|
---|
Category:Deficiency Report (per 10CFR50.55e and Part 21)
MONTHYEARML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23241A0022023-08-25025 August 2023 Paragon Final Part 21 Report on Defect with Eaton/Cutler Hammer Size 4 and 5 Freedom Series Contactors Modified by Paragon with Special Coils And/Or with RTV to Improve the Securing of Shading Coils ML23221A3702023-08-0303 August 2023 Paragon Energy Solutions, 10CFR Part 21 Initial Notification: P21-08032023-IN, Rev. 0 ML23066A2212023-03-0707 March 2023 Velan, Inc. - Revised Part 21 Notification Re Butterfly Valves Found to Have a Number of Fasteners Loose ML23038A0192023-02-0606 February 2023 Curtiss-Wright Part 21 Notification for Qualtech Np Supplied Eaton TMR5 Timing Relays ML22341A0322022-11-30030 November 2022 10 CFR Part 21 Notification from Curtiss-Wright Nuclear Division for Qualtech Np Supplied Eaton TRM5 Timing Relays ML21260A0072021-09-0909 September 2021 Ametek Solidstate Controls, Notification of Potential Defect - 10CFR Part 21 Report Re Omron Timer Relay ML21225A0812021-08-0404 August 2021 Lake Engineering Co., Final Report Per 10 CFR Part 21 Degraded Snubber SF1154 Hydraulic Fluid Batch No. 17BLVS293 ML21181A2202021-06-29029 June 2021 Part 21 Written Notification - P21-03302021 Rev. 2 - Failures of Size 1 and 2 Freedom Series Full Voltage Reversing Starters ML21168A2172021-06-17017 June 2021 GE Hitachi Nuclear Energy Americas, LLC - 10 CFR Part 21.21(d)-Reportable Condition: Fuel Support Side Entry Orifice Meta-Stable Flow for 2 Beam Locations in the BWR/6 Reactors M210077, GE Hitachi Nuclear Energy Americas, LLC - 10 CFR Part 21.21(d)-Reportable Condition: Fuel Support Side Entry Orifice Meta-Stable Flow for 2 Beam Locations in the BWR/6 Reactors2021-06-17017 June 2021 GE Hitachi Nuclear Energy Americas, LLC - 10 CFR Part 21.21(d)-Reportable Condition: Fuel Support Side Entry Orifice Meta-Stable Flow for 2 Beam Locations in the BWR/6 Reactors ML21126A1722021-04-29029 April 2021 Paragon Energy Solutions Failures of Size 1 and 2 Freedom Series Full Voltage Reversing Starters ML20366A0482020-12-0707 December 2020 10CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10 CFR21-0114, Rev. 1 ML21014A2342020-12-0707 December 2020 Fourth Interim Notification Per 10 CFR Part 21 Re Degraded Snubber SF1154 Hydraulic Fluid Batch No. 17BLVS293 ML20366A0472020-11-18018 November 2020 Curtiss-Wright 10 CFR Part 21 Notification for SF-1154 Hydraulic Fluid Batch 17BLVS293 M200087, GE-Hitachi Nuclear Energy Americas, LLC - 10 CFR Part 21.21(d)-Reportable Condition: Non-Conservative BWR/6 Side Entry Orifice (SEO) Loss Coefficients2020-06-24024 June 2020 GE-Hitachi Nuclear Energy Americas, LLC - 10 CFR Part 21.21(d)-Reportable Condition: Non-Conservative BWR/6 Side Entry Orifice (SEO) Loss Coefficients ML20176A4322020-06-24024 June 2020 GE-Hitachi Nuclear Energy Americas, LLC - 10 CFR Part 21.21(d)-Reportable Condition: Non-Conservative BWR/6 Side Entry Orifice (SEO) Loss Coefficients ML20136A2552020-04-21021 April 2020 10 CFR Part 21 Report Notification for Curtiss Wright Scientech Certain RTL500 and RTL851 Modules ML20049A0752020-02-11011 February 2020 C&D Technologies, Inc. -10 CFR Part 21 Evaluation Regarding Container Failure in KCR-07 Batteries ML19317D0932019-10-25025 October 2019 Engine Systems, Inc., 10CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10 CFR21-0127, Rev. 0, Emd Fuel Injectors - Seized Plunger and Bushing ML19121A1552019-04-15015 April 2019 Curtiss-Wright Nuclear Division, Enertech - 10 CFR Part 21 Notification for SF-1154 Hydraulic Fluid ML18353A4282018-11-30030 November 2018 Engine Systems, Inc., 10CFR21-0123, Rev. 0, for a 10CFR21 Reportable Condition on Emd Fuel and Soakback Pumps ML17194A8252017-07-11011 July 2017 Part 21 Report Re Wedge Pin Failure in Anchor Darling Motor Operated Double Disc Gate Valves with Threaded Stem to Upper Wedge Connections ML17090A3982017-03-27027 March 2017 Engine Systems, Inc. - Part 21 Report Regarding Identification of Failed Diode Surge Suppressor with Internal Manufacturing Defect ML17081A4532017-03-20020 March 2017 Part 21 - Plastic Jar Dedication Sampling ML17055C1772017-02-0909 February 2017 10 CFR 21 Evaluation Regarding Design Basis Calculation Error Using FL0-2D Software ML17026A4142017-01-20020 January 2017 C&D Technologies, Inc. - Part 21 - Plastic Jar Dedication Sampling ML17032A0802016-12-30030 December 2016 Engine Systems, Inc., 10CFR21 Reporting of Defects and Non-Compliance, Report No. 10CFR21-0114, Rev. 0 ML17006A0102016-12-29029 December 2016 Engine Systems, Inc. - Part 21 Issues Identified with the Enterprise Diesel Engine Subcover ML17006A0142016-12-13013 December 2016 Enercon - Part 21 - Notification-Design Basis Errors Using Flo-2D Software ML16342A9812016-11-23023 November 2016 Enercon - Part 21 Notification - Design Basis Errors Using FLO-2D Software ML16278A4712016-09-22022 September 2016 Notification of 10 CFR Part 21 Condition, Masterpact Breaker Fail to Close ML16281A2702016-09-22022 September 2016 Part 21 - Initial Notification of Masterpact Breaker Fail to Close ML16251A0982016-09-0202 September 2016 Part 21 - Potential Failure of Battery System Connections ML16252A2742016-08-29029 August 2016 Azz/Nli - Part 21 Report - Potential Allen Bradley Timing Relay ML16243A4742016-08-26026 August 2016 Potential Part 21 Unqualified Component in Certain Allen Bradley Timing Relays ML16232A6042016-08-15015 August 2016 Potentially Unqualified Component in Certain Allen Bradley Timing Relays ML16238A1862016-08-15015 August 2016 Update - Report of Potential l0CFR Part 21, Allen Bradley Timing Relay Model 700RTC-NRC Event Number 51030, Accession Number ML15134A016 ML16188A3742016-06-30030 June 2016 Part 21 - Inadequate Swaging and Adherence of Silicone O-Ring and Silicone PAD Soft Seat Main Disc and Pilot Disc Assemblies ML16154A2072016-05-26026 May 2016 Part 21, Azz/Nli Nuclear Logistics, Inc., Potentially Unqualified Component in Certain Allen Bradley Timing Relays Model 700RTC ML16139A8322016-05-13013 May 2016 Part 21 - Initial Notification of Masterpact Breaker Fail to Close ML16139A8332016-05-13013 May 2016 Part 21 - Initial Notification of Masterpact Breaker Fail to Close ML16111A4202016-04-0808 April 2016 Part 21 Report No. P21-04302015, Rev. 1 Regarding Potentially Unqualified Component in Certain Allen Bradley Timing Relays, Per Browns Ferry, Ginna, Millstone, Nine Mile Point, North Anna, Ft. Calhoun, Perry, River Bend, South Texas Project ML16098A4462016-03-22022 March 2016 United Controls International - Part 21 Report Regarding Defective Fuses, Per Perry Nuclear Power Plant ML15217A3032015-08-0404 August 2015 Notification of Part 21 - Report - Ferraz Shawmut/Mersen Fuses P/N: AJT25 and AJT60 ML15205A2892015-07-24024 July 2015 Notification of Part 21 Report - Deviation in Nozzle Modeling Internal Reports ML15188A0662015-06-25025 June 2015 Part 21 Report - Deviation in Nozzle Modeling Internal Reports ML15140A2182015-05-11011 May 2015 Part 21 Report Regarding Defect Identified 6 Inch Gear Operated Ball Valves (Part Number GBV-B2-60-0020 & GBV-B2-60-0112), Notification No. 15-1 ML15134A0162015-05-0101 May 2015 Part 21 Report Regarding Potentially Unqualified Component in Certain Allen Bradley Timing Relays ML15159A5682015-04-30030 April 2015 Report of Potential 10CFR Part 21, Allen Bradley Timing Relay Model 700RTC 2023-08-03
[Table view] |
Text
Notification No. 15-1 Page l of`2 10 CFR Part 21 Report Defect Identified 6" Gear Operated Ball Valves (Part Number GBV-B2-60-0020
& GBV-B2-60-0112)
In accordance with I0 CFR Part 21.21(d)(4(i)-(ix), BNL Industries, Inc. (BNL) provides the following written notification: (i) Name and address of the individual or individuals informing the Commission.
Jeffrey Jacobs BNL Industries, Inc.30 Industrial Park Rd.Vernon, CT 06066 (ii) Identification of the facility, the activity, or the basic component supplied for such facility or such activity within the United States which rails to comply or contains a defect.The following are the basic components which are the subject of this notification:
First Energy -Perry -- (PO 45467911, Item 00001, Mat. No. 100100014)-
P/N GBV-B2-60-0020 PC. 3, Serial Number A 150217- I -I (Trace Number 547G- I)First Energy -Beaver Valley -(PO 45459398, Item 00023, Mat. No. 100095602)
-GBV-B2-60-0112 PC.3, Serial Numbers A 141009-23-3, A 141009-23-4, A 14,1009-23-5, A 141009-23-6 (Trace Number 547G- 1)No addition defective material has been supplied and no other facilities are affected.(iii) Identification of the firm constructing the facility or supplying the basic component which fails to comply or contains a defect.BNL Industries, Inc.30 Industrial Park Rd.Vernon, CT 06066 (iv) Nature of the defect or failure to comply and the safety hazard which is created or could be created by such defect or failure to comply.On May 1, 2015 BNL identified a discrepant condition in which material was identified by an audited third-party material testing facility as meeting the requirements of ASME SA-105, despite having a test yield strength of 35.6ksi (vice 36k required by the specification).
The discrepant material has already been manufactured and incorporated into a basic component and shipped to the end users.Based on BNL engineering evaluations of the design criteria, code requirements and supplied material, BNL has determined there to be no safety hazard. Engineering evaluations EE-A 150217 Rev. 0 and EE-A 141009-23 Rev. 0 are being supplied to the purchasers.(v) The date on which the information of such defect or failure to comply was obtained.May 01, 2015 Page 2 of 2 (vi) In the case of a basic component which contains a defect or fails to comply, the number and location of these components in use at, supplied for, being supplied for, or may be supplied for, manufactured, or being manufactured for one or more facilities or activities subject to the regulations in this part.First Energy -Perry- I endcap supplied, P/N GBV-B2-60-0020 PC. 3, Serial Number AI50217-1-1 (Trace Number 547G-1)First Energy -Beaver Valley -7 endcaps supplied, GBV-B2-60-0112 PC. 3, Serial Numbers A 141009 3 (2pcs.), A141009-23-4 (2pcs.), A141009-23-5 (2pcs.), A141009-23-6 (lpc.) (Trace Number 547G-1)(vii) The corrective action which has been, is being, or will be taken; the name of the individual or organization responsible for the action; and the length of time that has been or will be taken to complete the action.Following identification of the discrepant material, BNL performed a review of all material test reports from the third part material testing facility.
Trace number 547G-I was the only discrepant material found.Concurrently, BNL performed engineering evaluations EE-A 150217 Rev. 0 and EE-A 141009-23 Rev. 0 to determine the impact on the design suitability.
Based on the evaluations, the design is acceptable as is.BNL has initiated a request for corrective action (RCA 0121), which will require all material test certifications to receive a secondary review. This action has been implemented immediately.(viii) Any advice related to the defect or failure to comply about the facility, activity, or basic component that has been, is being, or will be given to purchasers or licensees.
The following Engineering Evaluations will be supplied to the purchaser:
First Energy -Perry -EE-A 150217 Rev. 0 First Energy -Beaver Valley -EE-A 141009-23 Rev. 0 (ix) In the case of an early site permit, the entities to whom an early site permit was transferred.
This is not an early site permit concern.Engineering Supervisor