiabloCanyonNPEm Resource From: Green, Kimberly Sent: Tuesday, October 12, 2010 8:46 AM To: Grebel, Terence Cc: DiabloCanyonNPEm Resource

Subject:

Telecon Summaries Attachments:

Telecon Summary 09-27-10 Aging Management Review.doc; Telecon Summary 09-16-10 TLAA.doc; Telecon Summary 09-22-10 Aging Management Programs.docTerry, Attached are three draft telecon summaries. Please let me know if any changes or corrections are needed.

Thanks, KimberlyGreenSafetyPM(301)4151627kimberly.green@nrc.gov Hearing Identifier: DiabloCanyon_LicenseRenewal_NonPublic Email Number: 1920 Mail Envelope Properties (F5A4366DF596BF458646C9D433EA37D7389CFFD2DA)

Subject:

Telecon Summaries Sent Date: 10/12/2010 8:45:53 AM Received Date: 10/12/2010 8:45:54 AM From: Green, Kimberly Created By: Kimberly.Green@nrc.gov Recipients: "DiabloCanyonNPEm Resource" <DiabloCanyonNPEm.Resource@nrc.gov>

Tracking Status: None "Grebel, Terence" <TLG1@pge.com>

Tracking Status: None Post Office: HQCLSTR01.nrc.gov

Files Size Date & Time MESSAGE 258 10/12/2010 8:45:54 AM Telecon Summary 09-27-10 Aging Management Review.doc 79866 Telecon Summary 09-16-10 TLAA.doc 79866 Telecon Summary 09-22-10 Aging Management Programs.doc 79866

Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received:

LICENSEE: Pacific Gas and Electric Company

FACILITY: Diablo Canyon Nuclear Power Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON SEPTEMBER 27, 2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND PACIFIC GAS AND ELECTRIC COMPANY CONCERNING THE DRAFT REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION - AGING MANAGEMENT REVIEW

The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Pacific Gas and Electric Company (PG&E) held a telephone conference call on September 27, 2010, to obtain clarification on the staff's draft request for additional information (D-RAI) regarding the Diablo Canyon Nuclear Power Plant, Units 1 and 2, license renewal application (LRA).

By letter dated September 16, 2010, the staff issued D-RAIs to PG&E regarding aging management review. PG&E reviewed the information contained therein, and requested a telephone conference call. The telephone conference call was useful in clarifying the intent of the staff's D-RAIs. No changes to D-RAIs were necessary as a result of this telephone conference call. Formal RAIs will be issued by a separate letter.

The enclosure provides a listing of the participants.

The applicant had an opportunity to comment on this summary.

Nathaniel Ferrer, Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323

Enclosure:

As stated

cc w/encl: Distribution via Listserv

ML102700617 OFFICE LA:DLR PM:RPB2:DLR BC:RPB2:DLR PM:RPB2:DLR NAME NFerrer DWrona NFerrer DATE / /10 / /10 / /10 / /10

ENCLOSURE TELEPHONE CONFERENCE CALL DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS SEPTEMBER 27, 2010

PARTICIPANTS A FFILIATIONS Nate Ferre r U.S. Nuclear Re g ulator y Commission (NRC)Bill Holston NRC Terr y Grebel Pacific Gas & Electric (PG&E) Phili ppe Soenen PG&EKevin Braico PG&E

David Kunsemille r Strate gic Teamin g And Resource Sharin g (STARS)

Memorandum to Pacific Gas and Electric Company from N. Ferrer dated September XX, 2010

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON SEPTEMBER 27, 2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND PACIFIC GAS AND ELECTRIC COMPANY CONCERNING THE DRAFT REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION - AGING MANAGEMENT REVIEW DISTRIBUTION

HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDlr Resource

RidsNrrDlrRpb1 Resource

RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource

RidsNrrDlrRerb Resource

RidsNrrDlrRpob Resource RidsOgcMailRoom Resource ---------------------

NFerrer KGreen AStuyvenberg

DWrona AWang MPeck, RIV TBrown, RI

GMiller, RIV NO'Keefe, RIV

ICouret, OPA VDricks, OPA WMaier, RIV

JWeil, OCA EWilliamson, OGC

SUttal, OGC RRihm, EDO

LICENSEE: Pacific Gas and Electric Company

FACILITY: Diablo Canyon Nuclear Power Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON SEPTEMBER 16, 2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND PACIFIC GAS AND ELECTRIC COMPANY CONCERNING THE DRAFT REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION - TIME LIMITED AGING ANALYSIS

The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Pacific Gas and Electric Company (PG&E) held a telephone conference call on September 16, 2010, to obtain clarification on the staff's draft request for additional information (D-RAI) regarding the Diablo Canyon Nuclear Power Plant, Units 1 and 2, license renewal application.

By e-mail dated September 7, 2010, the staff sent D-RAIs to PG&E regarding time limited aging analyses. PG&E reviewed the information contained therein, and requested a telephone conference call. The telephone conference call was useful in clarifying the intent of the staff's D-RAIs. No changes to D-RAIs were necessary as a result of this telephone conference call.

Formal RAIs will be issued by a separate letter.

The enclosure provides a listing of the participants.

The applicant had an opportunity to comment on this summary.

Nathaniel Ferrer, Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323

Enclosure:

As stated

cc w/encl: Distribution via Listserv

ML102700626 OFFICE LA:DLR PM:RPB2:DLR BC:RPB2:DLR PM:RPB2:DLR NAME NFerrer DWrona NFerrer DATE / /10 / /10 / /10 / /10

ENCLOSURE TELEPHONE CONFERENCE CALL DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS SEPTEMBER 16, 2010

PARTICIPANTS A FFILIATIONS Nate Ferre r U.S. Nuclear Re g ulator y Commission (NRC)James Medof f NRC Terr y Grebel Pacific Gas & Electric (PG&E) Phili ppe Soenen PG&E Chalmer M y e r Strate gic Teamin g And Resource Sharin g (STARS)

Enclosure 2 Memorandum to Pacific Gas and Electric Company from N. Ferrer dated September XX, 2010

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON SEPTEMBER 16, 2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND PACIFIC GAS AND ELECTRIC COMPANY CONCERNING THE DRAFT REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION - TIME LIMITED AGING ANALYSIS DISTRIBUTION

HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDlr Resource

RidsNrrDlrRpb1 Resource

RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource

RidsNrrDlrRerb Resource

RidsNrrDlrRpob Resource

RidsOgcMailCenter Resource ---------------------

NFerrer KGreen AStuyvenberg

DWrona AWang MPeck, RIV TBrown, RI

GMiller, RIV NO'Keefe, RIV

ICouret, OPA VDricks, OPA WMaier, RIV

JWeil, OCA EWilliamson, OGC

SUttal, OGC RRihm, EDO

LICENSEE: Pacific Gas and Electric Company

FACILITY: Diablo Canyon Nuclear Power Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON SEPTEMBER 22, 2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND PACIFIC GAS AND ELECTRIC COMPANY CONCERNING THE REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION - AGING MANAGEMENT PROGRAMS

The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Pacific Gas and Electric Company (PG&E) held a telephone conference call on September 22, 2010, to obtain clarification on the staff's request for additional information (RAI) regarding the Diablo Canyon Nuclear Power Plant, Units 1 and 2, license renewal application.

By letter dated September 1, 2010, the staff issued RAIs to PG&E regarding aging management programs. PG&E reviewed the information contained therein, and requested a telephone conference call. The telephone conference call was useful in clarifying the intent of the staff's RAIs. No changes to RAIs were necessary as a result of this telephone conference call.

The enclosure provides a listing of the participants.

The applicant had an opportunity to comment on this summary.

Nathaniel Ferrer, Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation

Docket Nos. 50-275 and 50-323

Enclosure:

As stated

cc w/encl: Distribution via Listserv

ML102700622 OFFICE LA:DLR PM:RPB2:DLR BC:RPB2:DLR PM:RPB2:DLR NAME NFerrer DWrona NFerrer DATE / /10 / /10 / /10 / /10

ENCLOSURE TELEPHONE CONFERENCE CALL DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS SEPTEMBER 22, 2010

PARTICIPANTS A FFILIATIONS Nate Ferre r U.S. Nuclear Re g ulator y Commission (NRC)Abdul Sheikh NRC Br yce Lehman NRCDan Naus Oak Rid ge National Laborator y Ter r y Grebel Pacific Gas & Electric (PG&E) K yle Duke PG&E David Won g PG&EBill Horstman PG&E Behrooz Shakibnia PG&E Bob O'Sullivan PG&E

Memorandum to Pacific Gas and Electric Company from N. Ferrer dated September xx, 2010

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON SEPTEMBER 22, 2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND PACIFIC GAS AND ELECTRIC COMPANY CONCERNING THE REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION - AGING MANAGEMENT PROGRAMS DISTRIBUTION

HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDlr Resource

RidsNrrDlrRpb1 Resource

RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource

RidsNrrDlrRerb Resource

RidsNrrDlrRpob Resource

RidsOgcMailCenter Resource ---------------------

NFerrer KGreen AStuyvenberg

DWrona AWang MPeck, RIV TBrown, RI

GMiller, RIV NO'Keefe, RIV

ICouret, OPA VDricks, OPA WMaier, RIV

JWeil, OCA EWilliamson, OGC

SUttal, OGC RRihm, EDO