May 28, 2002 Mr. Charles H. Cruse Vice President - Nuclear Energy Calvert Cliffs Nuclear Power Plant, Inc.

Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702

SUBJECT:

BULLETIN 2002-01, REACTOR PRESSURE VESSEL HEAD DEGRADATION AND REACTOR COOLANT PRESSURE BOUNDARY INTEGRITY, 15-DAY RESPONSE FOR CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NO. 2 (TAC NO. MB4534)

Dear Mr. Cruse:

On March 18, 2002, the Nuclear Regulatory Commission (NRC) staff issued Bulletin 2002-01, Reactor Pressure Vessel Head Degradation and Reactor Coolant Pressure Boundary Integrity, to the industry requesting that addressees provide information related to the structural integrity of the reactor coolant pressure boundary, including the reactor pressure vessel head, and the extent to which inspections have been undertaken to satisfy applicable regulatory requirements.Bulletin 2002-01 also required licensees to provide the basis for concluding that plans for future inspections of the reactor coolant pressure boundary will satisfy applicable regulatory requirements at their respective pressurized-water reactor plants. All addressees were requested to respond to Items 1.A. through E. within 15 days of the Bulletins issuance, or to provide a written response to the NRC in accordance with the provisions of Title 10, Section 50.54(f), of the Code of Federal Regulations (10 CFR 50.54(f)) if they are unable to provide the information or they cannot meet the requested completion dates.

You provided your 15-day Bulletin response by letter dated April 2, 2002. The staff finds that you have provided the requested information, and has concluded that your plant does not appear to have conditions similar to those which lead to the degradation at Davis-Besse.

However, the staff may issue questions to confirm or verify the information that was provided in your 15-day response to Bulletin 2002-01.

We will complete a full review of your response to Bulletin 2002-01 after we review your response to Items 2 and 3 of the Bulletin.

Sincerely,

/RA/

Donna Skay, Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-318 cc: See next page

Mr. Charles H. Cruse Vice President - Nuclear Energy Calvert Cliffs Nuclear Power Plant, Inc.

Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702

SUBJECT:

BULLETIN 2002-01, REACTOR PRESSURE VESSEL HEAD DEGRADATION AND REACTOR COOLANT PRESSURE BOUNDARY INTEGRITY, 15-DAY RESPONSE FOR CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NO. 2 (TAC NO. MB4534)

Dear Mr. Cruse:

On March 18, 2002, the Nuclear Regulatory Commission (NRC) staff issued Bulletin 2002-01, Reactor Pressure Vessel Head Degradation and Reactor Coolant Pressure Boundary Integrity, to the industry requesting that addressees provide information related to the structural integrity of the reactor coolant pressure boundary, including the reactor pressure vessel head, and the extent to which inspections have been undertaken to satisfy applicable regulatory requirements.Bulletin 2002-01 also required licensees to provide the basis for concluding that plans for future inspections of the reactor coolant pressure boundary will satisfy applicable regulatory requirements at their respective pressurized-water reactor plants. All addressees were requested to respond to Items 1.A. through E. within 15 days of the Bulletins issuance, or to provide a written response to the NRC in accordance with the provisions of Title 10, Section 50.54(f), of the Code of Federal Regulations (10 CFR 50.54(f)) if they are unable to provide the information or they cannot meet the requested completion dates.

You provided your 15-day Bulletin response by letter dated April 2, 2002. The staff finds that you have provided the requested information, and has concluded that your plant does not appear to have conditions similar to those which lead to the degradation at Davis-Besse.

However, the staff may issue questions to confirm or verify the information that was provided in your 15-day response to Bulletin 2002-01.

We will complete a full review of your response to Bulletin 2002-01 after we review your response to Items 2 and 3 of the Bulletin.

Sincerely,

/RA/

Donna Skay, Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-318 cc: See next page DISTRIBUTION:

PUBLIC RLaufer OGC WBateman PDI-1 R/F DSkay ACRS ALee SBloom MEvans, RI SCoffin ACCESSION NO. ML021430246 OFFICE PDI-1/PM PDI-1/LA EMCB PDI-1/SC NAME DSkay SLittle SBloom PTam for RLaufer DATE 5/24/02 5/23/02 5/24/02 5/28/02 OFFICIAL RECORD COPY

Calvert Cliffs Nuclear Power Plant Unit Nos. 1 and 2 cc:

President Kristen A. Burger, Esquire Calvert County Board of Maryland Peoples Counsel Commissioners 6 St. Paul Centre 175 Main Street Suite 2102 Prince Frederick, MD 20678 Baltimore, MD 21202-1631 James Petro, Esquire Patricia T. Birnie, Esquire Counsel Co-Director Constellation Power Source Maryland Safe Energy Coalition 111 Market Street P.O. Box 33111 Baltimore, MD 21202 Baltimore, MD 21218 Jay E. Silberg, Esquire Mr. Loren F. Donatell Shaw, Pittman, Potts, and Trowbridge NRC Technical Training Center 2300 N Street, NW 5700 Brainerd Road Washington, DC 20037 Chattanooga, TN 37411-4017 Mark Geckle Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 287 St. Leonard, MD 20685 Mr. Richard I. McLean, Manager Nuclear Programs Power Plant Research Program Maryland Dept. of Natural Resources Tawes State Office Building, B3 Annapolis, MD 21401 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406