Abilene Christian University, FRN for Issuance of Construction Permit for the Molten Salt Research Reactor
ML24243A043
Person / Time
Site: Abilene Christian University
Issue date: 09/16/2024
From: Jeremy Bowen
NRC/NRR/DANU
To:
Shared Package
ML24243A039 List:
References
NRC-2022-0167
Download: ML24243A043 (4)


Text

[7590-01-P]

NUCLEAR REGULATORY COMMISSION

[Docket No. 50-610; NRC-2022-0167]

Abilene Christian University;

Molten Salt Research Reactor;

Construction Permit

AGENCY: Nuclear Regulatory Commission.

ACTION: Notice; issuance.

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) is providing notice of the

issuance of Construction Permit No. CPRR-124 to Abilene Christian University (ACU).

DATES: Construction Permit No. CPRR-124 was issued on September 16, 2024.

ADDRESSES: Please refer to Docket ID NRC-2022-0167 when contacting the NRC

about the availability of information for th is action. You may obtain publicly available

information related to this action by any of the following methods:

for Docket ID NRC-2022-0167. Address questions about Docket IDs in Regulations.gov

to Stacy Schumann; telephone: 301-415-0624; email: Stacy.Schumann@nrc.gov. For

technical questions, contact the individual listed in the For Further Information Contact

section of this document.

  • NRCs Agencywide Documents Access and Management System

(ADAMS): You may obtain publicly available doc uments online in the ADAMS Public

Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the

search, select Begin Web-based ADAMS Search. For problems with ADAMS, please

contact the NRCs Public Document Room (P DR) reference staff at 1-800-397-4209, at

301-415-4737, or via email to PDR.Resource@nrc.gov. For the convenience of the reader, instructions about obtaining materials referenced in this document are provided

in the Availability of Documents section.

  • NRCs PDR: The PDR, where you may examine and order copies of publicly

available documents, is open by appointment. To make an appointment to visit the PDR,

please send an email to PDR.Resource@nrc.gov or call 1-800-397-4209 or

301-415-4737, between 8 a.m. and 4 p.m. eastern time (ET), Monday through Friday,

except Federal holidays.

FOR FURTHER INFORMATION CONTACT: Richard Rivera, Office of Nuclear Reactor

Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001;

telephone: 301-415-7190; email: Richard.Rivera@nrc.gov.

SUPPLEMENTARY INFORMATION:

I. Discussion

In accordance with section 2.106 of title 10 of the Code of Federal Regulations

(10 CFR), the NRC is providing notice of the issuance of Construction Permit No.

CPRR-124 to ACU. The construction permit, wh ich is immediately effective, authorizes

ACU to construct a research reactor in the Gayle and Max Dillard Science and

Engineering Research Center on the ACU campus in Abilene, Texas, as described in

ACUs construction permit application, as supplemented. With respect to the

construction permit application filed by ACU, the NRC staff performed an environmental

review and a safety review, and its evaluat ions and conclusions are documented in an

environmental assessment and a safety eval uation, respectively. Based, in part, on

these documents, the NRC found that the applicable standards and requirements of the

Atomic Energy Act of 1954, as amended (the Act), and the Commissions regulations

have been met. The NRC also found that any required notifications to other agencies or

bodies have been duly made and that, among other things, there is reasonable

2 assurance that the activities authorized by the construction permit will be conducted in

compliance with the rules and regulations of the Commission. On the basis of the

foregoing, the NRC found that there is reasonable assurance that taking into

consideration siting criteria, the proposed facility can be constructed and operated at the

proposed location without undue risk to the health and safety of the public, subject to the

conditions listed in the construction permit. Furthermore, the NRC found that ACU is

technically and financially qualified to engage in the activities authorized and that the

issuance of the construction permit will not be inimical to the common defense and

security or to the health and safety of the public. Finally, the NRC found that the

applicable requirements of subpart A of 10 CFR part 51 have been satisfied.

Accordingly, the immediately effective construction permit was issued on

September 16, 2024.

II. Availability of Documents

The documents identified in the following table are available to interested

persons through ADAMS.

Document Description ADAMS Accession No.

Construction Permit No. CPRR-124 ML24243A040

Safety Evaluation Related to the Abilene ML24243A042 Christian University Construction Permit Application for the Molten Salt Research Reactor Environmental Assessment for the ML23300A053 Construction Permit Application for the Abilene Christian University Molten Salt Research Reactor ACU Construction Permit Application, as ML22227A201 (Package) supplemented ML22293B816 (Package)

ML23230A392

3 Document Description ADAMS Accession No.

ML23319A094 (Package)

ML24024A009

ML24094A332

ML24109A203

ML24121A271 (Package)

ML24164A236

ML24219A258 (Package)

Dated: September 16, 2024.

For the Nuclear Regulatory Commission.

/RA/

Jeremy Bowen, Director, Division of Advanced Reactors and Non-Power Production and Utilization Facilities, Office of Nuclear Reactor Regulation.

4