RR-67 6-16-21 Pre-Submittal Public Meeting Presentation Slides
ML21165A183
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 06/14/2021
From:
Arizona Public Service Co
To: Siva Lingam
NRC/NRR/DORL/LPL4
Lingam S, 301-415-1564
References
Download: ML21165A183 (12)


Text

Proposed IWL Inspection Alternative Relief Request 67 - Pre-submittal Meeting Palo Verde Nuclear Generating Station (PVNGS)

June 16, 2021

Agenda

  • Introduction
  • Relief Request Summary
  • Current Requirements
  • Alternative Requirements
  • Alternative Justifications
  • Duration of Proposed Alternatives
  • Precedents
  • Schedule

Relief Request Summary

  • Reason for the request:
  • The alternative modified schedule proposed will reduce resources required and safety risks associated with performing the exams while still providing reasonable assurance the containment post-tensioning systems will continue to perform their function.

3

Relief Request Summary

  • ASME BPV Section XI, Subsection IWL requires certain scheduling frequencies and specific tests of post-tensioning system tendons
  • Units 1 and 3: Alternatives are being requested from IWL-2520 ten year surveillance scheduling requirements Unit 2 will be addressed in a subsequent submittal after the next surveillance is completed in Dec 2021 / Jan 2022.
  • Units 1, 2, and 3: Alternatives are being requested from certain IWL-2523 tendon wire and strand testing 4

Current Requirements

  • IWL-2421 - PVNGS Units 1, 2, and 3 are currently using the alternative scheduling requirements of IWL-2421(b):
  • (1) For the containment with the first structural integrity test, all examinations required by IWL-2520 shall be performed at 1, 3, and 10 years, and every 10 years thereafter. In addition, the examinations required by IWL-2524 and IWL-2525 shall be performed at 5 and 15 years, and every 10 years thereafter.
  • (2) For each subsequent containment constructed at the site, all examinations required by IWL-2520 shall be performed at 1, 5, and 15 years, and every 10 years thereafter. In addition, the examinations required by IWL-2524 and IWL-2525 shall be performed at 3 and 10 years, and every 10 years thereafter.

5

Current Requirements IWL-2523.1

  • Requires tendon detensioning and wire sample removal, as follows:
  • One sample tendon of each type shall be completely detensioned. A single wire or strand shall be removed from each detensioned tendon.

IWL-2523.2

  • Requires that tension tests be performed on each removed wire or strand, as follows:
  • Tension tests shall be performed on each removed wire or strand: one at each end, one at mid-length, and one in the location of the most corroded area, if any. []

6

Alternative Requirements - IWL-2421

  • Units 1 and 3:
  • (1) For the containment with the first structural integrity test, all examinations required by IWL-2520 shall be performed every 20 years thereafter.
  • (2) For each subsequent containment constructed at the site, all examinations required by IWL-2520 shall be performed every 20 years thereafter.

NOTE: Unit 2 is currently excluded from this scheduled alternative, and is planned to be addressed in 2022 after the next scheduled Unit 2 surveillance is completed.

7

Alternative Requirements -IWL-2523.1 and IWL-2523.2

  • For Units 1, 2, and 3:
  • IWL-2523.1: Detension a tendon and remove a single wire for examination only if a tendon anchorage visual examination in accordance with IWL-2524 detects a loss of wires in excess of that permitted by the design, or if required as a result of an engineering evaluation
  • IWL-2523.2: Eliminate tension testing to determine the yield strength, ultimate tensile strength, and elongation of tendon wires. Visual examinations shall continue to be performed when detensioning is required.

8

Alternative Justifications

  • Previous IWL examination results indicate excellent performance of the post-tensioning system.
  • Tendon Force trendlines indicate tendons for Units 1 and 3 will remain above the minimum required value beyond the next alternative scheduled surveillance (Code requirement), and even beyond 100 years from initial tensioning.

9

Duration of Proposed Alternatives

  • The proposed alternatives are requested for the third and subsequent intervals until the end of PVNGS plant life.

10

Precedents

  • Millstone Power Station, Unit 2 [ML20287A471]
  • Vogtle Electric Generating Plant, Units 1 and 2 [ML19182A077]
  • Three Mile Island Nuclear Station, Unit 1 [ML19226A023]

11

Schedule

  • Planning to submit in early July 2021
  • NRC approval requested in June 2022 12