(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Letter Sequence Approval |
---|
|
Results
Other: ML22341A615, ML23013A089, ML23052A087, ML23061A132, ML23065A048, ML23065A051, ML23065A052, ML23065A055, ML23065A056, ML23249A095, ML24024A009, ML24096B783, ML24162A093, ML24229A195
|
MONTHYEARML22313A0972022-11-18018 November 2022 Abilene Christian University (Acu) Molten Salt Research Reactor (Msrr) Construction Permit Application Acceptance Letter Project stage: Acceptance Review PMNS20221202, Public Meeting with Abilene Christian University (Acu)2022-11-21021 November 2022 Public Meeting with Abilene Christian University (Acu) Project stage: Request ML22341A6152022-12-16016 December 2022 Abilene Christian University (Acu) Molten Salt Research Reactor (Msrr) Construction Permit Application Review Schedule Letter Project stage: Other ML23013A0892023-01-13013 January 2023 NRR E-mail Capture - Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Technical Topics Project stage: Other ML23065A0562023-03-0202 March 2023 NRR E-mail Capture - Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapters 9.2 and 13 Project stage: Other ML23065A0522023-03-0202 March 2023 NRR E-mail Capture - Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapters 1, 5, 8, 9 (Except 9.2 and 9.6), 10, 11, 12, 14-18, and General Topics Project stage: Other ML23065A0512023-03-0202 March 2023 NRR E-mail Capture - Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapter 7 Project stage: Other ML23065A0482023-03-0202 March 2023 NRR E-mail Capture - Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapters 2 & 3 Project stage: Other ML23065A0552023-03-0202 March 2023 NRR E-mail Capture - Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapters 4, 6, and 9.6 Project stage: Other ML23061A1322023-03-0909 March 2023 Acu Lu, Vr, WR, Rh, Wm, TR, AC, Fc Info Needs Items Q2FY2023 Project stage: Other ML23052A0872023-03-0909 March 2023 Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Technical Topics Project stage: Other ML23065A3342023-05-0101 May 2023 Abilene Christian University - December 9, 2022, Public Meeting Summary Regarding Discussion on Technical Focus Areas Project stage: Meeting ML23249A0952023-09-14014 September 2023 Abilene Christian University - Update to Construction Permit Application Technical Review Schedule Project stage: Other ML23319A0942023-11-14014 November 2023, 30 November 2023 Abilene Christian University Construction Permit Application Preliminary Safety Analysis Report Revision 1 Project stage: Request ML23348A1962023-12-21021 December 2023 Abilene Christian University (Acu) - Transmittal of Requests for Additional Information Project stage: RAI ML24024A0092024-01-23023 January 2024 Abilene Christian University Construction Permit Application Partial Response to Audit Questions 3.5-4, 4.2-9, and 4.3-3 Project stage: Other ML24030A8702024-02-0606 February 2024 NRC Response to Request for Withholding Information from Public Disclosure for Abilene Christian University (Acu) Project stage: Withholding Request Acceptance ML24094A3322024-03-28028 March 2024 Abilene Christian University, Construction Permit Application - Response to Request for Additional Information 1 Project stage: Response to RAI ML24096B7832024-04-0505 April 2024 NRR E-mail Capture - Requests for Confirmation of Information Related to the Abilene Christian University (Acu) Molten Salt Research Reactor (Msrr) Construction Permit Application Project stage: Other ML24109A2032024-04-18018 April 2024 Next, Abilene Christian University Construction Permit Application Response to Request for Confirmatory Information Project stage: Request ML24121A2722024-04-30030 April 2024 Abilene Christian University Construction Permit Application Response to Request for Additional Information 2 Project stage: Response to RAI ML24164A2362024-06-12012 June 2024 Abilene Christian University Construction Permit Application Response to Request for Confirmatory Information Project stage: Request ML24162A0932024-06-12012 June 2024 Abilene Christian University - Molten Salt Research Reactor Construction Permit Application Revised Review Schedule Letter Project stage: Other ML24229A1952024-09-0303 September 2024 Notice of Significant Licensing Action - Abilene Christian University (Acu) Construction Permit Issuance Project stage: Other ML24243A0412024-09-16016 September 2024 Abilene Christian University, Transmittal Letter for Issuance of Construction Permit for the Molten Salt Research Reactor Project stage: Approval ML24243A0422024-09-16016 September 2024 Abilene Christian University, Safety Evaluation for Issuance of Construction Permit for the Molten Salt Research Reactor Project stage: Request ML24249A0302024-09-27027 September 2024 Abilene Christian University, Response to Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance 2023-09-14
[Table View] |
|
---|
Category:Letter
MONTHYEARML24305A2882024-10-31031 October 2024 Nuclear Energy Experimental Testing Lab. (Next) - Abilene Christian University - Molten Salt Research Reactor Regulatory Engagement Plan, Revision 2 ML24282A7322024-10-10010 October 2024 Transmittal Letter of NRC Feedback on MC&A White Paper ML24249A0302024-09-27027 September 2024 Abilene Christian University, Response to Request for Withholding Information from Public Disclosure ML24243A0412024-09-16016 September 2024 Abilene Christian University, Transmittal Letter for Issuance of Construction Permit for the Molten Salt Research Reactor ML24213A2862024-07-30030 July 2024 Submittal of Abilene Christian University Construction Permit Application Preliminary Safety Analysis Report Revision 2 ML24164A2362024-06-12012 June 2024 Abilene Christian University Construction Permit Application Response to Request for Confirmatory Information ML24162A0932024-06-12012 June 2024 Abilene Christian University - Molten Salt Research Reactor Construction Permit Application Revised Review Schedule Letter ML24121A2722024-04-30030 April 2024 Abilene Christian University Construction Permit Application Response to Request for Additional Information 2 ML24117A0712024-04-26026 April 2024 Submittal of Abilene Christian University Molten Salt Research Reactor White Paper on Material Control and Accounting ML24109A2032024-04-18018 April 2024 Next, Abilene Christian University Construction Permit Application Response to Request for Confirmatory Information ML24094A3322024-03-28028 March 2024 Abilene Christian University, Construction Permit Application - Response to Request for Additional Information 1 ML24030A8702024-02-0606 February 2024 NRC Response to Request for Withholding Information from Public Disclosure for Abilene Christian University (Acu) ML24030A0142024-01-29029 January 2024 Natura Resources, LLC, Plan for Regulatory Engagement ML24027A0022024-01-26026 January 2024 Next, Abilene Christian University Molten Salt Research Reactor Regulatory Engagement Plan, Revision 1 ML24024A0092024-01-23023 January 2024 Abilene Christian University Construction Permit Application Partial Response to Audit Questions 3.5-4, 4.2-9, and 4.3-3 ML23348A1962023-12-21021 December 2023 Abilene Christian University (Acu) - Transmittal of Requests for Additional Information ML23319A0952023-11-14014 November 2023 Abilene Christian University Construction Permit Application Preliminary Safety Analysis Report Revision 1 ML23249A0952023-09-14014 September 2023 Abilene Christian University - Update to Construction Permit Application Technical Review Schedule ML23230A3922023-08-17017 August 2023 Abilene Christian University Construction Permit Application Information Related to the Nuclear Waste Policy Act ML23157A0642023-06-22022 June 2023 Interim Report on Regulatory Audits of the Abilene Christian University Preliminary Safety Analysis Report ML23241A8492023-06-12012 June 2023 Achp Letter Response ML23013A2592023-05-0909 May 2023 Acu Draft Ea Fws Request to Initiate Sect 106 Consultation for Acu Non-Power Molten Salt Research Reactor Construction Permit Review in Abilene Tx ML23009B6142023-05-0808 May 2023 Acu Dea Achp Letter - Request to Initiate Section 106 Consultation for Abilene Christian University Non-Power Molten Salt Research Reactor Construction Permit Review in Abilene, Tx ML23009B6072023-05-0808 May 2023 Request to Initiate Section 106 Consultation for Abilene Christian University Molten Salt Research Reactor Construction Permit Application (Docket No. 05000610) ML23122A2832023-05-0505 May 2023 Ltr. to Debbie Dotson, President, Delaware Nation of Oklahoma, Re Acu Molten Salt Research Reactor Construction Permit Application ML23122A2892023-05-0505 May 2023 Ltr. to Terri Parton, President, Wichita and Affiliated Tribes of Oklahoma, Re Acu Molten Salt Research Reactor Construction Permit Application ML23122A2882023-05-0505 May 2023 Ltr. to Russell Martin, President, Tonkawa Tribe of Indians of Oklahoma, Re Acu Molten Salt Research Reactor Construction Permit Application ML23122A2872023-05-0505 May 2023 Ltr. to Reggie Wassana, Governor, Cheyenne and Arapaho Tribes of Oklahoma, Re Acu Molten Salt Research Reactor Construction Permit Application ML23122A2862023-05-0505 May 2023 Ltr. to Juan Garza, Chairman, Kickapoo Tribe of Texas, Re Acu Molten Salt Research Reactor Construction Permit Application ML23122A2852023-05-0505 May 2023 Ltr. to E. Michael Silvas, Governor, Ysleta Del Sur Pueblo, Re Acu Molten Salt Research Reactor Construction Permit Application ML23122A2842023-05-0505 May 2023 Ltr. to Durell Cooper, Chairman, Apache Tribe of Oklahoma, Re Acu Molten Salt Research Reactor Construction Permit Application ML23122A2822023-05-0505 May 2023 Ltr. to Brad Killscrow, Chief, Delaware Tribe of Indians, Re Acu Molten Salt Research Reactor Construction Permit Application ML23122A2812023-05-0505 May 2023 Ltr. to Bobby Gonzalez, Chairman, Caddo Nation of Oklahoma, Re Acu Molten Salt Research Reactor Construction Permit Application ML23009B6172023-05-0505 May 2023 Ltr. to Ricky Sylestine, Chairman, Alabama-Coushatta Tribe of Texas, Re Acu Molten Salt Research Reactor Construction Permit Application ML23012A0262023-02-0303 February 2023 Abilene Christian University, Review of Abilene Christian University Safeguards Information - Modified Handling Protection Plan ML22341A6152022-12-16016 December 2022 Abilene Christian University (Acu) Molten Salt Research Reactor (Msrr) Construction Permit Application Review Schedule Letter ML22313A0972022-11-18018 November 2022 Abilene Christian University (Acu) Molten Salt Research Reactor (Msrr) Construction Permit Application Acceptance Letter 2024-09-27
[Table view] |
Text
Dr. Rusty Towell Director of NEXT Lab Abilene Christian University ACU Box 27963 Abilene, TX 79699
SUBJECT:
ABILENE CHRISTIAN UNIVERSITY - ISSUANCE OF A CONSTRUCTION PERMIT FOR THE ABILENE CHRISTIAN UNIVERSITY MOLTEN SALT RESEARCH REACTOR (EPIDS: L-2022-NFW-0002 AND L-2022-NFW-0003)
Dear Dr. Towell:
The U.S. Nuclear Regulatory Commission (NRC) is issuing to Abilene Christian University (ACU) the enclosed Construction Permit (CP) No. CPRR-124 pursuant to Title 10 of the Code of Federal Regulations (10 CFR) section 50.35, Issuance of construction permits. The issuance of this CP is in response to ACUs application for a CP for its proposed Molten Salt Research Reactor (MSRR) dated August 12, 2022, as supplemented by letters dated October 14, 2022, August 17 and November 14, 2023, and January 23, March 28, April 18, April 30, June 12, and July 30, 2024. The CP, which is immediately effective, authorizes ACU to construct the MSRR in the Gayle and Max Dillard Science and Engineering Research Center on the ACU campus in Abilene, Texas, as described in the application, as supplemented.
The safety evaluation that documents the NRC staffs safety review for the CP application is also enclosed. A notice of issuance for CP No. CPRR-124 will be sent to the Office of the Federal Register for publication. The notice of issuance of the environmental assessment and finding of no significant impact for the CP application was published in the Federal Register on March 14, 2024 (89 FR 18678).September 16, 2024 If you have questions regarding this matter, please contact Richard Rivera at 301-415-7190 or via email at Richard.Rivera@nrc.gov.
Sincerely, Jeremy S. Bowen, Director Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation Docket No.: 50-610
Enclosures:
- 1. Construction Permit No. CPRR-124
- 2. Safety Evaluation cc:
Distribution via Gov Delivery Commissioner Bobby Janecka, Texas Commission on Environmental Quality Bobby.janecka@tceq.texas.gov Chief Nim Kidd, Texas Department of Public Safety, Emergency Management Division Nim.kidd@tdem.texas.gov Weldon Hurt, Mayor of Abilene Weldon.hurt@abilenetx.gov City Council Members of Abilene council@abilenetx.gov Robert Hanna, Abilene City Manager Robert.Hanna@abilenetx.gov Signed by Bowen, Jeremy on 09/16/24
Package: ML24243A039 Letter: ML24243A041 Construction Permit CPRR-124: ML24243A040 Safety Evaluation: ML24243A042 NRR-106 OFFICE NRR/DANU/UAL2:PM NRR/DANU/UAL2:LA OGC NAME RRivera CSmith JWachutka DATE 9/5/2024 9/4/2024 8/29/2024 OFFICE NRR/DANU/UTB1:BC NMSS/REFS/EPMB3:BC NRR/DANU/UAL2:BC NAME GOberson DBarnhurst SPhilpott DATE 9/5/2024 9/4/2024 9/5/2024 OFFICE NRR/DANU/D DNAME JBowen DATE 09/16/2024