MONTHYEARML24303A4232024-10-11011 October 2024 PCA Letter to NRC Vogtle Hurricane Helene ML23165A2492023-06-14014 June 2023 4Q 2022 Performance Summary U4 ML22334A0832022-12-0101 December 2022 Attachment 1 - Targeted ITAAC Listing VEGP Unit 4 ML22334A0842022-12-0101 December 2022 Attachment 2 - ITAAC Family Listing VEGP Unit 4 ML21278A3552021-10-0505 October 2021 Enclosure 2: Safety Determination Input for IEEE 384 Separation Issues and Safety Determination Input for IEEE 384 Separation Issues within IDS Enclosures ML21278A3562021-10-0505 October 2021 Enclosure 3: AP1000 Plant At-Power Internal Events PRA Risk Assessment for Spatial Separation Criteria Nonconformances ML21277A0212021-10-0404 October 2021 2021 Q2 Cross Cutting Page ML20358A1802020-12-23023 December 2020 (VEGP) Units 3 and 4 - Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2) - Alternative Requirements for A8ME Section XI Examination Coverage of Weldolet Branch Connection Welds (VEGP 3&4-PSI/ISI-ALT-15) ML20343A0432020-12-0808 December 2020 Construction Reactor Oversight Process Resources December 2020 ML20022A0602020-01-20020 January 2020 Assessment of Communications in Response Request for Information for Vogtle Electric Generating Plant Units 3 and 4 ML19325C6722019-11-21021 November 2019 Staff Bullets for October 21, 2019 Public Meeting, Vogtle Electric Generating Plant Units 3 and 4, LAR-19-017, Request for License Amendment: Removal of the PRHR-HX Natural Circulation Test ML19233A0072019-08-22022 August 2019 NRC Contacts for New Power Reactors ML19113A0922019-04-23023 April 2019 Functional Arrangement ITAAC Acceptance Criteria R1 ML17235B1482017-08-23023 August 2017 U.S. Nuclear Regulatory Commission - Tornado Missile Risk Evaluator (TMRE) Methodology Topics and Methodology Feedback ML14141A6272014-05-20020 May 2014 LTR-14-0288-Ticket - Senator Edward J. Markey Ltr. Information About NRC-Sanctioned Job Shadow Program with China ML14094A3582014-04-0808 April 2014 Enclosure - PWROG Peer Review Form 4-03-14, Table 1 ML14078A6212014-04-0101 April 2014 Enclosure 3 - RASCAL 4.3 Inputs for Site Boundary Dose Projections ML14072A4632014-03-0606 March 2014 Response to NRC Request for Additional Information 2-1, Sheet 3 of 10 ML14072A4542014-03-0606 March 2014 Response to NRC Request for Additional Information Site Plan, 2-1, Sheet 1 of 1 ML12056A0522012-03-12012 March 2012 Enclosure 6 - List of Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status ML1135406252012-02-10010 February 2012 Amendment to Indemnity Agreement No. B-107 - Amendment No. 6 ML12010A0342011-12-28028 December 2011 Onsite Ground/Surface Water Questionnaire, Onsite Radiological Effluent/Remp Monitoring Program ML1122005052011-08-0404 August 2011 Crop Tabletop Example Findings ML1132604282011-01-0303 January 2011 NRC 2011 Vogtle ML1019301932010-06-0909 June 2010 Undated Onsite Ground/Surface Water Monitoring Questionnaire 4 for Vogtle ML1019304602010-03-25025 March 2010 List of Historical Leaks and Spills at Us Commercial Nuclear Power Plants NL-08-0869, Enclosure 11, List of Regulatory Commitments2008-06-27027 June 2008 Enclosure 11, List of Regulatory Commitments ML0811902022008-04-24024 April 2008 End of Cycle Public Meeting Attendee List ML0808000362008-03-13013 March 2008 List of Attendees, 03/13/2008 Summary of Meeting with Eight Operating Nuclear Power Plant Licensees to Discuss Emerging Metallurgical Issues Certain Welds in Reactor Coolant System for Pressurized-Water Reactors ML0806704192008-03-0707 March 2008 CDBI Findings ML0732407112007-11-0505 November 2007 Project Wings (Wildlife Incentives for Nongame and Game Species) ML0732407472007-11-0505 November 2007 Electrical Design Parameters of Typical 230kv and 500kv Transmission Lines Terminating Into Plant Vogtle ML0732407642007-11-0505 November 2007 Vogtle - FSAR-2, Calculation Package ML0732400242007-10-25025 October 2007 Examples of Max Thermal Power License Conditions ML0726301142007-09-14014 September 2007 / P. Paquin Ltr Amendment to Certificate of Compliance No. 9208 for the Model No. 10-142B Package (TAC L24117)/S121170 ML0732407042007-06-27027 June 2007 Cooperative Safe Harbor Management Agreement (2005 Updated Version) No. 28 for Red-Cockaded Woodpeckers (Picoides Borealis) and Their Habitat on Private Land in Georgia ML0714103852007-05-17017 May 2007 Enclosure 1 - Attendee List for 05/17/2007 Vogtle Public Meeting ML0713402122007-05-10010 May 2007 Log of Congressional Correspondence for January 16, 2007 - February 28, 2007 ML0634705992006-12-14014 December 2006 Plant Service List ML0619203352006-04-14014 April 2006 Attachment 3 - List of Attendees for April 14, 2006 Public Meeting to Discuss Vogtle Early Site Permit Seismic Activities ML0609006412005-10-11011 October 2005 Spent Fuel Pool Action Plan, from Entergy ML0732407432005-08-22022 August 2005 Submittal of Photocopies of the Highway Capacity Manual 2000 ML0732407362005-02-21021 February 2005 Safe Drinking Water Information System ML0404104922004-02-20020 February 2004 Order EA-03-009 Service List ML0732407172003-07-24024 July 2003 Movement and Population Size of American Shad Near a Low-Head Lock and Dam ML0732407292000-01-31031 January 2000 Habitat Utilization and Biological Characteristics of Adult Atlantic Sturgeon in Two South Carolina Rivers ML0732407661999-07-31031 July 1999 Savannah River Basin Comprehensive Reconnaissance Study ML0732407411999-06-0606 June 1999 State of Georgia, Permit No. GA0026786, Authorization to Discharge Under the National Pollutant Discharge Elimination System ML0732406901998-04-0101 April 1998 State of Georgia, Permit to Operate a Public Water System Issued on 04/01/1998 to Vogtle Plant ML0630002251997-05-0808 May 1997 Georgia Power Transmission Bulletin No. 6-10: Maintenance of Plant Vogtle Transmission Line Corridors. Revised 2024-10-11
[Table view] |
Text
CONSTRUCTION REACTOR OVERSIGHT PROCESS RESOURCES The U.S. Nuclear Regulatory Commission (NRC) staff originally estimated that direct inspection will require 35,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> per unit over the course of a 5-year nuclear power plant construction project. As of December 8, 2020, revised estimates are approximately 40,900 hours0.0104 days <br />0.25 hours <br />0.00149 weeks <br />3.4245e-4 months <br /> for Vogtle Unit 3 and 28,800 hours0.00926 days <br />0.222 hours <br />0.00132 weeks <br />3.044e-4 months <br /> for Vogtle Unit 4. These revised estimates include:
- 20,200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> for inspections related to ITAAC for Vogtle Unit 3, and 13,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for Vogtle Unit 4;
- 10,700 hours0.0081 days <br />0.194 hours <br />0.00116 weeks <br />2.6635e-4 months <br /> for construction and operational program inspections for Vogtle Unit 3, and 5,800 hours0.00926 days <br />0.222 hours <br />0.00132 weeks <br />3.044e-4 months <br /> for Vogtle Unit 4;
- 5,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for reactive inspections above the baseline program in response to licensee performance issues, allegations, and nonperformance issues or events;
- and 5,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for technical support of construction inspections.
Table 1 and figure 1 show the total number of direct inspection hours expended through November 2020, for Vogtle Units 3 and 4.
Table 1: Actual Total Construction Inspection Program Resource Expenditures Unit ITAAC Inspection Program Reactive/Allegation- Technical Total Hours/Percentage Inspections Related Inspections Support*
of Planned Inspections Vogtle, 17,733 / 88% 8,039 544 2,556 28,872 Unit 3 Vogtle, 9,253 / 71% 4,850 342 1,753 16,198 Unit 4
- To date, NRC Headquarters technical staff inspection support has not been linked to a specific docket and has not been fee billable. Therefore, it is not possible to distinguish the technical support hours expended by the Office of Nuclear Reactor Regulation on each unit. In Table 1, the total hours expended on technical support have been split between the units.
December 8, 2020 35000 30000 25000 20000 15000 10000 5000 0
2012 2013 2014 2015 2016 2017 2018 2019 2020 2020 Proj Hours Vogtle, Unit 3, Cumulative Data Vogtle, Unit 4, Cumulative Data Figure 1 Total cumulative direct inspection hours for Vogtle, Unit 3 and 4 20000 18000 16000 14000 12000 10000 8000 6000 4000 2000 0
2012 2013 2014 2015 2016 2017 2018 2019 2020 2020 Vogtle, Unit 3, ITAAC direct inspections Proj Hours Vogtle, Unit 4, ITAAC direct inspections Figure 2 Cumulative ITAAC-related direct inspection hours for Vogtle, Units 3 and 4 Figure 2 summarizes the direct inspection hours expended for inspections related to ITAAC since the start of construction at Vogtle Units 3 and 4. The staff estimates that there will be approximately 20,200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> of direct inspection related to ITAAC for Unit 3 and 13,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> of direct inspection related to ITAAC for Unit 4.
14000 12000 10000 8000 6000 4000 2000 0
2012 2013 2014 2015 2016 2017 2018 2019 2020 2020 Proj Hours Vogtle, Unit 4, Program direct inspection Vogtle, Unit 4, QA direct inspection Vogtle, Unit 3, Program direct inspection Vogtle, Unit 3, QA direct inspection Figure 3 Cumulative quality assurance and program inspection for Vogtle, Units 3 and 4 Figure 3 summarizes the NRC staff resources in hours expended for programmatic inspection since the start of construction at Vogtle, Units 3 and 4. Based on Vogtles schedule, total cumulative program inspections are estimated at 10,700 hours0.0081 days <br />0.194 hours <br />0.00116 weeks <br />2.6635e-4 months <br /> for Vogtle Unit 3, and 5,800 hours0.00926 days <br />0.222 hours <br />0.00132 weeks <br />3.044e-4 months <br /> for Unit 4.
3000 2500 2000 1500 1000 500 0
2012 2013 2014 2015 2016 2017 2018 2019 2020 2020 Proj Hours Vogtle, Unit 3, Reactive and Allegations Vogtle, Unit 3, HQ Technical Support Vogtle, Unit 4, Reactive and Allegations Vogtle, Unit 4, HQ Technical Support Figure 4 Cumulative reactive and technical support hours for Vogtle, Units 3 and 4 Figure 4 summarizes the direct inspection hours expended for reactive and allegation inspections and hours spent providing technical support for inspections since the start of construction at Vogtle, Units 3 and 4. The staff has not identified a need to revise the estimate of 5,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for reactive inspections above the baseline program in response to licensee performance issues, allegations, and nonperformance issues or events, or the 5,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> estimated for technical support for construction inspections.