NRC / NEI / UTILITY MTG 6/11/14 4" & 6" RD/CH Drain Piping Inspection at the Palo Verde Nuclear Generating Station Utilizing Quest's HYDRA' Intelligent Pigging Technology

- Dan Wittas -

NRC / NEI / UTILITY MTG 6/11/14 1

WHY IN-LINE INSPECTION?

  • Consequence of a leak on these drain lines
  • Location of the piping

- Between 3 large tanks

- Under other utilities

  • Relatively accessible for deployment and retrieval inside the lines NRC / NEI / UTILITY MTG 6/11/14 2

NRC / NEI / UTILITY MTG 6/11/14 3

WHY IN-LINE INSPECTION?

Location of the RD/CH piping

NRC / NEI / UTILITY MTG 6/11/14 4

WHY IN-LINE INSPECTION?

REFUELING WATER TANK

NRC / NEI / UTILITY MTG 6/11/14 5

WHY IN-LINE INSPECTION?

HOLDUP TANK REACTOR MAKEUP WATER TANK

NRC / NEI / UTILITY MTG 6/11/14 6

WHY IN-LINE INSPECTION?

HOLDUPTANK SUMP

NRC / NEI / UTILITY MTG 6/11/14 7

WHY IN-LINE INSPECTION?

NRC / NEI / UTILITY MTG 6/11/14 8

WHY IN-LINE INSPECTION?

RD LINES 4" THREADED CAP AND FLOOR DRAIN

NRC / NEI / UTILITY MTG 6/11/14 9

IN-LINE INSPECTION PLAN

  • Build a team - BP Engr / Ops / Proj Mgr /

ISI / RP / Work Planner

  • Select vendor and technology

- Site visits to 2 potential vendors

- Consideration of NDE technology, FME, equipment decontamination

- Quest's HYDRA' Intelligent Pigging Ultrasonic Technology was selected

NRC / NEI / UTILITY MTG 6/11/14 10 IN-LINE INSPECTION PLAN

  • Full scale mockup for deployment, retrieval and blind flaw detection capability

- The inspection tool could be deployed and retrieved, thru 90s and a tee.

- The Quest Hydra' UT inspection tool detected 26 of 34 flaws. All 8 undetected flaws were below the published detection threshold. 10 flaws below the threshold were detected, including 2 - 1/8 diameter flaws.

NRC / NEI / UTILITY MTG 6/11/14 11 IN-LINE INSPECTION PLAN

  • Contingencies / Lessons Learned -

- Design engineering T-min acceptance criteria

- Sump pumps need to be removed for access

- 2 Launchers

- Backup water pump & inspection pig

- Pre-req for hot water flush to dilute boric acid

- Leak test ILI piping and use catch basins

NRC / NEI / UTILITY MTG 6/11/14 12 IN-LINE INSPECTION PLAN FG-47 Pump House Floor Drain Ground Penetration FG-46 Ground Penetration Valve Pit Sump Pit

NRC / NEI / UTILITY MTG 6/11/14 13 IN-LINE INSPECTION PLAN FULL SCALE MOCK-UP W/ 32 FLAWS PRIOR TO BURIAL

NRC / NEI / UTILITY MTG 6/11/14 14 IN-LINE INSPECTION PLAN

  • Work and inspection instructions, with

- Initial conditions, such as, remove sump pumps, remove 90° elbow in sump, disconnect tank overflow pipes, cap HUT pump skid and floor drains

- Connection of ILI equip, pump, launcher, pipe and valves

- Operate the ILI, evaluate the results and restore systems