1/25/22 Pre-submittal Meeting Presentation Slides for RR-69 to Extend Containment Tendon Inspection by Three Months Beyond 2/8/22
ML22025A001
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 01/25/2022
From:
Arizona Public Service Co
To:
Division of Operating Reactor Licensing
Lingam S, 301-415-1564
References
EPID L-2022-LRM-0008
Download: ML22025A001 (8)


Text

Palo Verde Nuclear Generating Station Containment Post-Tensioning System Inspection Unit 2 Relief Request 69 Pre-Submittal Call with NRC January 25, 2022

Agenda

  • Introduction
  • Code Required Tendon Surveillance
  • Proposed Relief Request 69
  • Relief Request Summary
  • Schedule
  • Questions/Comments 2

Code Required Tendon Surveillance

  • ASME BPVC Section XI Subsection IWL-2420 requires containment post-tensioning systems to be examined visually every 5 years (10 years for physical exams)
  • 35th surveillance year was February 2020
  • PVNGS deadline for inspection was 2/8/21
  • Extended to 2/8/22 by Relief Request (RR) 66
  • The surveillance was previously performed in 2015 and 2011 (30th and 25th year surveillances)
  • Both surveillances concluded the post-tensioned tendons met the applicable Code requirements with no abnormal degradation of the post-tensioning system identified
  • The 35th year surveillance is currently in progress
  • The final test report will not be complete by 2/8/22 4

Proposed Relief Request 69 Purpose and Basis

  • Requesting relief from the requirements of IWL-2420 regarding the interval between containment tendon inspections for Unit 2
  • Representing a hardship or unusual difficulty without a compensating increase in the level of quality and safety
  • Applies to ASME Code Class CC Concrete Component of Light-Water Cooled Plants - Containment Post-Tensioning System Inspections
  • Requesting approximately 3-month extension of the current 12-month extension provided by RR 66 to permit time to finalize the inspection report and complete the surveillance 5

Proposed Relief Request 69 Purpose and Basis

  • Good faith efforts made to complete by 2/8/22 date
  • Examinations originally scheduled to start in November 2021
  • Delays in vendor completion of work at other sites
  • Inspections initiated at PVNGS January 2022
  • Majority of inspection work complete by 2/8/22
  • Continuing to experience COVID-19 impacts
  • Final vendor report targeted for March 2022
  • Final APS acceptance targeted for April 2022
  • Past Unit 2 examinations support technical adequacy of Unit 2 containment tendons as described in RR 66
  • RR 67 provides a description of Units 1 and 3 similar design and basis for a further extension of certain examinations to 20-years (APS letter 102-08286 dated July 29, 2021, ML21210A300)
  • Data from these examinations will be used to form the basis for a similar Unit 2 RR at a later date 6

Relief Request Summary

  • Provided a one-time extension of the 35th year inspections to 2/8/2022
  • Proposed RR 69 requests an approximately 3-month extension of current 12-month extension provided by RR 66 to permit completion of final test report and surveillance 7

Schedule

  • Planning to submit January 28, 2022
  • NRC approval requested by February 8, 2022 8