Rev to Monthly Operating Rept for Feb 1984
ML20084E425
Person / Time
Site: Millstone Dominion icon.png
Issue date: 02/29/1984
From: Borchert R
NORTHEAST NUCLEAR ENERGY CO.
To:
Shared Package
ML20084E405 List:
References
NUDOCS 8405020274
Download: ML20084E425 (1)


Text

__ ____ -

O REVISED OPERATING DATA REPORT DOCKET NO. 50-336 DATE l COMPLETED BY R. Borchert

! TELEPHONE (203) 447-1791 Ext. 4418 OPERATING STATUS

1. Unit Name: Millstone Unit 2 Notes Items 21 and 22
2. Reporting Period: February 1984 (revised) cumulative are weighted
3. Licensed Thermal Power (MWt): 2700 ave. unit operated at
4. Nameplate Rating (Gross MWe): 909 2560 MW Thermal prior
5. Design Electrical Rating (Net MWe): 870 to its uprating to the
6. Maximum Dependable Capacity (Gross MWe): 895 current 2700 MW
7. Maximum Dependable Capacity (Net MWe): 864 thermal power level.
8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7)

Since Last Report, Give Reasons:

N/A

9. Power Level To Which Restricted, If Any (Net MWe): N/A
10. Reasons For Restrictions, If Any:

N/A This Month Yr.-to-Date Cumulative

11. Hours In Reporting Period 696 1440 71712
12. Number Of Hours Reactor Was Critical- 696 1316.9 49682.2
13. Reactor Reserve Shutdown Hours 0 0 2205.5
14. Hours Generator On-Line 577.7 1014.1 47196.3
15. Unit Reserve Shutdown Hours 0 0 468.2
16. Gross Thermal Energy Generated (MWH) 1507373 2317304 118628973
17. Gross Elec. Energy Generated (MWH) _486800 735401 38541779
18. Net Electrical Energy Generated (MWH) 465633 693900 36909601
19. Unit Service Factor 83.0 70.4 65.8
20. Unit Availability Factor 83.0 70.4 66.5
21. Unit Capacity Factor (Using MDC Net) 77.4 55.8 61.2
22. Unit Capacity Factor (Using DER Net) 76.9 55.4 60.4
23. Unit Forced Outage Rate 17.0 14.'6 _

19.0

24. Shutdowns Scheduled Over Next 6 Months (Type Date, and Duration of Each):

None

25. If Shut Down At End Of Report Period, Estimated Date of Startup: N/A
26. Units In Test Status (Prior to Commercial Operation): Forecast Achieved i l

INITIAL CRITICALITY N/A N/A l INITIAL ELECTRICITY fi/X N/A l COMMERCIAL OPERATION N/A. N/A