MONTHYEARML24260A1222024-09-14014 September 2024 14 Sept 2024 Ltr - California Coastal Commission to Pg&E, Incomplete Consistency Certification for Requested Nuclear Regulatory Commission License Renewal for Diablo Canyon Power Plant DCL-24-087, License Renewal - Historic and Cultural Resources Reference Documents (Redacted)2024-09-12012 September 2024 License Renewal - Historic and Cultural Resources Reference Documents (Redacted) ML24262A2462024-09-11011 September 2024 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Petitioner Response to Acknowledgement Letter - DCL-24-083, CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated2024-09-0909 September 2024 CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated DCL-24-078, Pre-Notice of Disbursement from Decommissioning Trust2024-09-0303 September 2024 Pre-Notice of Disbursement from Decommissioning Trust DCL-24-082, Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment2024-08-28028 August 2024 Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment ML24205A0662024-08-27027 August 2024 OEDO-24-00083 - 10 CFR 2.206 - Ack Letter - Diablo Canyon Units 1 and 2 Seismic Core Damage Frequency - IR 05000275/20243012024-08-26026 August 2024 NRC Examination Report 05000275/2024301; 05000323/2024301 IR 05000275/20240052024-08-22022 August 2024 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2024005 and 05000323/2024005) DCL-24-077, Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident2024-08-15015 August 2024 Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident DCL-24-075, Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React2024-08-0808 August 2024 Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React IR 05000275/20240022024-08-0606 August 2024 Integrated Inspection Report 05000275/2024002 and 05000323/2024002 DCL-24-070, License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2024-07-31031 July 2024 License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies DCL-24-071, Core Operating Limits Report for Unit 2 Cycle 252024-07-22022 July 2024 Core Operating Limits Report for Unit 2 Cycle 25 DCL-2024-523, Submittal of Report on Discharge Self-Monitoring2024-07-18018 July 2024 Submittal of Report on Discharge Self-Monitoring ML24187A1352024-07-16016 July 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of June 2024 Audit Related to the License Renewal Application Severe Accident Mitigation Alternatives Review IR 05000275/20240142024-07-11011 July 2024 Age-Related Degradation Inspection Report 05000275/2024014 and 05000323/2024014 IR 05000275/20244012024-07-0808 July 2024 Security Baseline Inspection Report 05000275/2024401 and 05000323/2024401 (Full Report) IR 05000323/20240112024-07-0303 July 2024 License Renewal Phase Report 05000323/2024011 DCL-2024-527, Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant2024-07-0101 July 2024 Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant DCL-24-066, Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL2024-06-27027 June 2024 Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL ML24155A2182024-06-18018 June 2024 OEDO-23-00350-NRR - (LTR-23-0228-1) - Closure Letter - 10 CFR 2.206 Petition from Mothers for Peace and Friends of the Earth Regarding Diablo Canyon ML24129A1762024-06-14014 June 2024 National Historic Preservation Act Section 106 Consultation – Results of Identification and Evaluation (Docket Number: 72-026) ML24200A2052024-06-0707 June 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project for Diablo Canyon License Renewal ML24099A2192024-05-29029 May 2024 Issuance of Amendment Nos. 245 and 247 Revision to TSs to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24117A0132024-05-20020 May 2024 Letter to Paula Gerfen-Diablo Canyon Units 1 and 2-Regulatory Audit Regarding Severe Accident Mitigation Alternatives for the License Renewal Application DCL-24-054, LCO 3.0.3 Completion Time Limits2024-05-17017 May 2024 LCO 3.0.3 Completion Time Limits DCL-24-052, Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report2024-05-16016 May 2024 Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report DCL-24-051, One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage2024-05-0808 May 2024 One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage ML24127A2042024-05-0202 May 2024 02May2024 Ltr - California Coastal Commission to Pg&E, Coastal Development Permit Needed for Pg&E’S Proposed Relicensing of Diablo Canyon Nuclear Power Plant DCL-24-047, 2023 Annual Non-radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Non-radiological Environmental Operating Report DCL-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Radiological Environmental Operating Report L-24-004, Independent Spent Fuel Storage Installation - Responses to NRC Requests for Additional Information on the Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Application (Cac/Epid 001028/L-2022-RNW-0007)2024-04-30030 April 2024 Independent Spent Fuel Storage Installation - Responses to NRC Requests for Additional Information on the Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Application (Cac/Epid 001028/L-2022-RNW-0007) DCL-24-048, O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 20232024-04-30030 April 2024 O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 2023 DCL-24-027, 2023 Annual Radioactive Effluent Release Report2024-04-28028 April 2024 2023 Annual Radioactive Effluent Release Report DCL-24-045, Annual Report of Occupational Radiation Exposure for 20232024-04-24024 April 2024 Annual Report of Occupational Radiation Exposure for 2023 IR 05000275/20240012024-04-23023 April 2024 Integrated Inspection Report 05000275/2024001 and 05000323/2024001 ML24114A2032024-04-22022 April 2024 Request for Information for EP Program and Performance Indicator Verification Inspection (Wolf Creek Nuclear Generating Station) Inspection Report 05000482/2024003 ML24106A2882024-04-18018 April 2024 License Renewal Application Environmental Review RCIs and RAIs ML24106A2892024-04-18018 April 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of March 2024 Audit Regarding the Environmental Review of the License Renewal Application DCL-24-042, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-04-17017 April 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24108A1122024-04-15015 April 2024 License Amendment Request 24-02 Request for Approval of DCPP Early Warning System to Meet 10 CFR 73.55(i)(2) and 10 CFR 73.55(e)(9)(vi)(A) DCL-24-022, Notification of Changes to Decommissioning Schedule2024-04-0202 April 2024 Notification of Changes to Decommissioning Schedule DCL-24-023, Revised Certification of Permanent Cessation of Power Operations2024-04-0202 April 2024 Revised Certification of Permanent Cessation of Power Operations DCL-24-031, Decommissioning Funding Report2024-03-27027 March 2024 Decommissioning Funding Report DCL-24-032, 2024 Annual Statement of Insurance for Pacific Gas and Electric Company’S Diablo Canyon Power Plant2024-03-27027 March 2024 2024 Annual Statement of Insurance for Pacific Gas and Electric Company’S Diablo Canyon Power Plant ML24082A2592024-03-25025 March 2024 Notice of Enforcement Discretion for Diablo Canyon Power Plant, Unit 2 (EPID L-2024-LLD-0002) - March 25, 2024 ML24081A0462024-03-22022 March 2024 Audit Summary in Support of the License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b DCL-24-028, Request for Enforcement Discretion Regarding Compliance with Technical Specification 3.0.3, Limiting Condition for Operation Applicability2024-03-21021 March 2024 Request for Enforcement Discretion Regarding Compliance with Technical Specification 3.0.3, Limiting Condition for Operation Applicability ML24081A4052024-03-21021 March 2024 Request for Enforcement Discretion Regarding Compliance with Technical Specification 3.0.3, Limiting Condition for Operation Applicability 2024-09-09
[Table view] Category:License-Operator Examination Report
MONTHYEARIR 05000275/20243012024-08-26026 August 2024 NRC Examination Report 05000275/2024301; 05000323/2024301 IR 05000275/20233012023-07-25025 July 2023 NRC Initial Operator Licensing Examination Approval 05000275/2023301, 05000323/2023301 IR 05000275/20163012016-06-0707 June 2016 NRC Examination Report 05000275/2016301; 05000323/2016301 ML15265A0802015-09-21021 September 2015 Notification of NRC Initial Operator Licensing Examination 05000275/2016301; 05000323/2016301 IR 05000275/20143012014-09-25025 September 2014 Er 050002752014301; 050003232014301; on August 8 - August 27, 2014; Diablo Canyon Power Plant, Units 1 and 2; Initial Operator Licensing Examination Report IR 05000275/20123022013-01-0303 January 2013 IR 05000275-12-302; Pacific Gas & Electric Company; 05000323-12-302;11/21- 12/3/ 2012; Diablo Canyon Power Plant, Units 1 and 2; Initial Operator Licensing Examination Report IR 05000275/20123012012-04-0303 April 2012 Er 05000275-12-301, 05000323-12-301, March 9, 2012 to March 27, 2012, Diablo Canyon Power Plant, Units 1 and 2, Initial Operator Licensing Retake Written Examination Report IR 05000275/20113022012-01-18018 January 2012 Er 05000275-11-302; 05000323-11-302; November 15 - 21, 2011; Diablo Canyon Power Plant, Units 1 and 2; Initial Operator Licensing Examination Report IR 05000275/20113012011-09-20020 September 2011 Er 05000275-11-301; 05000323-11-301; July 8 - August 22, 2011; Diablo Canyon Power Plant, Units 1 and 2; Initial Operator Licensing Examination Report DCL-11-074, Response to NRC Regulatory Issue Summary 2011-04, Preparation and Scheduling of Operator Licensing Examinations2011-07-0101 July 2011 Response to NRC Regulatory Issue Summary 2011-04, Preparation and Scheduling of Operator Licensing Examinations IR 05000275/20103012010-02-24024 February 2010 Er 05000275-10-301, 05000323-10-301; on January 8 - 28, 2010; Diablo Canyon Power Plant, Units 1 & 2; Initial Operator Licensing Examination Report IR 05000275/20093012009-03-31031 March 2009 IR 05000275-09-301, 05000323-09-301 on 02/06/09 - 02/20/09 for Diablo Canyon, Units 1 and 2, Initial Operator Licensing Examination Report IR 05000275/20083012008-07-22022 July 2008 Er 05000275-08-301, 05000323-08-301, on June 13 - 23, 2008, Diablo Canyon Power Plant, Units 1 and 2; Initial Operator Licensing Examination Report ML0901405642008-06-27027 June 2008 DC - 2008 -06 - Post Examination Comments DCL-05-107, Response to NRC Regulatory Issue Summary 2005-19; Preparation and Scheduling of Operator Licensing Examinations2005-09-16016 September 2005 Response to NRC Regulatory Issue Summary 2005-19; Preparation and Scheduling of Operator Licensing Examinations IR 05000275/20053012005-03-31031 March 2005 Er 05000275-05-301 and 05000323-05-301, on 2/8-16/2005, Diablo Canyon Generating Station, Operator Licensing Examinations ML0409200332004-03-30030 March 2004 Generic Fundamentals Section of the Written Operator Licensing Examination DCL-02-078, Response to NRC Regulatory Issue Summary 2002-09; Preparation and Scheduling of Operator Licensing Examinations2002-07-12012 July 2002 Response to NRC Regulatory Issue Summary 2002-09; Preparation and Scheduling of Operator Licensing Examinations 2024-08-26
[Table view] |
Text
August 26, 2024
SUBJECT:
DIABLO CANYON POWER PLANT, UNITS 1 AND 2 - NRC EXAMINATION REPORT 05000275/2024301 AND 05000323/2024301
Dear Mr. Peck:
On August 13, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an initial operator license examination at Diablo Canyon Nuclear Power Plant, Units 1 and 2. The enclosed report documents the examination results and licensing decisions. The preliminary examination results were discussed on July 18, 2024, with Mr. A. Wilson, Senior Director of Engineering, and other members of your staff. An exit meeting was conducted on August 13, 2024, with Mr. A. Kadir, Operations Training Manager, who was provided the NRC licensing decisions.
The examination included the evaluation of six applicants for reactor operator licenses, nine applicants for instant senior reactor operator licenses, and one applicant for an upgrade senior reactor operator license. The license examiners determined that all applicants satisfied the requirements of 10 CFR Part 55, and the appropriate licenses have been issued. There were no post-examination comments submitted by your staff. The enclosure contains details of this report.
There were no findings identified for this examination. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Heather J. Gepford, Ph.D., Chief Operations Branch Division of Operating Reactor Safety Docket Nos. 05000275, 05000323 License Nos. DPR-80, DPR-82 Enclosure:
Examination Report 05000275/2024301, and 05000323/2024301 Electronic distribution via LISTSERV Signed by Gepford, Heather J.
on 08/26/24
ML24234A097 SUNSI Review: ADAMS: Non-Publicly Available Non-Sensitive Keyword:
By: KDC1 Yes No Publicly Available Sensitive NRR-079 OFFICE SOE:DORS/OB SOE:DORS/OB NSE:DRSS/RCB SOE:DORS/OB OE:DORS/OB OE:DORS/OB NAME KClayton TFarina MBloodgood NHernandez RWilliams DYou SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA/ /RA/
DATE 08/23/24 08/21/24 08/21/24 08/21/24 08/23/24 08/21/24 OFFICE BC:DORS/OB NAME HGepford SIGNATURE /RA/
DATE 08/26/24
U.S. NUCLEAR REGULATORY COMMISSION Examination Report
Docket Numbers: 05000275, 05000323
License Numbers: DPR-80, DPR-82
Report Numbers: 05000275/2024301, 05000323/2024301
Enterprise Identifier: L-2024-OLL-0030
Licensee: Pacific Gas and Electric Company
Facility: Diablo Canyon Power Plant, Units 1 and 2
Location: Avila Beach, California
Inspection Dates: June 3, 2024, to August 13, 2024
Inspectors: K. Clayton, Senior Operations Engineer, Chief Examiner N. Hernandez, Senior Operations Engineer T. Farina, Senior Operations Engineer M. Bloodgood, Nuclear Systems Engineer D. You, Operations Engineer R. Williams, Operations Engineer
Approved By: Heather J. Gepford, Ph.D., Chief Operations Branch Division of Operating Reactor Safety
Enclosure SUMMARY
Examination Report 05000275/2024301 and 05000323/2024301; June 3, 2024 - August 13, 2024; Diablo Canyon Power Plant, Units 1 and 2; Initial Operator Licensing Examination Report
The NRC examiners evaluated the competency of six applicants for reactor operator licenses, nine applicants for instant senior reactor operator licenses, and one applicant for an upgrade senior reactor operator license at Diablo Canyon Power Plant, Units 1 and 2.
The licensee developed the examinations using NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," Revision 12. The written examination was administered by the licensee on August 2, 2024. The NRC examiners administered the operating tests on July 15 - July 22, 2024.
The NRC examiners determined that all applicants satisfied the requirements of 10 CFR Part 55, and the appropriate licenses have been issued.
A. NRC-Identified and Self-Revealing Findings
None.
B. Licensee-Identified Violations
None.
REPORT DETAILS
OTHER ACTIVITIES - INITIAL LICENSE EXAMINATION
.1 License Applications
a. Scope
The NRC examiners reviewed all license applications submitted to ensure each applicant satisfied relevant license eligibility requirements. The NRC examiners also audited four of the license applications in detail to confirm that they accurately reflected the subject applicants qualifications. This audit focused on the applicants experience and on-the-job training, including control manipulations that provided significant reactivity changes.
b. Findings
No findings were identified.
.2 Examination Development
a. Scope
The NRC examiners reviewed integrated examination outlines and draft examinations submitted by the licensee against the requirements of NUREG-1021. The NRC examiners conducted an onsite validation of the operating tests.
b. Findings
The NRC examiners provided outline, draft examination and post-validation comments to the licensee. The licensee satisfactorily completed comment resolution prior to examination administration.
The NRC examiners determined the written examinations and operating tests initially submitted by the licensee were within the range of acceptability expected for a proposed examination.
.3 Operator Knowledge and Performance
a. Scope
On August 2, 2024, the licensee proctored the administration of the written examinations to all sixteen applicants. The licensee staff graded the written examinations, analyzed the results, and presented their analysis to the NRC on August 5, 2024.
The NRC examination team administered the various portions of the operating tests to all applicants on July 15 - July 22, 2024.
b. Findings
No findings were identified.
All applicants passed the written examination and all parts of the operating tests. The final written examinations and post-examination analysis may be accessed in the ADAMS system under the accession numbers noted in the attachment. There were no post-examination comments as indicated in the licensee submittal.
The examination team noted no generic weaknesses associated with applicant performance on the operating tests. Post-examination analysis revealed five generic weaknesses associated with applicant performance on the written examination.
Questions 33, 53, 84, 89, and 100 demonstrated knowledge weaknesses. These weaknesses were tracked under Notification 51178743, task 15. Copies of all individual examination reports were sent to the facility training manager for evaluation and determination of appropriate remedial training.
.4 Simulation Facility Performance
a. Scope
The NRC examiners observed simulator performance regarding plant fidelity during examination validation and administration.
b. Findings
No findings were identified.
.5 Examination Security
a. Scope
The NRC examiners reviewed examination security for examination development during both the onsite preparation week and examination administration week for compliance with 10 CFR 55.49 and NUREG-1021. Plans for examination security and applicant control were reviewed and discussed with licensee personnel.
b. Findings
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
Exit Meeting Summary
The chief examiner presented the preliminary examination results to Mr. A. Wilson, Senior Director of Engineering, and other members of the staff on July 18, 2024. An exit meeting was conducted on August 13, 2024, between Mr. K. Clayton, chief examiner, and Mr. A. Kadir, Operations Training Manager. The licensee did not identify any information or materials used during the examination as proprietary.
ADAMS DOCUMENTS REFERENCED
Accession No. ML24234A065 - FINAL WRITTEN EXAMS Accession No. ML24234A066 - FINAL OPERATING TEST Accession No. ML24234A062 - POST-EXAMINATION ANALYSIS
5