MONTHYEARW3F1-2004-0075, Reissue of Report BAW-2177, Analysis of Capsule W-97 Entergy Operations, Inc. Waterford Generating Station Unit 3 - Reactor Vessel Material Surveillance Program2004-09-13013 September 2004 Reissue of Report BAW-2177, Analysis of Capsule W-97 Entergy Operations, Inc. Waterford Generating Station Unit 3 - Reactor Vessel Material Surveillance Program Project stage: Request W3F1-2005-0005, 90 Day Response to GL-04-002, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors2005-03-0303 March 2005 90 Day Response to GL-04-002, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Request ML0515305472005-05-27027 May 2005 RAI Related to GL 2004-02, Potential Impact of Debris Blockage on Emergency Sump Recirculation at pressurized-water Reactors Project stage: RAI ML0516605012005-06-0202 June 2005 RAI Related to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors Project stage: RAI ML0521402772005-07-28028 July 2005 Part 21 Deficiency Report Re Framatome Anp Supplied Pressurizer Heaters with Internals Manufactured by Thermocoax. Initially Reported on 07/22/05 Project stage: Request ML0603903862006-02-0909 February 2006 Request for Additional Information Response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design-Basis Accident at Pressurized-Water Reactors Project stage: RAI ML0733900652007-12-10010 December 2007 Approval of Extension Request, Corrective Actions Due Date, GL 2004-02 Potential Impact of Debris Blockage on Emergency Recirculation During Design-Basis Accidents at Pressurized Water Reactors Project stage: Other ML0801400072008-01-28028 January 2008 Report on Results of Staff Audit of Corrective Actions to Address GL 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design-Basis Accidents at PWRs Project stage: Other ML0801403182008-01-28028 January 2008 Staff Audit Report on Results of Corrective Actions to Address GSI-191 GL 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design-Basis Accidents at PWRs Project stage: Other ML0917302832009-06-11011 June 2009 Email, Draft Request for Additional Information Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design-Basis Accidents at Pressurized Water Reactors Project stage: Draft RAI ML0917302852009-06-11011 June 2009 Draft Request for Additional Information Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design-Basis Accidents at Pressurized Water Reactors Project stage: Draft RAI ML0920901072009-08-0606 August 2009 Notice of Conference Call with Entergy Operations, Inc. to Discuss Draft Request for Additional Information on Generic Letter 2004-02 for Waterford, Unit 3 Project stage: Draft RAI ML0925101242009-09-22022 September 2009 RAI, Regarding Supplemental Response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents Project stage: RAI ML0927200322009-10-0101 October 2009 Notice of Forthcoming Conference Call with Entergy Operations, Inc. to Discuss Waterford Steam Electric Station, Unit 3, Planned Response to Request for Additional Information on Generic Letter 2004-02 Project stage: RAI ML1005400832010-02-24024 February 2010 Forthcoming Conference Call with Entergy Operations, Inc. to Licensees Responses to NRC Generic Letter 2004-02 for Waterford Steam Electric Station, Unit 3 Project stage: Request ML1006903722010-03-0808 March 2010 Licensee Slides from 3/8/2010 Meeting Generic Letter 2004-02 Response to RAIs Project stage: Response to RAI ML1007003012010-04-0707 April 2010 Summary Follow-Up Conference Call with Entergy Operations, Inc. to Discuss Draft Response for Waterford, Unit 3, to the Request for Additional Information for Generic Letter 2004-02 Project stage: Draft RAI ML1013400612010-05-18018 May 2010 Notice of Forthcoming Conference Call with Entergy Operations, Inc. to Discuss Draft Response on GL-2004-02 for Waterford Steam Electric Station, Unit 3 Project stage: Draft Other ML1015204762010-06-0101 June 2010 Email, Request for Additional Information Regarding Supplemental Response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: RAI ML1015302322010-06-0909 June 2010 Summary of Conference Call Meeting with Entergy Operations, Inc. to Discuss Draft Response on GL-2004-02 for Waterford Steam Electric Station, Unit 3 ML1017301902010-06-17017 June 2010 Revised Responses to the Request for Additional Information Related to GL-2004-02 Project stage: Request ML1017301952010-06-17017 June 2010 Revised Responses to the NRCs Request for Additional Information Related to GL-2004-02 Project stage: Request ML1017302002010-06-17017 June 2010 Chemical Effects Summary Related to RAI Response to GL-2004-02 Project stage: Other W3F1-2010-0032, Response to Request for Additional Information Regarding Final Supplemental Response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors2010-11-23023 November 2010 Response to Request for Additional Information Regarding Final Supplemental Response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Supplement 2009-06-11
[Table View] |
Text
MEMORANDUM TO:
FROM:
SUBJECT:
DATE AND TIME:
LOCATIONS:
PURPOSE:
CATEGORY 1:*
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 1, 2009 Michael T. Markley, Chief Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Kaly N. Kalyanam, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation FORTHCOMING CONFERENCE CALL WITH ENTERGY OPERATIONS, INC.
Tuesday, October 15, 2009 8:30 a.m. - 4:30 p.m.
U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike, Room 0-7B04 Rockville, MD 20852 Generation Support Building Mechanical Work Room (2nd Floor)
Waterford Steam Electric Station, Unit 3 17265 River Road Killona, LA 70057-3093 The purpose of the conference call between the Entergy Operations, Inc. (Entergy, the licensee), and the U.S. Nuclear Regulatory Commission (NRC). Office of Nuclear Reactor Regulation (NRR) staff is to discuss the Waterford Steam Electric Station, Unit 3's planned response to the NRC "Request for Additional Information Regarding Supplemental Response to Generic Letter 2004-02, 'Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors'," dated September 22,2009 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML092510124); provide feedback on the licensee's plans and discuss any points of disagreement; and discuss the licensee's path forward.
This is a Category 1 meeting via conference call. The public is invited to participate in this meeting and will have one or more
- Commission's Policy Statement on Enhancing Public Participation in NRC Meetings (67 FR 36920), May 28, 2002.
M. Markley
- 2 opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.
PARTICIPANTS:
NRC Waterford 3 M. Scott, NRR Greg Ferguson J. Lehning, NRR Nick Petit S. Smith, NRR Brian Lanka N. Kalyanam, NRR John Russo et al.
Jim Furman (Contractor) et al.
Interested members of the public can participate in this meeting via a toll-free audio teleconference. Please call one of the meeting contacts listed below before October 13, 2009, 1:00 p.m.
(Eastern Savings Time) to get the telephone number and the pass code.
MEETING CONTACTS:
Kaly N. Kalyanam, NRR Alan Wang, NRR 301-415-1480 301-415-1445 kaly.kalyanam@nrc.gov alan.wang@nrc.gov Michael Mason, Entergy 504-739-6673 mmason@entergy.com The NRC provides reasonable accommodation to individuals with disabilities where appropriate.
If you need a reasonable accommodation to participate in a meeting, or need a meeting notice or a transcript or other information from a meeting in another format (e.g., Braille, large print),
please notify the NRC's meeting contact. Determinations on requests for reasonable accommodation will be made on a case-by-case basis.
To receive a summary of this meeting and begin receiving other plant-specific e-mail distributions, you must subscribe to the Operating Reactor Correspondence electronic distribution for this plant via http://www.nrc.gov/public-involve/listserver/plants-by-region.html.
Once subscribed, if you wish to discontinue receiving electronic distribution, you may unsubscribe at any time by visiting the same web address above.
Docket No. 50-382
Enclosure:
Agenda cc w/encl: Distribution via Listserv
AGENDA FORTHCOMING CONFERENCE CALL WITH ENTERGY OPERATIONS, INC. (ENTERGY)
AND U.S. NUCLEAR REGULATORY COMMISSION (NRC)
Tuesday, October 15, 2009 8:30 a.m. - 4:30 p.m.
- 1.
Introductions
- 2.
Discuss the Waterford Steam Electric Station, Unit 3's planned response to the NRC "Request for Additional Information Regarding Supplemental Response to Generic Letter 2004-02, 'Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors'," dated September 22,2009 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML092510124); provide feedback on the licensee's plans and discuss any points of disagreement; and discuss the licensee's path forward.
- 3.
Public Participation
- 4.
Adjourn Enclosure