W3F1-2005-0005, 90 Day Response to GL-04-002, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors

From kanterella
Revision as of 21:40, 15 January 2025 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

90 Day Response to GL-04-002, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors
ML050660261
Person / Time
Site: Waterford Entergy icon.png
Issue date: 03/03/2005
From: Harris A
Entergy Nuclear South, Entergy Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
W3F1-2005-0005, GL-04-002 W3F1-2005-0005
Download: ML050660261 (5)


Text

.

i A-Entergy Entergy Nuclear South Entergy Operations, Inc.

17265 River Road Killona, LA 70057-3093 Tel 504-739-6475 Fax 504-739-6698 aharrisXentergy.com Alan J. Harris Director. Nuclear Safety Assurance Waterford 3 W3FI-2005-0005 March 3, 2005 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

Subject:

90 Day Response to Generic Letter 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors" Waterford Steam Electric Station, Unit 3 (Waterford 3)

Docket No. 50-382 License No. NPF-38

Dear Sir or Madam:

By letter dated September 13, 2004, the NRC requested licensees to provide a response within 90 days of the date of the safety evaluation report (SER) providing the guidance for performing the requested actions in the subject generic letter (GL). Entergy will utilize the methodology in Nuclear Energy Institute (NEI) 04-07, Pressurized-Water Reactor(PWR)

Sump Performance Evaluation Methodology, Revision 0 with guidance provided in the NRC SER dated December 6, 2004. This methodology will be used in the analyses to evaluate the susceptibility of the emergency core cooling system (ECCS) and the containment spray system (CSS) recirculation functions for Waterford-3 to the adverse effects of post-accident debris blockage and operation with debris-laden fluids identified in the GL. Entergy plans to utilize NEI 04-07 with the exception of conflicts with our current licensing basis (not associated with the ECCS sump analyses) and the planned exceptions described below.

Other exceptions that may be taken in the analyses will be described and justified in the September 1, 2005, required response.

  • Additional testing and/or evaluation of existing data relative to qualified and unqualified coatings are planned by the Electric Power Research Institute (EPRI) and industry owners' groups. These future test and evaluation results may be used in Waterford-3's debris generation analysis.

NEI 04-07 does not provide specific guidance for evaluating the chemical precipitation effects. NRC/EPRI tests for chemical precipitation are in progress.

The significance of chemical precipitant and the methodology for head loss to account for the chemical precipitants is currently not developed. Entergy plans to use future test results and industry/NRC guidance to account for chemical precipitant effects in the net positive suction head (NPSH) analysis.

Ao\\

W3Fl-2005-0005 Page 2 NEI 04-07 does not provide specific guidance for evaluating downstream effects.

Entergy plans to evaluate the downstream effects by identifying the downstream components that are susceptible to blockage and the minimum clearance for flow through these components. The long-term performance degradation due to wear of susceptible downstream components and sub-components will also be evaluated.

Entergy plans to use industry owners' group guidance and component manufacturer data to evaluate long-term performance degradation due to wear caused by debris-laden fluid.

The analyses based on NEI 04-07 for the current plant configuration, including an NPSH loss analysis, will be completed by September 1, 2005. The evaluation of chemical effects and downstream effects may occur after September 1, 2005, depending on the schedule for testing and availability of industry guidance. The final NPSH loss analysis, if strainer modifications are required, will be completed as part of the sump strainer modification.

Containment walkdowns have been performed for Waterford-3 in the fall of 2003 utilizing NEI 02-01, Condition Assessment Guidelines, Debris Sources Inside PWR Containments, to support the analysis of susceptibility of the ECCS and CSS recirculation functions to the adverse effects of debris blockage identified in the GL. A dust and lint sampling will be collected for Waterford-3 in the spring of 2005.

The new commitments contained in this submittal are summarized in the attachment.

Should you have any questions concerning this submittal, please contact Mr. Greg Scott at (504) 739-6703.

I declare under penalty of perjury that the foregoing is true and correct. Executed on March 3, 2005.

Sincerely, ALH/gcs h

Attachment

W3Fl-2005-0005 Page 3 cc:

Dr. Bruce S. Mallett Regional Administrator U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 NRC Senior Resident Inspector Waterford Steam Electric Station Unit 3 P.O. Box 822 Killona, LA 70066-0751 U. S. Nuclear Regulatory Commission Attn: Mr. N. Kalyanam Mail Stop O-07D1 Washington, DC 20555-0001 Wise, Carter, Child & Caraway ATTN: J. Smith P.O. Box 651 Jackson, MS 39205 Winston & Strawn ATTN: N.S. Reynolds 1400 L Street, NW Washington, DC 20005-3502

Attachment to W3FI -2005-0005 List of Regulatory Commitments

Attachment W3Fl-2005-0005 Page 1 of 1 List of Regulatory Commitments The following table identifies those actions committed to by Entergy in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments.

TYPekoE)

SCHEDULED ONE-heck One)

COMPLETION TIME CONTINUING DATE COMMITMENT ACTION COMPLIANCE (If Required)

By letter dated September 13, 2004, the X

September 1, 2005 NRC requested licensees to provide a response within 90 days of the date of the SER providing the guidance for performing the requested actions in the GL. Entergy will utilize the methodology in NEI 04-07, PWR Sump Performance Evaluation Methodology, Revision 0 with guidance provided in the NRC SER dated December 6, 2004. This methodology will be used in the analyses to evaluate the susceptibility of the ECCS and the CSS recirculation functions for Waterford-3 to the adverse effects of post-accident debris blockage and operation with debris-laden fluids identified in the GL.

Other exceptions that may be taken in the analyses will be described and justified in the September 1, 2005, required response.

The analyses based on NEI 04-07 for the current plant configuration, including an NPSH loss analysis, will be completed by September 1, 2005.

The final NPSH loss analysis, if strainer X

December 31, 2007 modifications are required, will be completed as part of the sump strainer modification.

A dust and lint sampling will be collected for X

June 21, 2005 Waterford-3 in the spring of 2005.