ML041480225

From kanterella
Revision as of 18:27, 24 March 2020 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Restart Status
ML041480225
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 02/19/2004
From:
- No Known Affiliation
To:
Office of Nuclear Reactor Regulation
References
FOIA/PA-2004-0140
Download: ML041480225 (2)


Text

A$7-S - FOR O 1 =

I/

DAVIS-BESSE RESTART STATUS This Information is current as of 5:30 pm (EST) on February 19, 2004. I The plant is in Mode 3 maintaining Normal Operating Pressure/Normal Operating Temperature.

(NOP/NOT - 532 0F/2155 psig). The licensee expects to maintain the plant in these conditions until restart.

The 0350 Panel activities remain focused on restart deliberations. The final SERP was conducted on February 19 for the High Pressure Injection pump Greater than Green issue, with a final significance determination of White. Region III plans to issue the final significance letter and Notice of Violation in the next 2 weeks.

LICENSEE ACTIVITIES PRIOR TO RESTART The licensee Is currently tracking outstanding activities that need to be completed prior to restart [Mode 2/1]. There are approximately 24 restart items. I

  • Corrective Actions: 7 Condition Reports:

Field Work:

7 7

I

  • Surveillance Tests: 1 NRC ACTIVITIES PRIOR TO RESTART Below is a simplified time fine that describes the significant NRC-and licensee activities and milestones that are necessary for NRC to authorize restart.

These tentative dates are predicated upon the licensee successfully completing NRC pre-restart activities and demonstrating acceptable operating performance.

Key Agency decision points are annotated with asterisks (**) In the timeline below.

The outcome of each decision point could materially alter the timing and substance of the rest of the schedule.

The details of these activities are described in three internal NRC documents: the Davis-Besse Oversight Panel Process Plan, the Davis-Besse Restart Communications Plan and the Davis-Besse Restart Punch List.

Panel deliberations on restart decision Panel briefing for Jim Caldwell, Jim Dyer, and Sam Collins on restart deliberations Panel Issues restart recommendation to Jim Caldwell Panel briefing for Commissioners' TAs Jim Caldwell issues draft Order to licensee (for affirmation/hearing

'5 dclznination)

Licensee affirms conditions of Order and declines hearing Finalize restart authorization letter and Order (letter to be signed by Jim Caldwell; will authorize restart and transmit the Order - Ordi Dr to be 'IJ signed by Jim Dyer) ntri,,,.io ini rnit d V^ ENFICIAL USE ONLY A

.t La ;i FOSS -______

SENX EINOMTO-FOOF -USE ONLY Implement Restart Communications Plan (1-day Enforcement ANotification)

Issue restart authorization letter and Order Implement restart inspection plan

[I CHALLENGES THAT THE LICENSEE IS CURRENTLY ADDRESSING None at this time.

LICENSEE ACTIVITIES FOLLOWING RESTART AUTHORIZATION The following sequence of events were taken from a licensee Level 1 schedule.

NRC approval for restart Enter operational Mode 2 (reactor startup)

Reactor critical - Zero power physics testing Enter Mode 1 (greater than 5%power)

Readiness and effectiveness review prior to synch to the grid Synch to the grid Readiness and effectiveness review prior to exceeding 50% power Reactor at 100% power SE N -EFOR FFICIAL USE ONLY