Perry Nuclear Power Plant, Unit No. 1 - Withdrawal of Requested Licensing Action 10 CFR 50.55A Relief Requests in Support of the Third 10-year in-service Inspection Interval, IR-009, Revision 1
ML120200454
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 01/31/2012
From: Michael Mahoney
Plant Licensing Branch III
To: Kaminskas V A
FirstEnergy Nuclear Operating Co
mahoney, m NRR/DORL/LPLIII-2 415-3867
References
TAC ME5378
Download: ML120200454 (2)


Text

UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 January 31,2012 Mr. Vito A. Kaminskas Site Vice President FirstEnergy Nuclear Operating Company Mail Stop A-PY-A290 P.O. Box 97,10 Center Road Perry, OH 44081-0097 PERRY NUCLEAR POWER PLANT, UNIT NO.1 -WITHDRAWAL OF REQUESTED LICENSING ACTION RE: 10 CFR 50.55A RELIEF REQUESTS IN SUPPORT OF THE THIRD 10-YEAR IN-SERVICE INSPECTION INTERVAL, IR-009, REVISION 2 (TAC NO. ME5378)

Dear Mr. Kaminskas:

By letter dated January 24, 2011 (Agency Documents Access and Management System (ADAMS) Accession No. ML 110320065), FirstEnergy Nuclear Operating Company (FENOC) submitted nine separate relief requests associate with the Perry Nuclear Power Plant, Unit 1, Inservice Inspection Program. By letter dated January 30, 2012, FENOC requested to withdraw one of the nine relief requests from U.S. Nuclear Regulatory Commission (NRC) review, specifically, IR-009, Revision 2. The NRC acknowledges your request to withdraw the application. NRC staff activities on the review for the subject Technical Assignment Control (TAC) number have ceased and TAC No. ME5378 has been closed. If you have any questions, please contact me at (301) 415-3867 or by email at michael. mahoney@nrc.gov. SfhI//; / Michael Mahoney, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-440 cc: Distribution via Listserv January 31, 2012 Mr. Vito A. Kaminskas Site Vice President FirstEnergy Nuclear Operating Company Mail Stop A-PY-A290 P.O. Box 97,10 Center Road Perry,OH 44081-0097 PERRY NUCLEAR POWER PLANT, UNIT NO.1 -WITHDRAWAL OF REQUESTED LICENSING ACTION RE: 10 CFR 50.55A RELIEF REQUESTS IN SUPPORT OF THE THIRD 10-YEAR IN-SERVICE INSPECTION INTERVAL, IR-009, REVISION 2 (TAC NO. ME5378)

Dear Mr. Kaminskas:

By letter dated January 24, 2011 (Agency Documents Access and Management System (ADAMS) Accession No. ML 110320065), FirstEnergy Nuclear Operating Company (FENOC) submitted nine separate relief requests associate with the Perry Nuclear Power Plant, Unit 1, Inservice Inspection Program. By letter dated January 30, 2012, FENOC requested to withdraw one of the nine relief requests from U.S. Nuclear Regulatory Commission (NRC) review, specifically, IR-009, Revision 2. The NRC acknowleqges your request to withdraw the application. NRC staff activities on the review for the subject Technical Assignment Control (TAC) number have ceased and TAC No. ME5378 has been closed. If you have any questions, please contact me at (301) 415-3867 or by email at michael.mahoney@nrc.gov. Sincerely, IRA! Michael Mahoney, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-440 cc: Distribution via Listserv DISTRIBUTION: PUBLIC RidsNrrDorl Resource LPL3-2 rlf RidsNrrDorlLpl3-2 Resource RidsAcrsAcnw_MailCTR Resource RidsNrrDoriDpr Resource RidsNrrLASRohrer Resource RidsNrrPMPerry Resource RidsOgcRp Resource TMcLellan, NRR RidsRgn3MailCenter Resource RidsNrrDciCvib Resource ADAMS Accession No. ML 120200454 NRR-106 OFFICE DORULPL3-2/PM DORULPL3-21LA DORULPL3-21BC DORULPL3-21PM SRohrer JZimmermanNAME MMahoney 1/31/12 1131112DATE 1131/12 OFFICIAL RECORD