MONTHYEARML22227A2022022-08-12012 August 2022 Abilene Christian University, Submittal of Construction Permit Application for the Molten Salt Research Reactor Project stage: Request ML22313A0972022-11-18018 November 2022 Abilene Christian University (Acu) Molten Salt Research Reactor (Msrr) Construction Permit Application Acceptance Letter Project stage: Acceptance Review PMNS20221202, Public Meeting with Abilene Christian University (Acu)2022-11-21021 November 2022 Public Meeting with Abilene Christian University (Acu) Project stage: Request ML22341A6152022-12-16016 December 2022 Abilene Christian University (Acu) Molten Salt Research Reactor (Msrr) Construction Permit Application Review Schedule Letter Project stage: Other ML23013A0892023-01-13013 January 2023 NRR E-mail Capture - Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Technical Topics Project stage: Other ML23065A0562023-03-0202 March 2023 NRR E-mail Capture - Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapters 9.2 and 13 Project stage: Other ML23065A0522023-03-0202 March 2023 NRR E-mail Capture - Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapters 1, 5, 8, 9 (Except 9.2 and 9.6), 10, 11, 12, 14-18, and General Topics Project stage: Other ML23065A0512023-03-0202 March 2023 NRR E-mail Capture - Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapter 7 Project stage: Other ML23065A0482023-03-0202 March 2023 NRR E-mail Capture - Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapters 2 & 3 Project stage: Other ML23065A0552023-03-0202 March 2023 NRR E-mail Capture - Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapters 4, 6, and 9.6 Project stage: Other ML23052A0872023-03-0909 March 2023 Abilene Christian University - Audit Plan for the Molten Salt Research Reactor Construction Permit Application Technical Topics Project stage: Other ML23061A1322023-03-0909 March 2023 Acu Lu, Vr, WR, Rh, Wm, TR, AC, Fc Info Needs Items Q2FY2023 Project stage: Other ML23065A3342023-05-0101 May 2023 Abilene Christian University - December 9, 2022, Public Meeting Summary Regarding Discussion on Technical Focus Areas Project stage: Meeting ML23249A0952023-09-14014 September 2023 Abilene Christian University - Update to Construction Permit Application Technical Review Schedule Project stage: Other ML23319A0942023-11-14014 November 2023, 30 November 2023 Abilene Christian University Construction Permit Application Preliminary Safety Analysis Report Revision 1 Project stage: Request ML23348A1962023-12-21021 December 2023 Abilene Christian University (Acu) - Transmittal of Requests for Additional Information Project stage: RAI ML24024A0092024-01-23023 January 2024 Abilene Christian University Construction Permit Application Partial Response to Audit Questions 3.5-4, 4.2-9, and 4.3-3 Project stage: Other ML24030A8702024-02-0606 February 2024 NRC Response to Request for Withholding Information from Public Disclosure for Abilene Christian University (Acu) Project stage: Withholding Request Acceptance ML24094A3322024-03-28028 March 2024 Abilene Christian University, Construction Permit Application - Response to Request for Additional Information 1 Project stage: Response to RAI ML24096B7832024-04-0505 April 2024 NRR E-mail Capture - Requests for Confirmation of Information Related to the Abilene Christian University (Acu) Molten Salt Research Reactor (Msrr) Construction Permit Application Project stage: Other ML24109A2032024-04-18018 April 2024 Next, Abilene Christian University Construction Permit Application Response to Request for Confirmatory Information Project stage: Request ML24121A2722024-04-30030 April 2024 Abilene Christian University Construction Permit Application Response to Request for Additional Information 2 Project stage: Response to RAI ML24162A0932024-06-12012 June 2024 Abilene Christian University - Molten Salt Research Reactor Construction Permit Application Revised Review Schedule Letter Project stage: Other ML24164A2362024-06-12012 June 2024 Abilene Christian University Construction Permit Application Response to Request for Confirmatory Information Project stage: Request ML24213A2862024-07-30030 July 2024 Submittal of Abilene Christian University Construction Permit Application Preliminary Safety Analysis Report Revision 2 Project stage: Other ML24219A2592024-07-30030 July 2024 Enclosure 2, Mssr Codes and Service Conditions Redacted Project stage: Request ML24219A2622024-07-30030 July 2024 Enclosure 3, Safety Related Valve Requirements Redacted Project stage: Request ML24229A1952024-09-0303 September 2024 Notice of Significant Licensing Action - Abilene Christian University (Acu) Construction Permit Issuance Project stage: Other ML24243A0422024-09-16016 September 2024 Abilene Christian University, Safety Evaluation for Issuance of Construction Permit for the Molten Salt Research Reactor Project stage: Request ML24243A0412024-09-16016 September 2024 Abilene Christian University, Transmittal Letter for Issuance of Construction Permit for the Molten Salt Research Reactor Project stage: Approval ML24249A0302024-09-27027 September 2024 Abilene Christian University, Response to Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML24341A1332024-12-0505 December 2024 Abilene Christian University, Nuclear Energy Experimental Testing Lab., Msrr Degradation Management Program Project stage: Request ML25129A1262025-05-13013 May 2025 Request for Withholding Information from Public Disclosure for Abilene Christian University (Acu) Project stage: Withholding Request Acceptance 2024-01-23
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Dr. Rusty Towell Director of NEXT Lab Abilene Christian University ACU Box 27963 Abilene, TX 79699
SUBJECT:
ABILENE CHRISTIAN UNIVERSITY - MOLTEN SALT RESEARCH REACTOR CONSTRUCTION PERMIT APPLICATION REVISED REVIEW SCHEDULE (EPID: L-2022-NFW-0002)
Dear Dr. Towell:
The purpose of this letter is to inform Abilene Christian University (ACU) of the U.S. Nuclear Regulatory Commission (NRC) staffs revised schedule for the review of the construction permit application for ACUs proposed Molten Salt Research Reactor (MSRR) (Agencywide Documents Access and Management System (ADAMS) Accession No. ML22227A201), as supplemented. By letter dated December 16, 2022 (ML22341A615), the NRC staff previously communicated that it planned to complete its review of the construction permit application by May 2024. During regulatory audit meetings with ACU, it was identified that ACU needed additional time to further consider and refine certain design aspects of its MSRR. Therefore, the NRC staff determined that additional information was needed for the NRC staff to complete its review of the ACU application, and on December 21, 2023 (ML23348A196), the NRC staff issued a letter containing requests for additional information (RAIs). In that letter, the NRC staff also notified ACU that it would issue a revised schedule once ACU responded to the RAIs transmitted in that letter. ACU responded by letters dated March 28, 2024, (ML24094A332) and April 30, 2024 (ML24121A272).
Based on the status of the review and ACUs plan to provide the remaining information identified during the technical audits, the NRC staffs revised estimate for completing its review of the construction permit application is provided in the table below:
Milestone Group - Safety Review Estimated Completion Draft Safety Evaluation 06/28/2024 Advanced Safety Evaluation 08/16/2024 Final Safety Evaluation and Construction Permit Issuance 09/30/2024 The revised schedule is based on historical review timelines, and the NRC staffs judgement regarding the estimated level of effort necessary to complete the technical review and develop the safety evaluation. Additionally, the revised schedule accounts for the work that was done by June 12, 2024
R. Towell both the NRC staff and ACU to resolve additional technical issues in other areas while working in parallel to respond to the RAIs. The revised schedule could change due to several factors, including the timeframe for the resolution of the remaining technical issues, unanticipated changes to the scope of the review, unsolicited supplements to the application, design changes, and other factors. Finally, based on its assessment of the remaining scope of work, the NRC staff believes that the original estimate of 15,000 NRC staff hours to complete the review of the construction permit application remains valid.
If you have any questions, please contact Richard Rivera at (301) 415-7190 or via email at Richard.Rivera@nrc.gov or Edward Helvenston at (301) 415-4067 or via email at Edward.Helvenston@nrc.gov.
Sincerely, Richard Rivera, Project Manager Advanced Reactor Licensing Branch 2 Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation Docket No. 50-610 cc: Abilene Christian University MSRR via GovDelivery Subscribers Signed by Rivera, Richard on 06/12/24
ML24162A093 NRR-106 OFFICE NRR/DANU/UAL2:PM NRR/DANU/UAL2:LA NRR/DANU/UTB1:BC NAME RRivera CSmith GOberson DATE 06/10/2024 06/10/2024 06/11/2024 OFFICE NRR/DANU/UAL2:(A)BC NRR/DANU/UAL2:PM NAME SPhilpott RRivera DATE 06/12/2024 06/12/2024