MONTHYEARIR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) ML23311A3482023-10-20020 October 2023 DTE Electric Company (DTE) - Submittal of the Renewed Fermi 3 Michigan Department of Environmental, Great Lakes, and Energy (EGLE) National Pollutant Discharge Elimination System (NPDES) Permit No. MI0058892 ML23272A1552023-10-10010 October 2023 Letter to Licensee and Federal Register Notification of Amendment to Renewed Facility Operating License and Proposed No Significant Hazards Consideration Determination (Exigent Circumstances) (EPID L-2023-LLA-0134) (Letter) ML23283A0222023-10-0909 October 2023 Follow Up to Fermi Unit 2 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval ML23276B4542023-10-0505 October 2023 Cyber Security Inspection Report 05000341/2023402 ML23243A8852023-09-18018 September 2023 Issuance of Amendment No. 225 Regarding Revision of Technical Specifications 3.7.2, Emergency Equipment Cooling Water, Emergency Equipment Service Water and System and Ultimate Heat Sink (Exigent Circumstances) ML23248A2242023-09-0707 September 2023 Regulatory Audit in Support of Review of License Amendment Request for a Risk-Informed Approach for Addressing the Effects of Debris on ECCS Strainer Performance ML23223A2242023-08-29029 August 2023 Individual Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for Hearing (Exigent Circumstances) ML23237B4332023-08-25025 August 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI IR 05000341/20230052023-08-24024 August 2023 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2023005) ML23229A0122023-08-17017 August 2023 Issuance of Amendment No. 224 to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 (Emergency Circumstances) IR 05000341/20233012023-08-16016 August 2023 NRC Initial License Examination Report 05000341/2023301 ML23227A2212023-08-15015 August 2023 Emergency Application to Revise Technical Specifications to Adopt TSTF 568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 ML23219A1792023-08-0707 August 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Fermi Power Plant, Unit 2 IR 05000341/20230022023-08-0404 August 2023 Integrated Inspection Report 05000341/2023002 ML23216A1872023-08-0404 August 2023 Submittal of Relief Request RR-A25 for Extended License Period ML23206A1272023-07-26026 July 2023 NOED for Fermi Power Plant, Unit Two Technical Specification 3.7.2, Emergency Equipment Cooling Water Emergency Equipment Service Water System and Ultimate Heat Sink ML23200A2552023-06-28028 June 2023 Post-Exam Letter with Comments and Exam Analysis IR 05000341/20230012023-06-28028 June 2023 Integrated Inspection Report 05000341/2023001 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III ML23122A2332023-06-26026 June 2023 Issuance of Amendment No. 223 Regarding Revision of Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements IR 05000341/20220102023-06-21021 June 2023 Reissue Fermi Power Plant, Unit 2, Design Basis Assurance Inspection (Teams) Inspection Report 05000341/2022010 ML23166A0892023-06-15015 June 2023 Operator Licensing Examination Approval Fermi Power Plant, June 2023 ML23158A1332023-06-0808 June 2023 Notice of Enforcement Discretion (NOED) for Fermi Power Plant, Unit Two (EPID L-2023-LLD-0000) Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/ Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink ML23130A1032023-05-17017 May 2023 Regulatory Audit Summary Regarding License Amendment Request to Revise Technical Specification Surveillance Requirements Relating to Emergency Diesel Generator Voltage and Frequency IR 05000341/20234022023-05-0101 May 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000341/2023402 ML23118A3612023-05-0101 May 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000341/2023402 ML23114A1172023-05-0101 May 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23115A4152023-04-25025 April 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End-of-Cycle Plant Performance Assessment of Fermi Power Plant, Unit 2 ML23124A2032023-04-10010 April 2023 DTE Electric Company Submittal of Fermi 3 Periodic Reports ML23200A1842023-04-0606 April 2023 Proposed Exam Submittal Letter IR 05000341/20230112023-04-0606 April 2023 Triennial Fire Protection Inspection Report 05000341/2023011 IR 05000341/20234012023-03-17017 March 2023 Security Baseline Inspection Report 05000341/2023401 ML23074A1972023-03-16016 March 2023 Confirmation of Initial License Examination February 2024 IR 05000341/20220062023-03-0101 March 2023 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2022006) ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22325A2992023-02-24024 February 2023 Audit Plan in Support of Review of License Amendment Request to Revise Technical Specification Surveillance Requirements Relating to Emergency Diesel Generator Voltage and Frequency ML23039A1552023-02-14014 February 2023 Integrated Inspection Report 05000341/2022004 IR 05000341/20224032023-02-13013 February 2023 Security Baseline Inspection Report 05000341/2022403 ML23200A2162023-01-20020 January 2023 Outline Submittal Letter 2024-02-05
[Table view] |
Text
October 13, 2022 Mr. Eric Olson Site Vice President DTE Electric Company 6400 North Dixie Highway Newport, MI 48166
SUBJECT:
ENRICO FERMI ATOMIC POWER PLANT, UNIT 1 - U.S. NUCLEAR REGULATORY COMMISSIONS ANALYSIS OF DTE ELECTRIC COMPANYS DECOMMISSIONING FUNDING STATUS REPORT (DOCKET NO.50-016)
Dear Eric Olson:
By letter dated March 31, 2022, the U.S. Nuclear Regulatory Commission (NRC) received the decommissioning funding status (DFS) report for the Enrico Fermi Atomic Power Plant, Unit 1 (Fermi 1) (Agencywide Documents Access and Management System (ADAMS) Accession No. ML22090A097), which was submitted by the DTE Electric Company (DTE, the licensee).
The NRC has reviewed and analyzed the site-specific decommissioning cost estimate for this facility, as required by Section 50.82, Termination of license - For power reactor licensees, of Title 10 of the Code of Federal Regulations (10 CFR). The NRC staff also verified the amount(s) stated within the licensees decommissioning trust fund for Fermi 1 as of December 31, 2021, as well as earnings assumptions and the balance of any other decommissioning funds. Based on the reported decommissioning trust fund balance, the NRC has determined that as of December 31, 2021, DTE is providing a total amount of decommissioning funding assurance in the amount of $3 million in 2021 dollars for Fermi 1, with an additional $35 million available via a DTE Energy (parent company) guarantee for additional financial assurance.
This letter confirms the correspondence, described above, regarding DFS reports for permanently shut down power reactors as required under 10 CFR 50.82(a)(8)(v) - (vi). As of the date of this letter, considering the available information, the NRC has determined that DTE has satisfied the decommissioning funding assurance requirements of 10 CFR 50.82 for Fermi 1 as of December 31, 2021. A summary report reflecting decommissioning power reactor DFS is expected to be completed and made publicly available by the end of calendar year 2022.
In accordance with 10 CFR 2.390, Public inspections, exemptions, requests for withholding, of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRCs ADAMS. ADAMS is accessible from the NRC website at https://www.nrc.gov/reading-rm/adams.html.
E. Olson If you or your staff have any questions regarding the above, please contact me at 301-415-3178 or via email at marlayna.doell@nrc.gov .
Sincerely, Signed by Doell, Marlayna on 10/13/22 Marlayna V. Doell, Project Manager Reactor Decommissioning Branch Division of Decommissioning, Uranium Recovery, and Waste Programs Office of Nuclear Material Safety and Safeguards Docket No.: 50-016 License No.: DPR-9 cc: Fermi ListServ
Ltr ML22285A101 OFFICE NMSS/DUWP/RDB NMSS/DUWP/RDB NMSS/DUWP/RDB NAME MDoell MD SAnderson SA MDoell MD DATE Oct 12, 2022 Oct 13, 2022 Oct 13, 2022