UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 31,2012 Mr. Vito A. Kaminskas Site Vice President FirstEnergy Nuclear Operating Company Mail Stop A-PY-A290 P.O. Box 97,10 Center Road Perry, OH 44081-0097
SUBJECT:
PERRY NUCLEAR POWER PLANT, UNIT NO.1 - WITHDRAWAL OF REQUESTED LICENSING ACTION RE: 10 CFR 50.55A RELIEF REQUESTS IN SUPPORT OF THE THIRD 10-YEAR IN-SERVICE INSPECTION INTERVAL, IR-009, REVISION 2 (TAC NO. ME5378)
Dear Mr. Kaminskas:
By letter dated January 24, 2011 (Agency Documents Access and Management System (ADAMS) Accession No. ML110320065), FirstEnergy Nuclear Operating Company (FENOC) submitted nine separate relief requests associate with the Perry Nuclear Power Plant, Unit 1, Inservice Inspection Program.
By letter dated January 30, 2012, FENOC requested to withdraw one of the nine relief requests from U.S. Nuclear Regulatory Commission (NRC) review, specifically, IR-009, Revision 2. The NRC acknowledges your request to withdraw the application. NRC staff activities on the review for the subject Technical Assignment Control (TAC) number have ceased and TAC No. ME5378 has been closed.
If you have any questions, please contact me at (301) 415-3867 or by email at michael. mahoney@nrc.gov.
SfhI//;
/
Michael Mahoney, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-440 cc: Distribution via Listserv
ML120200454 NRR-106 OFFICE DORULPL3-2/PM DORULPL3-21LA DORULPL3-21BC DORULPL3-21PM SRohrer JZimmerman NAME MMahoney 1/31/12 1131112 DATE 1131/12