MONTHYEARML0209101702002-04-0404 April 2002 Documentation of Conference Call to Calvert Cliffs Nuclear Power Plant, Unit No. 1 and 2 on March 26, 2002, Regarding Reactor Vessel Head Inspection Activities Project stage: Other ML0214302462002-05-28028 May 2002 Bulletin 2002-01, Reactor Pressure Vessel Head Degradation and Reactor Coolant Pressure Boundary Integrity, 15-Day Response Project stage: Other ML0224000952002-09-0606 September 2002 Bulletin 2002-01, Reactor Pressure Vessel Head Degradation and Reactor Coolant Pressure Boundary Integrity, 15-Day Response for Calvert Cliffs Nuclear Power Plant, Unit No. 1 (Tac MB4533) Project stage: Other ML0232304472002-11-19019 November 2002 Bulletin 2002-01, Reactor Pressure Vessel Head Degradation and Reactor Coolant Pressure Boundary Integrity, 60-Day Response for Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 Request for Additional Information Project stage: RAI ML0306400672003-02-28028 February 2003 BL2002-01 60-Day Response Draft Audit Plan Project stage: Draft Other 2002-05-28
[Table View] |
|
---|
Category:Memoranda
MONTHYEARML21333A2412021-11-24024 November 2021 Level 1 FEMA Finding Successfully re-demonstrated on November 23, 2021 ML21277A2472021-11-0505 November 2021 Notification of Significant Licensing Action - Proposed Issuance of Order Approving the Transfer of Licenses for Which a Hearing Has Been Requested - Exelon Generation Company, LLC; Et. Al ML21130A0382021-05-21021 May 2021 Memo to File - Draft Request for Additional Information Relief Request CISI-03-01 Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements ML21067A0922021-04-20020 April 2021 Documentation of Decision by NRC Staff That EPRI Report 3002012988, Alternative Approaches for Addressing Seismic Risk in 10 CFR 50.69 Risk-Informed Categorization, Meets Criteria for a Federal Record ML20212L5772020-11-20020 November 2020 Memo to File: Environmental Assessment-Finding of No Significant Impact and NRC Financial Analysis for Constellation and Exelon Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Calvert Cliffs Nuclear Pow ML19298C9722019-10-31031 October 2019 50.69 Apla SE Input L-2018-LLA-0482 ML17142A2382017-05-25025 May 2017 OEDO-17-00280 - Briefing Package for Drop-In Visit on June 9, 2017, by Senior Management of Exelon Generation Company, LLC with Chairman Svinicki, Commissioner Baran, and Commissioner Burns ML16075A4562016-04-12012 April 2016 February 24, 2016, Summary of Meeting with Exelon Generation Company, LLC, to Discuss the Flaw Indication in the Calvert Cliffs Unit 1 Pressurizer Safety Valve Dissimilar Metal Weld ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML16075A3292016-03-16016 March 2016 OEDO-16-00165 - Briefing Package for Drop-In Visit on March 23, 2016, by Senior Management of Exelon Generation Company, LLC with the NRC Executive Director for Operations ML14363A0452014-12-29029 December 2014 Safety Evaluation Close-out Letter for Calvert Cliffs Nuclear Power Plant and Independent Spent Fuel Storage Installation with Enclosure ML14055A2132014-02-25025 February 2014 Summary of Telephone Conference Regarding the Verbal Authorization of Relief Request RR-ISI-04-08, Revision 1 ML14003A0242014-01-10010 January 2014 Summary of Telephone Conference Regarding the Verbal Authorization of Relief Request RR-ISI-04-09 ML13304B4032013-11-0101 November 2013 Notice of Forthcoming Meeting with Constellation Energy Nuclear Group, LLC, ML13267A2852013-09-25025 September 2013 Interim Staff Evaluation and Request for Additional Information - Calvert Cliffs Nuclear Plant, Unites 1 and 2 Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) ML13226A0902013-08-14014 August 2013 Notice of Forthcoming Meeting with Constellation Energy Nuclear Group, LLC ML13214A3532013-08-0606 August 2013 Notice of Forthcoming Pre-Application Meeting with Constellation Energy Nuclear Group, LLC (MF2516 and MF2517) ML13045A1822013-02-19019 February 2013 March 20, 2013, Notice of Forthcoming Teleconference with Calvert Cliffs and Nrc/Nrr Staff to Have Additional Discussions of Licensees'S Proposed Path for Resolution of Generic Letter 2004-02 ML13050A5112013-02-19019 February 2013 MC4672-3 Corrected Notice -Public Meeting on March 20, 2013 Re-GL2004-02 ML13196A2202012-06-0606 June 2012 Memo from B. Balsam, NRR and D. Logan, NRR to J. Susco, NRR on Summary of Section 7 Consultation Activities Related to the National Marine Fisheries Service'S Final Rule to List the Atlantic Sturgeon ML12136A5672012-05-17017 May 2012 Summary of Meeting with Constellation Energy to Discuss the Constellation Apparent Violation of NRC Regulations at Title 10 of the Code of Federal Regulations Part 50.9 ML12107A5052012-04-16016 April 2012 Forthcoming Category 1 Public Meeting with Constellation Energy Nuclear Group, LLC to Discuss Preliminary Enforcement ML12073A2912012-03-13013 March 2012 Notice of Public Meeting with Constellation Energy Nuclear Group, LLC Regarding NRCs Assessment of Safety Performance at Calvert Cliffs Nuclear Power Plant ML1131102432011-10-24024 October 2011 October 14, 2011, Summary of License Amendment Request (LAR) No. 10 Pre-Application Meeting with Calvert Cliffs Nuclear Power Plant, LLC, (TAC No. L24576) ML1113206252011-05-17017 May 2011 Notice of Forthcoming Closed Meeting with Calvert Cliffs Nuclear Power Plant, LLC and Areva to Discuss Transition to Areva Fuel ML1011903842010-05-0606 May 2010 Notice of Forthcoming Conference Call with Calvert Cliffs to Discuss Supplemental Responses to Generic Ltr. 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors ML0909705822009-04-0707 April 2009 Phone Call Summary with Licensees and Alion Science and Technology on April 2, 2009 to Address NRC Staff Position on Chemical Effects Refinements ML0903701402009-02-0606 February 2009 Probabilistic Assessment of Flaw in Support of Calvert Cliffs Unit 2 Relief Request ISI-020 ML0833102772008-10-24024 October 2008 DHS, Calvert Cliffs Consultation Report ML0809200582008-04-18018 April 2008 Summary of Phone Call with Licensees Concerning Sump Strainer Head Loss Testing ML0807400842008-03-14014 March 2008 Draft Regulatory Guide for Comment ML0706400412007-03-0606 March 2007 Commitment Lists for Renewed Operating License (ROL) Plants with No Commitment Appendix Attached to Its ROL Sers/Nuregs for Use with IP-71003 ML0617805592006-07-10010 July 2006 Revised Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors. ML0611101672006-04-21021 April 2006 Results of PTS Analysis of Calvert Cliffs Unit 1 to Post as Public Documents Into ADAMS ML0525007022005-09-20020 September 2005 Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors. ML0524101502005-08-30030 August 2005 Summary of Telephone Conference on March 7, 2005, Regarding Steam Generator Tube Inspections, Calvert Cliffs Nuclear Power Plant, Unit No. 2 ML0503901492005-02-23023 February 2005 Response to Generic Letter 2004-01, Requirements for Steam Generator Tube Inspections ML0433501182004-12-0303 December 2004 Reactor Oversight Process Midcycle Self - Assessment Performance Metrics ML0336403322004-01-0606 January 2004 Correction of License Authority Files ML0332900462003-12-11011 December 2003 Review of Revision 32 to the Updated Final Safety Analysis Report (UFSAR) ML0327205272003-10-21021 October 2003 Plan and Schedule for Implementation of Staff Position on the Station Blackout (SBO) Issue ML0314906662003-06-0303 June 2003 Summary of Meeting Held on May 13, 2003, Between the U.S. Nuclear Regulatory Commission (NRC) Staff and Calvert Cliffs Nuclear Power Plant, Inc., the Elimination of Offsite Review Committees ML0310705002003-04-17017 April 2003 Basf, Radioactive Waste Manifests, Princeton and Ewing Sites, Dtd January 2001 to September 2002 ML0308404632003-04-0101 April 2003 Closure of TAC Nos. MB2437 and MB2438 ML0307205722003-03-26026 March 2003 Telephone Conversation with Representatives of Calvert Cliffs Nuclear Power Plant, Inc., Concerning the Licensee'S Ongoing Reactor Pressure Vessel Head Inspection Program ML0228801162002-10-15015 October 2002 Evaluation of the Risk Assessment Information Provided by Calvert Cliffs Nuclear Power Plant in Support of Its Request to Decrease the Surveillance Testing Interval for Verifying Boron Concentration in the Safety Injection Tanks from Once E ML0215803662002-06-0606 June 2002 Memo to R. Bellamy, RGN-I from: M. Tokar Subject: Region I Independent Spent Fuel Storage Installation Inspection Plans Attachment: Sfpo Comments to Region I Integrated Inspection Plans ML0210603052002-05-24024 May 2002 Reply to Licensee'S Response to Order for Interim Safeguards and Security Compensatory Measures ML0209101702002-04-0404 April 2002 Documentation of Conference Call to Calvert Cliffs Nuclear Power Plant, Unit No. 1 and 2 on March 26, 2002, Regarding Reactor Vessel Head Inspection Activities 2021-05-21
[Table view] |
Text
April 4, 2002 MEMORANDUM TO: Joel Munday, Acting Chief, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Donna Skay, Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
DOCUMENTATION OF CONFERENCE CALL TO CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NO. 1 ON MARCH 26, 2002, REGARDING REACTOR VESSEL HEAD INSPECTION ACTIVITIES (TAC NO. MB4533)
On March 26, 2002, the NRC staff had a conference call with Calvert Cliffs Nuclear Power Plant, Inc. (CCNPPI) to discuss the results of their reactor vessel head inspections for Unit 1 and potential impact of the Davis-Besse control rod drive mechanism (CRDM) inspection findings (see: NRC BULLETIN 2002-01, dated March 18, 2002.) During the March 26, 2002, call, CCNPPI addressed the following areas.
- 1. Inspection of the reactor vessel head: The licensee performed a qualified visual inspection of 100% of the nozzles on the vessel head underneath the insulation. These inspections were performed with a video probe. The licensee found some boric acid residue during the inspections but found no indication of degradation of the reactor vessel head.
- 2. History of boric acid leaks: The licensee stated that a leakage event in 1994 from instrumentation nozzle flanges left boric acid residue around two of the flanges. The residue was cleaned up during the current inspection. After removal of the residue, the licensee found no evidence of corrosion. This was the first bare metal inspection of the area since the leakage in 1994 and no additional leakage events have occurred since then.
In conclusion, the inspections of Calvert Cliffs, Unit 1 did not identify any degradation of the reactor vessel head similar to that observed at Davis-Besse. Based on the preliminary findings from Davis-Besse, the inspections performed by the licensee, and the licensee's susceptibility to nozzle cracking, the NRC staff did not identify any issues that needed additional follow-up prior to plant restart. The staff will document its formal review after receiving the licensee'sBulletin 2002-01 response.
Docket No. 50-317
MEMORANDUM TO: Joel Munday, Acting Chief, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Donna Skay, Project Manager, Section 1 /RA/
Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
DOCUMENTATION OF CONFERENCE CALL TO CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NO. 1 ON MARCH 26, 2002, REGARDING REACTOR VESSEL HEAD INSPECTION ACTIVITIES (TAC NO. MB4533)
On March 26, 2002, the NRC staff had a conference call with Calvert Cliffs Nuclear Power Plant, Inc. (CCNPPI) to discuss the results of their reactor vessel head inspections for Unit 1 and potential impact of the Davis-Besse control rod drive mechanism (CRDM) inspection findings (see: NRC BULLETIN 2002-01, dated March 18, 2002.) During the March 26, 2002, call, CCNPPI addressed the following areas.
- 1. Inspection of the reactor vessel head: The licensee performed a qualified visual inspection of 100% of the nozzles on the vessel head underneath the insulation. These inspections were performed with a video probe. The licensee found some boric acid residue during the inspections but found no indication of degradation of the reactor vessel head.
- 2. History of boric acid leaks: The licensee stated that a leakage event in 1994 from instrumentation nozzle flanges left boric acid residue around two of the flanges. The residue was cleaned up during the current inspection. After removal of the residue, the licensee found no evidence of corrosion. This was the first bare metal inspection of the area since the leakage in 1994 and no additional leakage events have occurred since then.
In conclusion, the inspections of Calvert Cliffs, Unit 1 did not identify any degradation of the reactor vessel head similar to that observed at Davis-Besse. Based on the preliminary findings from Davis-Besse, the inspections performed by the licensee, and the licensee's susceptibility to nozzle cracking, the NRC staff did not identify any issues that needed additional follow-up prior to plant restart. The staff will document its formal review after receiving the licensee'sBulletin 2002-01 response.
Docket No. 50-317 DISTRIBUTION PUBLIC R. Laufer Sam Collins Brian Sheron D. Skay Jon Johnson Bill Kane S. Bloom Bill Borchardt M. Evans, RGI S. Little Mike Case PDI-1 Reading ACCESSION No. ML020910170 *See previous concurrence OFFICE PDI-1/PM PDI-/LA NRR/EMCB (A)SC:PDI-1 NAME DSkay SLittle SBloom* JMunday DATE 4/04/02 4/04/02 4/04/02 4/04/02 OFFICIAL RECORD COPY