ML24003A853

From kanterella
Jump to navigation Jump to search

January 4, 2024 Presubmittal Meeting Presentation-Risk Informed Process for Evaluations (RIPE) License Amendment Request for Safety Injection Tank (SIT) LCO (EPID: L?2023?LRM-0108)
ML24003A853
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 01/03/2024
From: Dennis Galvin
Plant Licensing Branch IV
To: Heflin A
Arizona Public Service Co
Lingam S, 301-415-1564
References
EPID L-2023-LRM-0108
Download: ML24003A853 (1)


Text

Risk-Informed Process for Evaluations (RIPE) License Amendment Request for Safety Injection Tank (SIT) LCO Pre-Submittal Meeting Palo Verde Nuclear Generating Station (PVNGS)

January 4, 2024

Agenda

  • Introduction
  • Case for Action
  • Mitigation Plan
  • Proposed Technical Specification (TS) Changes
  • Background
  • Design Features
  • RIPE Screening Results
  • Risk Insights
  • Schedule 2

Case for Action Recent plant operating experience resulted in a station-initiated effort to increase SIT reliability 4 examples of unexpected SIT depressurization over the last 2 years across all three units 3 failed open SIT vent valves 1 cracked weld 24-hour LCO Action Cycles the organization and does not allow for planning and deliberate execution Potential NOED situation 3

Mitigation Plan Multi-phase effort includes:

1. Increasing the TS allowed outage time
2. Increasing the nitrogen cover pressure band (reduction in required pressure adjustments)
3. Potential vent valve modification to more robust design Risk analysis supports a LAR using the RIPE process to increase the allowed outage time for a single safety injection tank out of service 4

Proposed TS Changes 10 days 5

Proposed TS Changes 6 10 days

=

Background===

  • CE NPSD-994, CEOG Joint Applications Report for Safety Injection Tank AOT/STI Extension, May 1995, provided the following information that supported LCO change from 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> to 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />s:
  • Deterministic and probabilistic findings that support 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> as being either "risk beneficial" or "risk neutral" in comparison to shorter periods for restoring the SIT to OPERABLE status.
  • Best-estimate analysis for a typical PWR that confirmed that, during large-break LOCA scenarios, core melt can be prevented by either operation of one low pressure safety injection (LPSI) pump or the operation of one high pressure safety injection (HPSI) pump and a single SIT.
  • Plant-specific probabilistic analysis that evaluated the risk-impact of the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> recovery period in comparison to shorter recovery periods.

7

Design Features

  • The SITs are credited for both large and small break LOCAs.

- The functions of the four SITs are to supply water to the reactor vessel during the blowdown phase of a LOCA, to provide inventory to help accomplish the refill phase that follows thereafter, and to provide Reactor Coolant System (RCS) makeup for a small break LOCA.

- Each SIT is piped into one RCS cold leg via the injection lines utilized by the High Pressure Safety Injection and Low Pressure Safety Injection (HPSI and LPSI) Systems.

  • The SITs are passive components and requires no operator or control action for them to perform their function.
  • Each SIT is isolated from the RCS by a motor operated isolation valve and two check valves in series.

8

RIPE Screening Results

  • Applicable guidance documents:
  • NEI 21-01, Rev. 1, Industry Guidance to Support Implementation of NRCs Risk-Informed Process for Evaluations, June 2022
  • NRC Guidelines for Characterizing the Safety Impact of Issues, Rev.

2, May 2022

  • TSG-DORL-2021-01, Rev. 3 - NRR Temporary Staff Guidance, Risk-Informed Process for Evaluations, September 2023
  • PVNGS has implemented Risk-Informed Completion Times

[ML19085A525] and 10 CFR 50.69 [ML18243A280]

  • APS qualifies to use the RIPE process
  • Issue screened in as adverse, but minimal impact on safety 9

Risk Insights A plant specific risk assessment was conducted

  • SITs and their safety functions are in the scope of the PVNGS PRA model
  • Quantitative analysis performed for Modes 1 & 2
  • Bounding analysis used to quantify lower Modes (i.e.,

Modes 3 & 4)

  • No risk management actions are required to offset the risk 10

Risk Insights The PRA model used reflected the following:

  • Fully compliant internal events, flooding, fire and seismic PRA models
  • All Other External Hazards listed in RG 1.200, Revision 3, screened out
  • Addressed all NRC license conditions from the 10 CFR 50.69 and RICT License Amendments
  • No open finding level Facts and Observations (F&Os)
  • No newly developed methods
  • No additional key assumptions or sources of uncertainty
  • PRA model fully compliant with NRC RG 1.200, Revision 3 11

Risk Insights - Modes 3 & 4 PVNGS does not have a low power/shutdown PRA model to assess the change in CDF and LERF.

  • Per NEI 21-01: Where PRA models are not available, conservative or bounding analyses may be performed to quantify the risk impact (e.g., external events, low power and shutdown).
  • The following references stipulate that when RCS pressure is at 1000 psi that there is negligible probability of a pipe break and it would be appropriate to reduce the at power initiating event frequencies for large and small LOCA when quantifying risk impact of extending the AOT.
  • Therefore, a bounding conservative analysis associated with extending the AOT will be quantified using the PVGS at-power PRA model with no adjustments to large or small LOCA initiating events.

12

Risk Insights - Modes 1 & 2 Case CDF1 LERF1 PVNGS Baseline 2.62x10-6/year 1.28x10-7/year PVNGS SIT Sensitivity 2.96x10-6/year 1.31x10-7/year Yearly CDF Increase based on 10-day AOT 1.12x10-8/year 1.07x10-10/year (Downtime freq = 1.22/year)

NEI 21-01 Acceptance Guideline 1.0x10-7/year 1.0x10-8/year NRC RG 1.174 Acceptance Guideline 1.0x10-4/year 1.0x10-5/year Note 1 - Internal events (IE) results are bounding due to IE PRA model using a lower truncation value than the multi-hazard model. Additionally, the increase in risk associated with having a SIT out of service is driven by internal events hazards (large and small LOCA initiating events).

Therefore, extending the Completion Time for Condition B of LCOs 3.5.1 and 3.5.2 from 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to 10 days is not risk-significant and has a minimal impact on safety.

13

Path to Schedule

  • Challenge board w/ NEI - December 15, 2023 (Complete)
  • Pre-submittal meeting w/ NRC - January 4, 2024
  • Completion of PRA Input - January 2024
  • Integrated Decision-Making Panel - January 2024
  • Final submittal - late February 2024
  • Requested approval - May 2024
  • Implementation - June 2024 14

Questions