MONTHYEARML24031A0502024-01-31031 January 2024 COL Docs - FW Erroneous Description of Tier 2 Change Process in Construction Lessons-Learned Report ML24017A1122024-01-17017 January 2024 NRR E-mail Capture - Request for Access to Cyber Security Data - Vogtle, Units 3 and 4 ML24009A1112024-01-0909 January 2024 NRR E-mail Capture - Acceptance Review - Hatch 1&2 LAR - Revise TS 3.7.1 & 3.7.2 to Adopt Risk-Informed Completion Times for RHRSW and Psw Systems (L-2023-LLA-0169) ML23360A0042023-12-23023 December 2023 NRR E-mail Capture - Fyi - Office of Nuclear Regulatory Research (RES) Requests for Vogtle 3 & 4 ML23354A2032023-12-18018 December 2023 Document Request for Hatch Nuclear Plant - Radiation Protection Inspection - Inspection Report 2024-01 ML23348A0782023-12-13013 December 2023 NRR E-mail Capture - Voluntary Request for Closed Meeting Regarding Cyber Security Assessments at Vogtle, Units 3 and 4 ML23342A0802023-12-0808 December 2023 NRR E-mail Capture - Request for Additional Information (RAI) - Vogtle, Unit 1 - Review of SG Tube Inspection Report for Refueling Outage 24 (L-2023-LRO-0067) ML23335A0122023-12-0101 December 2023 FNP - IP95001 Inspection Notification and Request for Information (Email to Farley) ML23331A9992023-11-27027 November 2023 COL Docs - Re Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23331A9492023-11-26026 November 2023 Email Dated November 26, 2023, from Bo Pham to SNC and NRC - Vogtle Seismic Hazard Report ML23331A9622023-11-22022 November 2023 Email Dated November 22, 2023, from SNC to NRC - Vogtle Seismic Hazard Report ML23326A2802023-11-22022 November 2023 COL Docs - Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23320A0342023-11-16016 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23320A2372023-11-0808 November 2023 NRR E-mail Capture - (External_Sender) Proposed LAR Regarding the Ultimate Heat Sink at Vogtle, Units 1 and 2 ML23312A2632023-11-0808 November 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Monday, November 13, 2023 - Vogtle Units 3&4, LAR-22-002, TS 3.8.3, Inverters - Operating Completion Time Extension ML23311A1512023-11-0707 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23304A2272023-10-31031 October 2023 NRR E-mail Capture - Request for State of Georgia Comment by 5pm Monday, Nov. 6, 2023 - License Amendment Request for Vogtle Unit 4 - to Remove Combined License Appendix C ML23289A1362023-10-16016 October 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Friday, October 20, 2023 - Vogtle Units 3&4, LAR-23-006, Rev.1, More Restrictive Action for Tech. Spec. 3.1.9 ML23283A0332023-10-10010 October 2023 COL Docs - FW Vogtle Units 3 and 4 (LAR 23-009) ML23283A0452023-10-0808 October 2023 E-Mail Re Plant Vogtle - Neop Letter Dated October 8, 2023 - Vogtle 3 & 4 - TS 3.7.6 License Amendment Request ML23279A2082023-10-0505 October 2023 Issuance of Formal RAIs - Vogtle, Units 1 and 2 - Proposed LAR and Proposed Alternative Request to Revise TS 3.4.14.1 and IST ALT-VR-02 (EPIDs L-2023-LLA-0061 and L-2023-LLR-0023) ML23275A1002023-10-0202 October 2023 COL Docs - Re Action Summary of 9.27.23 Clarification Call with Southern Nuclear Company on LAR-22-0002, TS 3.8.3 Inverters - Operating Completion Time ML23270B1912023-09-27027 September 2023 COL Docs - Update Vogtle Units 3&4 Acceptance Letter for LAR-22-002 Technical Specification 3.8.3, Inverters Operating ML23263A1042023-09-20020 September 2023 COL Docs - FW Fyi for Tomorrow'S Psm Meeting ML23264A0142023-09-14014 September 2023 NRR E-mail Capture - (External_Sender) Draft Round-2 RAI - Hatch, Units 1 and 2, Revise TS 1.1-1 Modes LAR ML23257A2092023-09-14014 September 2023 NRR E-mail Capture - Formal Issuance of 2nd Round RAIs for Surry Units 1&2 and North Anna Units 1&2 Emergency Plans LAR ML23257A0632023-09-13013 September 2023 NRR E-mail Capture - Acceptance Review of Southern Nuclear Operating Company'S License Amendment Request to Remove Combined License Appendix C ML23256A2682023-09-13013 September 2023 COL Docs - Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23249A2082023-09-0606 September 2023 NRR E-mail Capture - Change in Estimated Review Schedule and Level of Effort for Hatch 'Revise TS Table 1.1-1 (Modes)' LAR (L-2022-LLA-0120) ML23248A3482023-09-0505 September 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) 6 - Vogtle - TSTF-339 LAR (L-2023-LLA-0053) ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23243A9172023-08-31031 August 2023 NRR E-mail Capture - (External_Sender) Re Question - Legal Contact(S) for Vogtle Electric Generating Plant, Units 3 & 4 ML23243A9952023-08-31031 August 2023 Request for Baseline RP Inspection ML23241A0452023-08-29029 August 2023 COL Docs - FW Draft LAR and Exemption Request Regarding Tier 1 and Tier 2 Requirements ML23236A0022023-08-22022 August 2023 NRR E-mail Capture - Request for Additional Information - Farley, Units 1&2, Emergency TS 3.6.5 LAR ML23229A2322023-08-17017 August 2023 COL Docs - FW Re LAR 22-002 Second Round RAI Approved ML23188A151 for Vogtle Units 3 & 4 ML23223A0142023-08-10010 August 2023 NRR E-mail Capture - Acceptance Review - SNC Fleet Exemption to 10 CFR 73.2, Physical Barriers ML23221A3982023-08-0909 August 2023 COL Docs - LAR 22-002 Second Round RAI Approved ML23188A151 2024-01-09
[Table view] |
Text
From: John Lamb Sent: Monday, March 13, 2023 6:08 PM To: Sparkman, Wesley A.; Quarles, Adam Graham; Pournaras, DeLisa S.; Lowery, Ken G.
Cc: Joyce, Ryan M.; Chamberlain, Amy Christine; Michael Markley; Victor Hall (He/Him); Billy Gleaves; Cayetano Santos; michael norris; Dawnmathews Kalathiveettil
Subject:
FYI - Closeout the Evacuation Time Estimate (ETE) Reviews for SNC Fleet Importance: High
Dear Wes,
Adam, DeLisa, and Ken:
The U.S. Nuclear Regulatory (NRC) staff has reviewed the updated evacuation time estimate (ETE) analyses submitted by letter dated September 15, 2022 (Agencywide Documents Access and Management System (ADAMS) ML22262A071), in accordance with section IV.4 of Appendix E to Title 10, Part 50 of the Code of Federal Regulations (10 CFR Part 50). The NRCs staff review is intended to verify consistent application of the updated guidance contained in NUREG/CR-7002, Criteria for Development of Evacuation Time Estimate Studies, Revision 1, and does not constitute formal NRC approval of the updated ETE analyses.
As stated in the NRC letter to the Federal Emergency Management Agency (FEMA) dated March 13, 2023 (ADAMS Accession No. ML23054A253), Joseph M. Farley Nuclear Plant, Units 1 and 2; Edwin I. Hatch Nuclear Power Plant, Units 1 and 2; and Vogtle Electric Generating Plant, Units 1, 2, 3, and 4, updated ETE analyses has been reviewed and found to be generally consistent with the guidance in NUREG/CR-7002 and, as such, was found to be complete. This NRC letter to FEMA will be made available on March 21, 2023.
John G. Lamb, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Hearing Identifier: NRR_DRMA Email Number: 1992 Mail Envelope Properties (MN2PR09MB5084508ACF89DF275DD53D0DFAB99)
Subject:
FYI - Closeout the Evacuation Time Estimate (ETE) Reviews for SNC Fleet Sent Date: 3/13/2023 6:07:41 PM Received Date: 3/13/2023 6:07:00 PM From: John Lamb Created By: John.Lamb@nrc.gov Recipients:
"Joyce, Ryan M." <RMJOYCE@southernco.com>
Tracking Status: None "Chamberlain, Amy Christine" <ACCHAMBE@southernco.com>
Tracking Status: None "Michael Markley" <Michael.Markley@nrc.gov>
Tracking Status: None "Victor Hall (He/Him)" <Victor.Hall@nrc.gov>
Tracking Status: None "Billy Gleaves" <Bill.Gleaves@nrc.gov>
Tracking Status: None "Cayetano Santos" <Cayetano.Santos@nrc.gov>
Tracking Status: None "michael norris" <Michael.Norris@nrc.gov>
Tracking Status: None "Dawnmathews Kalathiveettil" <Dawnmathews.Kalathiveettil@nrc.gov>
Tracking Status: None "Sparkman, Wesley A." <WASPARKM@southernco.com>
Tracking Status: None "Quarles, Adam Graham" <AGQUARLE@southernco.com>
Tracking Status: None "Pournaras, DeLisa S." <DSPOURNA@SOUTHERNCO.COM>
Tracking Status: None "Lowery, Ken G." <KGLOWERY@southernco.com>
Tracking Status: None Post Office: MN2PR09MB5084.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 1318 3/13/2023 6:07:00 PM Options Priority: High Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: