Verification Letter for the Approved Version of NEDC-33840P (Prime)
ML17341A943
Person / Time
Site: PROJ0710, 99902024
Issue date: 01/05/2018
From: Morey D C
NRC/NRR/DLP/PLPB
To: Head J G
GE-Hitachi Nuclear Energy Americas
Golla J A
References
EPID L-2016-TOP-0003
Download: ML17341A943 (3)


Text

January 5, 2018

Mr. Jerald G. Head Senior Vice President, Regulatory Affairs

GE-Hitachi Nuclear Energy Americas, LLC P.O. Box 780, M/C A-18 Wilmington, NC 28401-0780

SUBJECT:

VERIFICATION OF THE APPROVAL VERSION OF GLOBAL NUCLEAR FUEL - AMERICAS TOPICAL REPORT NEDC-33840P, REVISION 0, "THE PRIME MODEL FOR TRANSIENT ANALYSIS OF FUEL ROD THERMAL - MECHANICAL PERFORMANCE" (EPID NO. L-2016-TOP-0003)

Dear Mr. Head:

By letter dated August 18, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17230A010), Global Nuclear Fuel - Americas (GNF) submitted an approval ("-A") version of Topical Report (TR) NEDC-33840P, Revision 0, "The PRIME Model for Transient Analysis of Fuel Rod Thermal - Mechanical Performance," to the U.S. Nuclear

Regulatory Commission (NRC) staff. GNF has done so in accordance with our request to publish an approved version of this TR, as detail ed in the transmittal letter of the NRC staff's final safety evaluation (SE) (ADAMS Accession No. ML17159A806) of the original TR. It is understood that the approval version of NEDC-33840P, Revision 0, is designated as NEDC-33840P-A, Revision 1.

The NRC staff has completed its review of the approval version of the TR. The NRC staff verified that Global Nuclear Fuel has met the requirements and determined that the submitted -A version is acceptable for referencing in licensing applications for nuclear power plants to the extent specified and under the limitations delineated in the approval version of the TR.

TR NEDC-33840P-A, Revision 1, "The PRIME Model for Transient Analysis of Fuel Rod Thermal - Mechanical Performance," is now approved for use in future licensing actions as specified in the final SE.

Please contact Joseph A. Golla at (301) 415-1002, if you have any questions on this subject.

Sincerely, /RA/ Dennis C. Morey, Chief Licensing Processes Branch Division of Licensing Projects Office of Nuclear Reactor Regulation

Docket No. 99902024 GE-Hitachi Nuclear Energy Americas Project No. 710

cc: Mr. James F. Harrison

GE-Hitachi Nuclear Energy Americas LLC Vice President - Fuel Licensing P.O. Box 780, M/C A-55

Wilmington, NC 28401-0780 james.harrison@ge.com Ms. Patricia L. Campbell Vice President, Washington Regulatory Affairs

GE-Hitachi Nuclear Energy Americas LLC 1299 Pennsylvania Avenue, NW, 9 th Floor Washington, DC 20004 patriciaL.campbell@ge.com

Mr. Brian R. Moore General Manager, Core & Fuel Engineering Global Nuclear Fuel-Americas, LLC P.O. Box 780, M/C A-75

Wilmington, NC 28401-0780 Brian.Moore@gnf.com

ML17341A943; *concurred via e-mail NRR-106 OFFICE NRR/DLP/PLPB/PM NRR/DLP/PLPB/LA* NRR/DSS/SNPB NRR/DLP/PLPB/BC NAME JGolla DHarrison RLukes DMorey DATE 1/3/2018 12/19/2017 1/3/2018 1/5/2018