Letter Sequence Request |
---|
|
|
MONTHYEARML1105908612011-02-28028 February 2011 Ltr. to W. Norton First Request for Additional Information for Application for NRC Consent to Indirect License Transfer/Threshold Determination (TAC Nos. L24496, L24497, L24498) Project stage: RAI CY-11-009, Connecticut Yankee Atomic Power Company - Decommissioning Funding Assurance Status Report2011-03-15015 March 2011 Connecticut Yankee Atomic Power Company - Decommissioning Funding Assurance Status Report Project stage: Request ML1108101152011-03-15015 March 2011 Yankee, Decommissioning Funding Assurance Status Report Project stage: Request ML1107700222011-03-16016 March 2011 Application for NRC Consent to Indirect License Transfer/Threshold Determination That NRC Consent Is Not Required in Connection with Merger of Northeast Utilities and Nstar Project stage: Request ML1111014022011-04-20020 April 2011 W. Norton Letter Second Request for Additional Information for Application for NRC Consent to Indirect License Transfer/Threshold Determination (TAC Nos. L24496, L24497, L24498) Project stage: RAI CY-11-015, Response to Second Request for Additional Information for Application for NRC Consent to Indirect License Transfer/Threshold Determination - Merger of Northeast Utilities and Nstar2011-05-16016 May 2011 Response to Second Request for Additional Information for Application for NRC Consent to Indirect License Transfer/Threshold Determination - Merger of Northeast Utilities and Nstar Project stage: Request ML1114703702011-05-27027 May 2011 W. Norton Letter Second Request for Additional Information, Part 2, for Application for NRC Consent to Indirect License Transfer/Threshold Determination Project stage: RAI ML11195A3392011-07-13013 July 2011 Morgan Lewis on Behalf of Northeast Utilities and Nstar - Submittal of Supplemental Response to Requests for Additional Information and Negation Action Plan Project stage: Supplement ML1119600682011-07-14014 July 2011 Enclosure - Request for Supplemental Information Related to the Request for Exemption from 10 CFR 50.38 and the Indirect License Transfer Related to Merger of Northeast Utilities and Nstar Project stage: Approval ML1119600612011-07-14014 July 2011 Ltr. to W. Norton Request for Exemption from 10 CFR 50.38 for Maine Yankee Atomic Power Company, Connecticut Yankee Atomic Power Company, and Yankee Atomic Electric Company - Supplemental Information Needed; Relationship of Exemption Reques Project stage: Approval ML1122100232011-08-0505 August 2011 Enclosuthird RAI Related to Application for NRC Consent/Threshold Determination for Indirect License Transfer Related to Merger of Northeast Utilities and Nstar Project stage: RAI ML1122100172011-08-0505 August 2011 W. Norton Letter Third Request for Additional Information for Application for NRC Consent to Indirect License Transfer/Threshold Determination (TAC L24496, L24497, and L24498) Project stage: RAI CY-11-025, Connecticut Yankee and Yankee Atomic, Response to Third Request for Additional Information for Application for NRC Consent to Indirect License Transfer/Threshold Determination - Merger of Northeast Utilities and Nstar2011-08-24024 August 2011 Connecticut Yankee and Yankee Atomic, Response to Third Request for Additional Information for Application for NRC Consent to Indirect License Transfer/Threshold Determination - Merger of Northeast Utilities and Nstar Project stage: Request ML1125003732011-09-0606 September 2011 Notice of Mtg W/ Maine Yankee to Discuss Status of Review of Indirect License Transfer Request Related to Pending Merger of Northeast Utilities & Nstar; Status of Request for Exemption from 10 CFR 50.38; & Decommissioning Financial Assuranc Project stage: Approval ML1127700152011-10-0303 October 2011 Request for Exemption from 10 CFR 50.38 for Maine Yankee Atomic Power Co., Connecticut Yankee Atomic Power Co., and Yankee Atomic Electric Co. - Accepted for Review; Relationship of Exemption Request to Indirect License Transfer and Status Project stage: Approval CY-11-035, Follow-Up to Meeting on September 20, 2011, Regarding Foreign Ownership and Decommissioning Funding Issues2011-10-0505 October 2011 Follow-Up to Meeting on September 20, 2011, Regarding Foreign Ownership and Decommissioning Funding Issues Project stage: Meeting ML11298A0912011-10-20020 October 2011 Summary of Meeting with Yankee Companies, Northeast Utilities (Nu) & Nstar to Discuss Indirect License Transfer Request Related to Pending Merger of Nu & Nstar, Request for Exemption from 10 CFR 50.38 & Decommissioning Financial Assurance Project stage: Meeting ML11326A2562011-12-20020 December 2011 W. Norton Letter Threshold Determination for Facility Operating License No. DPR-36 for Maine Yankee Atomic Power Station (TAC No. L24497) Project stage: Other ML1132701272011-12-20020 December 2011 Enclosure 2 - Safety Evaluation Report Project stage: Approval ML1132701192011-12-20020 December 2011 Order Approving Application Regarding Proposed Merger. DPR-61 (Haddam Neck Plant) Project stage: Other ML1132701142011-12-20020 December 2011 Ltr. to Wayne Norton Order Approving the Indirect Transfer of Facility Operating License No. DPR-61 for the Haddam Neck Plant Project stage: Other ML11327A0292011-12-20020 December 2011 Safety Evaluation Report - Safety Evaluation Indirect Transfer of Control Related to the Merger of Northeast Utilities and Nstar Maine Yankee Atomic Power Company Project stage: Approval ML1132702092011-12-20020 December 2011 Ltr. to W. Norton Order Approving the Indirect Transfers of Facility Operating License No. DPR-3 for the Yankee Nuclear Power Station (Yankee-Rowe) Project stage: Other ML1132702272011-12-20020 December 2011 Order - Approving the Indirect Transfer of Facility Operating License No. DPR-3 for the Yankee Nuclear Power Station (Yankee-Rowe) Project stage: Other CY-12-026, Notice of Merger Closing2012-04-0909 April 2012 Notice of Merger Closing Project stage: Other ML12101A1332012-04-0909 April 2012 Yankee Atomic Electric Company, Notice of Merger Closing Project stage: Other CY-12-030, Notification Regarding Vote on Negation Action Plan and Submittal of Corrected Plan2012-04-24024 April 2012 Notification Regarding Vote on Negation Action Plan and Submittal of Corrected Plan Project stage: Other ML12124A2292012-04-24024 April 2012 Yankee Atomic Electric Company - Notification of Vote on Negation Action Plan and Submittal of Corrected Plan Project stage: Other 2011-05-16
[Table View] |
|
---|
Category:Financial Assurance Document
MONTHYEARCY-20-002, Independent Spent Fuel Storage Installation, Letter Notifying NRC the Amount of Property Insurance Coverage in Force for 20202020-01-22022 January 2020 Independent Spent Fuel Storage Installation, Letter Notifying NRC the Amount of Property Insurance Coverage in Force for 2020 CY-18-005, Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste2018-03-0505 March 2018 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste CY-17-005, Independent Spent Fuel Storage Installation - Property Insurance Coverage2017-02-28028 February 2017 Independent Spent Fuel Storage Installation - Property Insurance Coverage CY-16-004, Independent Spent Fuel Storage Installation, Submittal of Property Insurance Coverage2016-02-29029 February 2016 Independent Spent Fuel Storage Installation, Submittal of Property Insurance Coverage ML16067A1202016-02-12012 February 2016 Certificate of Liability Insurance CY-13-014, Nuclear Liability Insurance Coverage2013-02-0707 February 2013 Nuclear Liability Insurance Coverage CY-13-013, Property Insurance Coverage for 20132013-02-0707 February 2013 Property Insurance Coverage for 2013 CY-12-005, Nuclear Liability Insurance Coverage2012-01-25025 January 2012 Nuclear Liability Insurance Coverage CY-11-009, Connecticut Yankee Atomic Power Company - Decommissioning Funding Assurance Status Report2011-03-15015 March 2011 Connecticut Yankee Atomic Power Company - Decommissioning Funding Assurance Status Report CY-11-007, Notification of Property Insurance Coverage in Force for 20112011-03-14014 March 2011 Notification of Property Insurance Coverage in Force for 2011 CY-11-006, Submittal of Nuclear Liability Insurance Coverage2011-03-14014 March 2011 Submittal of Nuclear Liability Insurance Coverage CY-10-010, Nuclear Liability Insurance Coverage2010-04-29029 April 2010 Nuclear Liability Insurance Coverage CY-10-005, Decommissioning Funding Assurance Status Report2010-03-0909 March 2010 Decommissioning Funding Assurance Status Report CY-10-003, Notification of Amount of Property Insurance Coverage for 2010 for the Haddam Neck Plant in Accordance with 10 CFR 50.54(w)(3)2010-02-18018 February 2010 Notification of Amount of Property Insurance Coverage for 2010 for the Haddam Neck Plant in Accordance with 10 CFR 50.54(w)(3) CY-05-089, Decommissioning Funding Assurance2005-03-31031 March 2005 Decommissioning Funding Assurance 2020-01-22
[Table view] Category:Letter
MONTHYEARIR 05000213/20240012024-08-27027 August 2024 Connecticut Yankee Atomic Power Company - Independent Spent Fuel Storage Installation NRC Inspection Report Nos. 07200039/2024001 and 05000213/2024001 ML24094A0742024-05-30030 May 2024 Issuance of Exemption for Connecticut Yankee Atomic Power Company Regarding Haddam Neck Plant Independent Spent Fuel Storage Installation ML23342A0972024-01-0909 January 2024 Connecticut Yankee Atomic Power Company - Independent Spent Fuel Storage Installation Security Inspection Plan CY-23-014, Biennial Update of the CYAPCO Quality Assurance Program for the Haddam Neck ISFSI2023-12-0404 December 2023 Biennial Update of the CYAPCO Quality Assurance Program for the Haddam Neck ISFSI ML23124A2012023-04-20020 April 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Offsite Dose Calculation Manual for 2022 CY-23-006, Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report2023-03-0606 March 2023 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report CY-23-007, Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste2023-03-0606 March 2023 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML22340A4922023-02-24024 February 2023 Closeout Letter to Connecticut Yankee Regarding 2018 and 2021 Updated DFPs for Haddam Neck Plant ISFSI CY-23-003, Independent Spent Fuel Storage Installation, Nuclear Liability Insurance Coverage2023-01-17017 January 2023 Independent Spent Fuel Storage Installation, Nuclear Liability Insurance Coverage CY-23-004, Independent Spent Fuel Storage Installation, Property Insurance Coverage2023-01-17017 January 2023 Independent Spent Fuel Storage Installation, Property Insurance Coverage CY-23-002, Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments2023-01-0505 January 2023 Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments CY-23-001, Independent Spent Fuel Storage Installation, Report of 10 CFR 50.59 Changes, Tests, and Experiments2023-01-0505 January 2023 Independent Spent Fuel Storage Installation, Report of 10 CFR 50.59 Changes, Tests, and Experiments IR 07200039/20224012022-10-0505 October 2022 Connecticut Yankee Atomic Power Company - NRC Independent Spent Fuel Storage Security Inspection Report No. 07200039/2022401 CY-22-012, Independent Spent Fuel Storage Installation, Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan2022-08-0303 August 2022 Independent Spent Fuel Storage Installation, Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan CY-22-010, Connecticut Yankee Atomic Power Company Haddam Neck Plant Independent Spent Fuel Storage Installation, Formal Announcement of New ISFSI Manager2022-05-25025 May 2022 Connecticut Yankee Atomic Power Company Haddam Neck Plant Independent Spent Fuel Storage Installation, Formal Announcement of New ISFSI Manager CY-22-006, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Offsite Dose Calculation Manual for 20212022-04-25025 April 2022 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Offsite Dose Calculation Manual for 2021 CY-22-003, and Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report2022-03-14014 March 2022 and Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report CY-22-004, Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste2022-03-14014 March 2022 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML22011A1352022-01-31031 January 2022 Connecticut Yankee Atomic Power Company - Independent Spent Fuel Storage Installation Security Inspection Plan CY-22-002, Independent Spent Fuel Storage Installation - Property Insurance Coverage2022-01-20020 January 2022 Independent Spent Fuel Storage Installation - Property Insurance Coverage CY-22-001, Independent Spent Fuel Storage Installation - Nuclear Liability Insurance Coverage2022-01-20020 January 2022 Independent Spent Fuel Storage Installation - Nuclear Liability Insurance Coverage CY-21-015, Independent Spent Fuel Storage Installation, Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan2021-12-10010 December 2021 Independent Spent Fuel Storage Installation, Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan CY-21-011, Biennial Update of the CYAPCO Quality Assurance Program for the Haddam Neck ISFSI2021-12-0101 December 2021 Biennial Update of the CYAPCO Quality Assurance Program for the Haddam Neck ISFSI CY-21-013, Biennial Update to the Haddam Neck Plant License Termination Plan2021-12-0101 December 2021 Biennial Update to the Haddam Neck Plant License Termination Plan ML22075A2382021-12-0101 December 2021 Biennial Update to the Haddam Neck Plant Updated Final Safety Analysis Report CY-21-014, Independent Spent Fuel Storage Installation - Adoption of Amendment 8 of NAC-MPC Certificate of Compliance No. 72-1025 and Canister Registration2021-11-18018 November 2021 Independent Spent Fuel Storage Installation - Adoption of Amendment 8 of NAC-MPC Certificate of Compliance No. 72-1025 and Canister Registration IR 05000213/20210012021-10-26026 October 2021 Connecticut Yankee Atomic Power Company - NRC Independent Spent Fuel Storage Installation Inspection Report Nos. 07200039/2021001 and 05000213/2021001 ML21144A2512021-04-13013 April 2021 Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Offsite Dose Calculation Manual for 2020 CY-21-006, Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste2021-03-0202 March 2021 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste CY-21-005, Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report2021-03-0202 March 2021 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report CY-21-004, Independent Spent Fuel Storage Installation - Property Insurance Coverage2021-01-27027 January 2021 Independent Spent Fuel Storage Installation - Property Insurance Coverage CY-21-003, Independent Spent Fuel Storage Installation Nuclear Liability Insurance Coverage2021-01-27027 January 2021 Independent Spent Fuel Storage Installation Nuclear Liability Insurance Coverage ML21012A3192021-01-13013 January 2021 Connecticut Yankee Atomic Power Company - Independent Spent Fuel Storage Installation Security Inspection Plan IR 07200039/20204012020-11-20020 November 2020 Connecticut Yankee Atomic Power Company - Independent Spent Fuel Storage Installation Security Inspection Report 07200039/2020401, Without Enclosure (Public - Cover Letter Only) ML20150A3352020-06-19019 June 2020 COVID-19 Exemption for Haddam Neck CY-20-011, Independent Spent Fuel Storage Installation - Request for a Temporary Exemption from 10 CFR 73, Appendix B, Section Le and 10 CFR 73.55(r) Annual Physical Requalification Requirement2020-05-14014 May 2020 Independent Spent Fuel Storage Installation - Request for a Temporary Exemption from 10 CFR 73, Appendix B, Section Le and 10 CFR 73.55(r) Annual Physical Requalification Requirement ML20143A0972020-04-16016 April 2020 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Offsite Dose Calculation Manual for 2019 CY-20-007, Independent Spent Fuel Storage Installation - Formal Announcement of New Tsfst Manager2020-03-31031 March 2020 Independent Spent Fuel Storage Installation - Formal Announcement of New Tsfst Manager CY-20-004, Independent Spent Fuel Storage Installation - Funding Report for Managing Irradiated Fuel and GTCC Waste2020-03-17017 March 2020 Independent Spent Fuel Storage Installation - Funding Report for Managing Irradiated Fuel and GTCC Waste CY-20-003, Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report2020-03-12012 March 2020 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report CY-20-002, Independent Spent Fuel Storage Installation, Letter Notifying NRC the Amount of Property Insurance Coverage in Force for 20202020-01-22022 January 2020 Independent Spent Fuel Storage Installation, Letter Notifying NRC the Amount of Property Insurance Coverage in Force for 2020 ML20015A5262020-01-15015 January 2020 Connecticut Yankee Atomic Power Company - Independent Spent Fuel Storage Installation Security Inspection Plan ML19269C4642019-10-11011 October 2019 Letter to B. Mitchell Exemption from 10 CFR 72.212 and 72.214 for Dry Spent Fuel Storage Activities - Haddam Neck Plant Independent Spent Fuel Storage Installation CY-19-014, Independent Spent Fuel Storage Installation - Formal Announcement of ISFSI Manager'S Return2019-06-0505 June 2019 Independent Spent Fuel Storage Installation - Formal Announcement of ISFSI Manager'S Return CY-19-012, Independent Spent Fuel Storage Installation - 2018 Individual Monitoring NRC Form 5 Report2019-04-23023 April 2019 Independent Spent Fuel Storage Installation - 2018 Individual Monitoring NRC Form 5 Report ML19070A0332019-02-20020 February 2019 Letter to C. Pizzella Nuclear Regulatory Commission'S Analysis of Connecticut Yankee Atomic Power Company'S Initial and Updated Decommissioning Funding Plans for the Haddam Neck Plant Independent Spent Fuel Storage Installation CY-18-021, Connecticut Yankee Atomic Power Company Haddam Neck Plant Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan2018-12-10010 December 2018 Connecticut Yankee Atomic Power Company Haddam Neck Plant Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan IR 05000213/20180012018-05-31031 May 2018 NRC Independent Spent Fuel Storage Installation Inspection Report Nos. 07200039/2018001 and 05000213/2018001, Connecticut Yankee Atomic Power Company, East Hampton, Connecticut Site IR 07200039/20184012018-05-17017 May 2018 Connecticut Yankee Atomic Power Company Independent Spent Fuel Storage Security Inspection Report No. 07200039/2018401 - (Cover Letter Only) CY-18-004, Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report2018-03-0505 March 2018 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report 2024-08-27
[Table view] |
Text
I.39 CONNECTICUT YANKEE ATOMIC POWER COMPANY HADDAM NECK PLANT 362 INJUN HOLLOW ROAD 9 EAST HAMPTON, CT 06424-3099 March 15, 2011 CY-1 1-009 Docket No. 50-213 Re: 10 CFR 50.75(f)U. S. Nuclear Regulatory Commission Attention:
Document Control Desk Washington, DC 20555
Reference:
Subject:
Gentlemen: (a) License No. DPR-61 (Docket No. 50-213)(b) Letter: CYAPCO to USNRC; Haddam Neck. Plant Certifications Of Permanent Cessation of Power Operation and that Fuel has been Permanently Removed From the Reactor, dated December 5, 1996 (c) Letter: USNRC to Wayne Norton; Haddam Neck Plant -Release of Land from Part 50 License, dated November 26, 2007 (d) USNRC Regulatory Issue Summary (RIS) 2001-07, REV 1 Decommissioning Funding Assurance Status Report- 1OCFR 50.75 In reference (b) Connecticut Yankee Atomic Power Company (CYAPCO) informed the USNRC that the Board of Directors of CYAPCO had decided to permanently cease operations at the Haddam Neck Plant and that fuel had been permanently removed from the reactor. In accordance with 1 OCFR 50.82(a)(2) the certifications in the letter modified the CYAPCO license to permanently withdraw CYAPCO's authority to operate the reactor. In 1996, CYAPCO commenced decommissioning the power plant. In Reference (c), the NRC amended the CYAPCO license, releasing most of the formerly licensed land for unrestricted use, shrinking the licensed land to the ISFSI only.Presently, CYAPCO is storing spent nuclear fuel and other high level waste on site until it is assumed to be removed by the DOE in 2021, through the final decommissioning of the Independent Fuel Storage Installation (ISFSI) in 2023.In accordance with the requirements of 10 CFR 50.75, direction provided by the NRC staff on March 5, 2008 and recent RIS 2001-07, Rev 1 regulatory clarification, CYAPCO hereby submits its report on the status of decommissioning funding for the year ending December 31, 2010 for CYAPCO. Attachment 1 provides the requested information.
If you should have any questions, please contact me at (860) 267-6426 x304.Carla M. Pizzella, Treasurl Date USNRC CY-1 1-009/Page 2 Attachment 1 -"NRC Decommissioning Funding Status Report" cc: J. Joustra, Chief, Decommissioning Branch, Region I W. Dean, NRC Regional Administrator, Region 1 J. Goshen, NRC Project Manager, Haddam Neck Plant E. L. Wilds, Jr., Director, CT DEP, Radiation Division CY-1 1-009 Attachment 1 NRC Decommissioning Funding Status Report March 2011 USNRC CY-1 1-009/Attachment 1/Page 1 Attachment I NRC Decommissioning Funding Status Report Connecticut Yankee -Haddam Neck Plant (Status as of 12/31/10)1. The amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c)2. The amount accumulated at the end of the calendar year preceding the date of the report for items included in 10 CFR 50.75 (e)(1)(i).
- 3. Schedule of the annual amounts remaining to be collected Including amounts beyond those required in 10 CFR 50. 75(e)(1)(i)
$144.9 million 1$197.2 million 2$40.9 million 3 (2011-2014)
$43.7 million (2015)1 Since the original power plant has been decommissioned and the license amended, the only remaining decommissioning as defined by the NRC in 10 CFR 50.75 is decontamination and dismantlement of the ISFSI once the fuel is removed.The Site-Specific Cost Estimate for future costs beyond 2010 is $144.9 million (in 2010 dollars) and includes the current estimate for spent fuel management costs, i.e. Long-term ISFSI operations through 2023 ($136.6 million) and D&D of the ISFSI ($8.3 million).2 This accrued market value balance includes amounts in the Decommissioning Trust for all decommissioning costs including site restoration and long-term spent fuel storage as well as decommissioning as defined in 10 CFR 50.75. Since the original power plant has been decommissioned and the license amended, the only remaining decommissioning is decontamination and dismantlement of the ISFSI (estimated at $8.3 million of the current market value balance) once the fuel is removed.3 CYAPCO revised its annual decommissioning collection rates effective October 1, 2008 continuing through 2015, based on the decommissioning cost reconciliation!PBOP/true-up rate filing and settlement submitted with the FERC on July 31, 2008 and accepted on September 10, 2008. On October 13, 2010, CYAPCO submitted its decommissioning cost estimate and schedule of decommissioning charges, ("2010 Rate Filing"), as it had committed to do in the 2006 Settlement.
The 2010 Rate Filing demonstrated that, after escalating costs to 2010 dollars and adjusting for the fact that the costs of the first part of the waste storage included in the 2006 Estimate have already been incurred, the 2006 Estimate remains a reasonable projection of costs upon which the Company may rely in calculating the rates necessary to fund the NDT. The 2010 Rate Filing noted ongoing uncertainties regarding prospective damage awards obtained from litigation with the Department of Energy ("DOE"), offsets to CYAPCO's funding needs, the DOE's commitment to remove CYAPCO's nuclear waste, and the timing of these key events. In light of these unknowns, along with the fact that the 2006 Settlement committed CYAPCO to file another update of decommissioning costs and charges by 2014, CYAPCO proposed to maintain its current level of collections.
On December 20, 2010, FERC issued an order accepting the 2010 Rate Filing and and granted CYAPCO's requested effective date of January 1, 2011.
USNRC CY-1 1-009/Attachment 1/Page 2 Attachment I NRC Decommissioning Funding Status Report Connecticut Yankee -Haddam Neck Plant (Status as of 12131110)4. The assumptions used regarding escalation of the decommissioning cost estimate, rates of earnings on decommissioning funds, and rates of other factors used in funding projections are: Annual escalation rate 2.5%Annual after-tax earnings rate on decommissioning trust funds 4.4%Other factors assumed None 5. Any contracts upon which the licensee is relying pursuant to 10 CFR 50. 75(e)(1)(ii)(A)
CYAPCO is currently collecting funds through its power contracts and amendatory agreements under FERC regulation.
The power contracts and the amendatory agreements specify the obligations of the purchasers for the costs of the HNP Including, decommissioning costs. Such contracts have been filed with FERC.6. Any modifications to a licensee's current method of providing financial assurance occurring since the last submitted report. None 7. Any material changes to trust agreements.
None As noted in the Decommissioning Funding Assurance Status Report dated March 9, 2010, effective January 1, 2010, CYAPCO changed its Nuclear Decommissioning Fund Trustee from Bank of New York Mellon to Bank of America. Although the Trustee changed, there were no material changes to the trust agreements.