MONTHYEARML24297A6392024-10-30030 October 2024 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML24128A2402024-05-0808 May 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24123A0502024-05-0202 May 2024 2023 Annual Assessment Public Meeting Summary Meeting Number 20240479 ML24124A0342024-05-0101 May 2024 Summary of Public Meeting Concerning Annual Assessment of Catawba Nuclear Station Units 1 and 2, McGuire Nuclear Station Units 1 and 2, Oconee Nuclear Station Units 1, 2, and 3, Brunswick Steam Electric Plant Units 1 and 2, Shearon Harris ML24122C6932024-05-0101 May 2024 Referral of Petition to Intervene and Request for Hearing Re Subsequent License Renewal Application from Duke Energy Carolinas, LLC for Oconee Units 1, 2 & 3 ML24071A1692024-03-15015 March 2024 February 2024 Subsequent License Renewal Public Draft Environmental Impact Statement Meetings-Memo ML24047A2092024-02-22022 February 2024 Calendar Year 2023 Baseline Inspection Completion ML23118A2852023-05-0202 May 2023 Public Meeting Summary - 2022 Annual Assessment Meeting Regarding Catawba Nuclear Station, McGuire Nuclear and Oconee Nuclear Station ML23047A3822023-03-21021 March 2023 Summary of December 15, 2022 Periodic Advanced Reactor Stakeholder Public Meeting ML22349A5052023-02-0808 February 2023 Results of a Reactor Oversight Process Self Assessment Effectiveness Review of the Recommendations from IP 95003 at Arkansas Nuclear One ML22299A0482023-01-11011 January 2023 Final Environmental Assessment and Finding of No Significant Impact for the Duke Energy’S Updated Decommissioning Funding Plans Submitted in Accordance with 10 CFR 72.30(C) for Oconee Nuclear Station Independent Spent Fuel Storage Installat ML22349A1482022-12-19019 December 2022 Transmittal Letter for Oconee SE for SLRA Review ML22193A2542022-08-0505 August 2022 SLRA - Audit Report ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML22111A3142022-05-0202 May 2022 Limited Aging Management Audit Plan Regarding the Subsequent License Renewal Application Review ML22108A1382022-04-18018 April 2022 Annual Assessment Public Meeting Summary ML22084A6142022-04-0404 April 2022 SLRA - Summary of March 16, 2022 (Closed Public Meeting) ML22024A1392022-03-11011 March 2022 SLRA - Request for Withholding Information ML22034A3932022-02-16016 February 2022 Calendar Year 2021 Security Baseline Completion Memo ML21347A0102021-12-20020 December 2021 Proposed Alternative to Implement ASME Code Case OMN-26 ML21333A2412021-11-24024 November 2021 Level 1 FEMA Finding Successfully re-demonstrated on November 23, 2021 ML21279A1542021-11-0808 November 2021 August 25, 2021, Oconee Nuclear Station, Units 1, 2, and 3 Subsequent License Renewal Application Public Environmental Scoping Meeting Summary Memo ML21277A2472021-11-0505 November 2021 Notification of Significant Licensing Action - Proposed Issuance of Order Approving the Transfer of Licenses for Which a Hearing Has Been Requested - Exelon Generation Company, LLC; Et. Al ML21280A2962021-10-22022 October 2021 Replacement of Page 2 to Letter Dated June 30, 2020, Titled License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions (EPID L-2020-LLA0150) ML21295A0882021-10-21021 October 2021 Fiscal Year 2021 Research and Test Reactors Inspection Program Completion Status ML21288A0392021-10-18018 October 2021 September 14, 2021, Summary of Public Workshop on Scale/Melcor Source Term Demonstration Project - Pebble-Bed Molten-Salt-Cooled Reactor ML21273A1772021-10-0101 October 2021 Fiscal Year 2021 Research and Test Reactors Inspection Program Completion Status ML21064A3502021-07-26026 July 2021 OEDO-21-00048 - Oconee Nuclear Station, Units 1, 2, and 3 - Response Memorandum ML21195A2692021-07-14014 July 2021 Meeting Summary: Pre-Submittal Meeting for the Oconee Subsequent License Renewal Application (EPID Number: L-2020-RNW-0028) (Docket Numbers: 50 269, 50-270, and 50-287) - Memo ML21181A3352021-07-0101 July 2021 June 23, 2021, Summary of Public Meeting to Discuss Technology Inclusive Content of Application Project ML21158A2232021-06-0808 June 2021 Meeting Summary for Ticap Workshop 3 ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML21130A0382021-05-21021 May 2021 Memo to File - Draft Request for Additional Information Relief Request CISI-03-01 Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements ML21132A2952021-05-14014 May 2021 Summary of Public Meeting to Discuss Technology Inclusive Content of Application Project ML21124A1232021-05-0404 May 2021 April 27, 2021, Public Meeting Summary Joseph M. Farley Nuclear Plant Units 1 and 2, Edwin I. Hatch Nuclear Plant Units 1 and 2, Docket No. 50-348, 50-364, 50-321, 50-366, Meeting Number ML21117A030 ML21055A8672021-04-22022 April 2021 Memo to File: Final Ea/Fonsi of Independent Spent Fuel Storage Facilities Decommissioning Funding Plans Related to Oconee ML21067A0922021-04-20020 April 2021 Documentation of Decision by NRC Staff That EPRI Report 3002012988, Alternative Approaches for Addressing Seismic Risk in 10 CFR 50.69 Risk-Informed Categorization, Meets Criteria for a Federal Record ML21099A0932021-04-0909 April 2021 Public Meeting Summary - 2020 Annual Assessment Meeting Regarding Catawba, McGuire, and Oconee Nuclear Stations ML20357B1332020-12-30030 December 2020 Transmittal Memo - Delivery of Partial Deliverable Associated with the Trace Code Maintenance, Plant Model Maintenance, and Plant Model Development to Support Licensing Actions and Emergent Technical Issues User Need ML20337A1572020-12-0808 December 2020 Summary of Teleconference Meeting with Entergy Operations, Inc. to Discuss the Forthcoming Supplemental Response Concerning Generic Letter 2004-02 for Arkansas Nuclear One, Units 1 and 2 ML20149K5412020-11-23023 November 2020 Memo to File: Environmental Assessment and Finding of No Significant Impact and NRC Financial Analysis for Entergy Operations, Inc. Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Arkansas Nuclear One I ML20150A4212020-11-23023 November 2020 Memo to File: Environmental Assessment and Finding of No Significant Impact and NRC Financial Analysis for Entergy Nuclear Company, LLC Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Grand Gulf ISFSI ML20212L5772020-11-20020 November 2020 Memo to File: Environmental Assessment-Finding of No Significant Impact and NRC Financial Analysis for Constellation and Exelon Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Calvert Cliffs Nuclear Pow ML20154K7242020-06-0202 June 2020 EOC Meeting Summary ML20141L4172020-05-20020 May 2020 EOC Public Meeting Summary ML20036E3902020-02-11011 February 2020 Regulatory Audit in Support of Review of License Amendment Request to Revise the Licensing Basis for High Energy Line Breaks Outside of the Containment Building ML19298C9722019-10-31031 October 2019 50.69 Apla SE Input L-2018-LLA-0482 ML19204A2972019-07-31031 July 2019 Memo to Management Review Board Arkansas Follow-up FY2019 Proposed Final Report ML19123A3542019-05-0202 May 2019 Public Meeting Summary - Hatch Nuclear Plant, Docket Nos. 50-321 and 50-366 ML19102A3352019-04-12012 April 2019 Public Meeting Summary - Oconee Nuclear Station Docket Nos. 50-269, 50-270, and 50-287 2024-05-08
[Table view] |
Text
October 21, 2003 MEMORANDUM TO: Docket File FROM: Guy S. Vissing, Senior Project Manager, Section 1 /RA/
Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
CALVERT CLIFFS UNIT NOS. 1 AND 2 - PLAN AND SCHEDULE FOR IMPLEMENTATION OF STAFF POSITION ON THE STATION BLACKOUT (SBO) ISSUE (TAC NOS. MB5214 AND MB5215)
In a May 7, 2002, memo, the NRC staff articulated that the offsite power system, used to connect the plant to offsite power source, should be included within the scope of the license renewal rule. The aforementioned memo also informed the Nuclear Energy Institute and the Union of Concerned Scientists that implementation of this staff position should start with the license renewal applications currently under review, and additional guidance would be issued to implement this staff position at Calvert Cliffs, Oconee, ANO-1, and Hatch.
The NRC staff is developing a process for evaluating licensees with renewed licenses for possible backfit of issues such as SBO. Since the interim staff guidance deals with aging management issues associated with the period of extended operation, the NRC staff will ensure the licensees address the issue before entering the period of extended operation. The plan is that when the staff updates the license renewal guidance documents to include the issues such as SBO, the staff will prepare an implementation package along with the recommended schedule. The staff is scheduled to update the license renewal guidance by July 2005.
Since the resolution path of the specific TAC is stretching out for about at least another year, we are closing the current TAC and we will open a new TAC for the future work, when the staff provides the guidance on the issue.
Docket Nos. 50-317 and 50-318
October 21, 2003 MEMORANDUM TO: Docket File FROM: Guy S. Vissing, Senior Project Manager, Section 1 /RA/
Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
CALVERT CLIFFS UNIT NOS. 1 AND 2 - PLAN AND SCHEDULE FOR IMPLEMENTATION OF STAFF POSITION ON THE STATION BLACKOUT (SBO) ISSUE (TAC NOS. MB5214 AND MB5215)
In a May 7, 2002, memo, the NRC staff articulated that the offsite power system, used to connect the plant to offsite power source, should be included within the scope of the license renewal rule. The aforementioned memo also informed the Nuclear Energy Institute and the Union of Concerned Scientists that implementation of this staff position should start with the license renewal applications currently under review, and additional guidance would be issued to implement this staff position at Calvert Cliffs, Oconee, ANO-1, and Hatch.
The NRC staff is developing a process for evaluating licensees with renewed licenses for possible backfit of issues such as SBO. Since the interim staff guidance deals with aging management issues associated with the period of extended operation, the NRC staff will ensure the licensees address the issue before entering the period of extended operation. The plan is that when the staff updates the license renewal guidance documents to include the issues such as SBO, the staff will prepare an implementation package along with the recommended schedule. The staff is scheduled to update the license renewal guidance by July 2005.
Since the resolution path of the specific TAC is stretching out for about at least another year, we are closing the current TAC and we will open a new TAC for the future work, when the staff provides the guidance on the issue.
Docket Nos. 50-317 and 50-318 DISTRIBUTION:
PUBLIC R. Laufer T. Lee S. Little T. Lee G. Vissing E. Marinos ADAMS Accession Number: ML032720527 *See previous concurrence.
OFFICE PDI-1/PM PDI-1/LA IROB-A PDI-1/SC NAME GVissing SLittle PTKuo* RLaufer DATE 10/08/03 10/08/03 10/02/03 10/15/03 OFFICIAL RECORD COPY