ML050540476

From kanterella
Revision as of 03:38, 24 March 2020 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Portions of Draft Edwin I. Hatch Nuclear Power Plant - NRC Triennial Fire Protection Inspection IR 05000321-03-006 and 05000366-03-006
ML050540476
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 10/31/2003
From:
NRC/RGN-II
To:
References
FOIA/PA-2004-0277, IR-03-006
Download: ML050540476 (10)


See also: IR 05000321/2003006

Text

2

SUMMARY OF FINDINGS

IR 05000321/2003-006, 05000366/2003-006; Southern Nuclear Operating Company;

7/7-11/2003 and 7/21-25/2003; E. l. Hatch Nuclear Plant, Units 1 and 2; Triennial Fire

Protection

The report covered a two-week period of inspection by three regional inspectors and a

contractor from Brookhaven National Laboratory. Three Green non-cited violations (NCVs) and

four unresolved items with potential safety significance greater than Green were identified. The

significance of most findings is indicated by their color (Green, White, Yellow, Red) using IMC 0609, "Significance Determination Process" (SDP). Findings for which the SDP does not apply

may be Green or be assigned a severity level after NRC management review. The NRC's

program for overseeing the safe operation of commercial nuclear power reactors is described in

NUREG-1 649, "Reactor Oversight Process," Revision 3, dated July 2000.

A. NRC-Identified and Self-Revealing Findings

Cornerstone: Mitigating Systems

prevent spurious opening of all eleven safety relief valves (SRVs) during a fire event,

would not be performed in sufficient time to be effective. Also, licensee reliance on this

manual action for hot shutdown during a fire, instead of physically protecting cables from

fire damage, had not been approved by the NRC.

This finding is unresolved pending completion of a significance determination. In

response to this potential issue, the licensee promptly moved the manual action step to

the front of the Fire Procedure to enable operators to accomplish the action much

sooner during a fire event. This finding was determined to have potential safety

significance greater than very low significance because of the use of manual actions in

lieu of physical protection as required by 10 CFR 50 Appendix R, Section III.G.2.

(Section 1R05.05.b.1)

URI. The team identified an unresolved item in that a fire in Fire Area 2104 could

cause all eleven SRVs to open at a time when residual heat removal (RHR) system

may not be available. To mitigate this event, the licensee's safe shutdown analysis

report (SSAR) credits the use of Core Spray Loop A to provide reactor coolant makeup.

However, the licensee did not provide any objective evidence (e.g., specific calculation

or analysis) which demonstrated that, assuming worst-case fire damage in Fire Area

2104, the limited set of equipment available would be capable of mitigating the event in

a manner that satisfies the shutdown performance goals specified in Appendix R,

section L.1.e to 10CFR 50.

This finding is unresolved pending completion of the NRC review of a calculation of

record which demonstrates the capability of the Core Spray system to mitigate the

above event. This finding was determined to have potential safety significance greater

than very low significance because of a lack of a calculation of record and

3

documentation of the limited set of equipment that would be credited for safe shutdown

under these conditions. (Section 1R.05.03.b)

URI: The team identified an unresolved item in connection with the implementation of

design change request (DCR)91-134, SRV Backup Actuation via Pressure Transmitter

Signals. The installed plant modification failed to implement the one-out-of-two taken

twice logic that was specified as design input requirements in the design change

package. Additionally, implementation of a two-out-of-two coincident taken twice logic,

has introduced a potential common cause failure of all eleven SRVs because of fire

induced damage to two instrumentation circuit cables in close proximity to each other.

This finding is unresolved pending completion of a significance determination. This

finding is greater than minor because it impacts the mitigating system cornerstone. This

finding has the potential for defeating manual control of Group "A" SRVs that are

required for ensuring that the suppression pool temperature will not exceed the heat

capacity temperature limit (HCTL) for the suppression pool. (Section 1R21.01)

  • Green. The team identified a finding with very low safety significance in that a local

manual operator action to operate safe shutdown equipment was too difficult and was

also unsafe. The licensee had relied on this action instead of providing physical

protection of cables from fire damage or preplanning cold shutdown repairs. However,

the team judged that some operators would not be able to perform the action.

This finding involved a violation of 10 CFR 50, Appendix R, Section III.G.1 and

Technical Specification 5.4.1. The finding is greater than minor because it affected the

availability and reliability objectives and the equipment performance attribute of the

mitigating systems cornerstone. Since the licensee could have time to develop and

implement cold shutdown repairs to facilitate accomplishment of the action, this finding

did not have potential safety significance greater than very low safety significance.

(Section 1R05.05.b.2)

  • Green. The team identified a finding with very low safety significance in that the

licensee relied on some manual operator actions to operate safe shutdown equipment,

instead of providing the required physical protection of cables from fire damage, and

without NRC approval.

This finding involved a violation of 10 CFR 50, Appendix R, Section III.G.2. The finding

is greater than minor because it affected the availability and reliability objectives and the

equipment performance attribute of the mitigating systems cornerstone. Since the

actions could reasonably be accomplished by operators in a timely manner, this finding

did not have potential safety significance greater than very low safety significance.

(Section 1R05.05.b.3)

  • Green. The team identified a finding with very low safety significance in that emergency

lighting was not adequate for some manual operator actions that were needed to

support post-fire operation of safe shutdown equipment.

4

This finding involved a violation of 10 CFR 50, Appendix R, Section III.J. The finding is

greater than minor because it affected the reliability objective and the equipment

performance attribute of the mitigating systems cornerstone. Since operators would be

able to accomplish the actions with the use of flashlights, this finding did not have

potential safety significance greater than very low safety significance. (Section

1R05.07.b)

B. Licensee-Identified Violations

None

REPORT DETAILS

1. REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems and Barrier Integrity

11R05 FIRE PROTECTION

The purpose of this inspection was to review the Hatch Nuclear Plant fire protection program

(FPP) for selected risk-significant fire areas. Emphasis was placed on verification that the post-

fire safe shutdown (SSD) capability and the fire protection features provided for ensuring that at

least one redundant train of safe shutdown systems is maintained free of fire damage. The

inspection was performed in accordance with the Nuclear Regulatory Commission (NRC)

Reactor Oversight Program using a risk-informed approach for selecting the fire areas and

attributes to be inspected. The team used the licensee's Individual Plant Examination for

External Events and in-plant tours to choose four risk-significant fire areas for detailed

inspection and review. The fire areas chosen for review during this inspection were:

_. Fire Area 2016, West 600 V Switchgear Room, Control Building, Elevation 130 feet.

Fire Area 2104, East Cableway, Turbine Building, Elevation 130 feet.

Fire Area 2404, Switchgear Room 2E, Diesel Generator Building, Elevation 130 feet.

Fire Area 2408, Switchgear Room 2F, Diesel Generator Building, Elevation 130 feet.

The team evaluated the licensee's FPP against applicable requirements, including Operating

License Condition 2.D, Fire Protection; Title 10 of the Code of Federal Regulations, Part 50 (10

CFR 50), Appendix R; 10 CFR 50.48; Appendix A of Branch Technical Position (BTP) Auxiliary

and Power Conversion Systems Branch (APCSB) 9.5-1; related NRC Safety Evaluation

Reports (SERs); the Hatch Nuclear Plant Updated Final Safety Analysis Report (UFSAR); and

plant Technical Specifications (TS). The team evaluated all areas of this inspection, as

documented below, against these requirements.

Documents reviewed by the team are listed In the attachment.

VOW Systems Required to Achieve and Maintain Post-Fire Safe Shutdown

a. Inspection Scope

The licensee's Safe Shutdown Analysis Report (SSAR) was reviewed to determine the

components and systems necessary to achieve and maintain safe shutdown conditions

in the event of fire in each of the selected fire areas. The objectives of this evaluation

were as follows:

(a) Verify that the licensee's shutdown methodology has correctly identified

the components and systems necessary to achieve and maintain a safe

shutdown condition.

2

(b) Confirm the adequacy of the systems selected for reactivity control,

reactor coolant makeup, reactor heat removal, process monitoring and

support system functions.

(c) Verify that a safe shutdown can be achieved and maintained without off-

site power, when it can be confirmed that a postulated fire in any of the

selected fire areas could cause the loss of off-site power.

(d) Verify that local manual operator actions are consistent with the plant's

fire protection licensing basis.

b. Findings P

The team identified a potential concern whefe4he licensee used manual actions to

disconnect terminal board sliding links in order to isolate two 4-20 Ma instrumentation

control loop circuits in order to prevent the spurious actuation of eleven SRVs. This

issue is discussed in section 1R05.03.b of the report.

.02 Fire Protection of Safe Shutdown Capabilitv

a. Inspection Scope

For the selected fire areas, the team evaluated the frequency of fires or the potential for

fires, the combustible fire load characteristics and potential fire severity, the separation

of systems necessary to achieve safe shutdown (SSD), and the separation of electrical

components and circuits located within the same fire area to ensure that at least one

SSD path was free of fire damage. The team also inspected the fire protection features

to confirm they were installed in accordance with the codes of record to satisfy the

applicable separation and design requirements of 10 CFR 50, Appendix R, Section 1Il.G,

and Appendix A of BTP APCSB 9.5-1. The team reviewed the following documents,

which established the controls and practices to prevent fires and to control combustible

fire loads and ignition sources, to verify that the objectives established by the

NRC-approved fire protection program (FPP) were satisfied:

Plan

  • Administrative Procedure 42FP-FPX-01 8-OS, Use, Control, and Storage of

Flammable/Combustible Materials

  • Preventive Maintenance Procedure 52PM-MEL-01 2-0, Low Voltage Switchgear

Preventive Maintenance

The team toured the selected plant fire areas to observe whether the licensee had

properly evaluated in-situ fire loads and limited transient fire hazards in a manner

consistent with the fire prevention and combustible hazards control procedures. In

addition, the team reviewed the licensee's fire safety inspection reports and corrective

action program (CAP) condition reports (CRs) resulting from fire, smoke, sparks, arcing,

and overheating incidents for the years 2000-2002 to assess the effectiveness of the fire

prevention program and to identify any maintenance or material condition problems

related to fire incidents.

3

The team reviewed fire brigade response, fire brigade qualification training, and drill

program procedures; fire brigade drill critiques; and drill records for the operating shifts

from January 1999 - December 2002. The reviews were performed to determine

whether fire brigade drills had been conducted in high fire risk plant areas and whether

fire brigade personnel qualifications, drill response, and performance met the

requirements of the licensee's approved FPP.

The team walked down the fire brigade equipment storage areas and dress-out locker

areas in the fire equipment building and the turbine building to assess the condition of

fire fighting and smoke control equipment. Fire brigade personal protective equipment

located at both of the fire brigade dress-out areas and fire fighting equipment storage

area in the turbine building were reviewed to evaluate equipment accessibility and

functionality. Additionally, the team observed whether emergency exit lighting was

provided for personnel evacuation pathways to the outside exits as identified in the

National Fire Protection Association (NFPA) 101, Life Safety Code, and the

Occupational Safety and Health Administration (OSHA) Part 1910, Occupational Safety

and Health Standards. This review also included examination of whether backup

emergency lighting was provided for access pathways to and within the fire brigade

equipment storage areas and dress-out locker areas in support of fire brigade

operations should power fail during a fire emergency. The fire brigade self-contained

breathing apparatuses (SCBAs) were reviewed for adequacy as well as the availability

of supplemental breathing air tanks and their refill capability.

The team reviewed fire fighting pre-fire plans for the selected areas to determine if

appropriate information was provided to fire brigade members and plant operators to

facilitate suppression of a fire that could impact SSD. Team members also walked down

the selected fire areas to compare the associated pre-fire plans and drawings with as-

built plant conditions. This was done to verify that fire fighting pre-fire plans and

drawings were consistent with the fire protection features and potential fire conditions

described in the Fire Hazards Analysis (FHA).

The team reviewed the adequacy of the design, installation, and operation of the manual

suppression standpipe and fire hose system for the control building. This was

accomplished by reviewing the FHA, pre-f ire plans and drawings, engineering

mechanical equipment drawings, design flow and pressure calculations and NFPA 14

for hose station location, water flow requirements and effective reach capability. Team

members also walked down the selected fire areas in the control building to ensure that

hose stations were not blocked and to verify that the required fire hose lengths to reach

the safe shutdown equipment in each of the selected areas were available. Additionally,

the team observed placement of the fire hoses and extinguishers to assess consistency

with the fire fighting pre-fire plans and drawings.

b. Findings

No findings of significance were identified.

4

.03 Post-Fire Safe Shutdown Capability

a Inspection Scope

10 CFR 50.48, "Fire Protection," and Appendix R to 10 CFR 50, "Fire Protection

Program for Nuclear Power Facilities Operating Prior to January 1, 1979" establish

specific fire protection features required to satisfy General Design Criterion 3, "Fire

Protection" (GDC 3, Appendix A to 10 CFR 50). Section lll.G of Appendix R requires

fire protection features be provided for equipment important to safe shutdown. An

acceptable level of fire protection may be achieved by various combinations of fire

protection features (barriers, fire suppression systems, fire detectors, and spatial

separation of safety trains) delineated in Section III.G.2. For areas of the plant where

compliance with the technical requirements of Section III.G.2 can not be achieved,

licensees must either seek an exemption from the specific requirement(s) or provide an

alternative shutdown capability in accordance with Sections III.G.3 and 1ll.L of the

regulation.

For each selected fire area, the results of the licensee's analysis for compliance with

Section IIl.G of Appendix R is documented in a SSAR . The overall approach of these

evaluations was to determine the fire-induced losses for a fire in each fire area and then

assess the plant impact given those loses.

On a sample basis, an evaluation was performed to verify that systems and equipment

identified in the licensee's SSAR as being required to achieve and maintain hot

shutdown conditions would remain free of fire damage in the event of fire in the selected

fire areas. The evaluation included a review of cable routing data depicting the location

of power and control cables associated with SSD Path 1 and Path 2 components of the

RCIC and HPCI systems. Additionally, on a sample basis, the team reviewed the

licensee's analysis of electrical protective device (e.g., circuit breaker, fuse, relay)

coordination.

b Findings

Capability of Equipment Credited in SSAR to Mitigate the Spurious Actuation of Eleven

SRVs

Introduction: The team identified a potential concern where the licensee used manual

actions to disconnect terminal board sliding links in order to isolate two 4 to 20 ma

instrumentation control loop circuits In order to prevent the spurious actuation of eleven

SRVs. The disconnection of terminal board sliding links is considered a repair and was

not consistent with the plants licensing basis for achieving and maintaining safe

shutdown conditions. Additionally, the use of manual actions in lieu of providing

protection for the instrumentation loop control circuits was not in compliance with the

requirements of 10 CFR 50 Appendix R. section III.G.2.

Description: The SSAR states that a fire in Fire Area 2104 could cause all eleven SRVs

to spuriously actuate as a result of fire damage to two cables that are located in close

proximity in this area. The specific circuits that could cause this event have been

identified by the licensee (circuit nos.: ABE019CO8 and ABE019CO9). Each of these

two circuits provides a 4 to 20 milliamp instrumentation signal from SRV high-pressure

actuation transmitters (2B21-N127B and 2B21-N127D) to master trip units 2B21-N697B

and 2B21 -N697D, respectively. The purpose of this circuitry is to provide an electrical

backup to the mechanical trip capability of the individual SRVs. In the event of high

reactor pressure, the circuits would provide a signal to the trip units which would cause

all eleven SRVs to actuate (open). The pressure signal from each transmitter is.

conveyed to its respective trip unit via a two-conductor, instrument cable that is routed

through .thisfire area (two separate cables). Each cable consists of a single twisted pair

of insulated conductors, an uninsulated drain wire that is wound around the twisted pair

of conductors, and a foil shield. In Fire Area 2104 the two cables are located in close

proximity, in the same cable tray. Actuation of the SRV electrical backup is completely

ublind" to the operators. Unlike ADS, it does not provide any pre-actuation indication

(e.g., actuation of the ADS timer) or an inhibit capability (e.g., ADS inhibit switch). Since

the operators typically would not initiate a manual scram until fire damage significantly

interfered with control of the plant, its possible that all eleven SRVs could open at 100%

power, prior to scramming the reactor. This scenario could place the plant in an

unanalyzed condition.

Unlike a typical control circuit, a direct short or "hot short" between conductors of a 4 to

20 milliamp instrument circuit may not be necessary to initiate an undesired (false high)

signal. For cables that transmit low-level instrument signals, any degradation of the

insulation of the individual twisted conductors due to fire damage may be sufficient to

cause leakage currents to be generated between the two conductors. Such leakage

current would appear as a false high pressure signal to the trip units. If both cables

were damaged as a result of fire, false signals generated as a result of leakage current

in each cable, would actuate the SRV electrical backup scheme which would cause all

eleven of the SRVs to open. The conductor insulation and jacket material of each cable

is cross-linked polyethylene (XLPE). Since both cables are in the same tray and

exposed to the same heating rate, there is a reasonable likelihood that both

instrumentation cables would suffer insulation damage at the same time and both

circuits could fail high simultaneously.

The licensee's SSAR recognizes the potential safety significance of this event and

describes methods that have been developed to prevent its occurrence and/or mitigate

its impact on the plant's post-fire safe shutdown capability should it occur. To prevent

this scenario, the licensee has developed procedural guidance which directs operators

to open link BB-10 in panel 2H11-P927 and link BB-10 in panel 2H11-P928. Opening of

these links would prevent actuation of the SRV trip units by removing the 4 to 20

milliamp signal fed by the pressure transmitters. In the event the SRVs were to open

prior to operators completing this action, the SSAR credits Core Spray loop A to mitigate

the event. However, the inspection team had several concerns regarding the

effectiveness of the licensee's approach. Specific concerns identified by the team

included:

1. The timing of operator actions necessary to prevent the event (the time

from fire detection to the time the two links would be opened);

6

2. Whether the operator actions (opening of links) were consistent with the

plants current fire protection licensing basis with respect to repairs

needed to achieve and maintain hot shutdown conditions.

3. The capability of the limited set of systems and equipment credited in the

SSAR for accomplishing post-fire safe shutdown conditions in the event

of fire in Fire Area 2104 to mitigate the event in a manner that satisfies

the shutdown performance goals specified in Appendix R to 10 CFR 50.

4 The inability of the operations staff to manually control the group A SRVs

that are credited for mitigating a fire in fire area 2104 because of spurious

actuation.

With regard to the timing of operator actions to prevent fire damage from causing all

SRVs to open, during the inspection the licensee performed an evaluation which

estimated that approximately thirty minutes would pass from the time of fire detection to

the time an operator would implement procedural actions to prevent its occurrence

(opening of links). The licensee concurred with the inspection team's concern that this

time (30 minutes) may be too long to provide an effective means of preventing the

actuation. To improve the effectiveness of this action the licensee agreed to enhance

its existing procedures so that the action would be taken immediately following

confirmation of fire in areas where the spurious actuation could occur.

The team considered the operators action of opening terminal board links to be not in

agreement with the plants licensing basis. Current licensing basis documents

(Reference: Georgia Power request for exemption dated May 16, 1986 and a

subsequent Safety Evaluation Report (SER) dated January 2, 1987) characterized the

opening of links as a repair activity that is not permitted as a means of complying with

Section III.G of Appendix R. Based on these documents the opening of links was

considered a repair by both the licensee and the NRC staff in 1987. The licensee could

not provide any evidence to justify why these actions are not characterized as a repair

activity in its current SSAR. In response to this inspection finding, the licensee initiated

a Condition Report (CR 2003800152, dated 7/24/03) to evaluate actions to open links, in

order to determine if they are necessary to achieve hot shutdown, and if an exemption

from Appendix R is required.

Because there is a potential for all SRVs to spuriously actuate as a result of fire in Fire

Area 2104 at a time when RHR is not available, the SSAR credits the use of Core Spray

Loop A to accomplish the reactor coolant makeup function. During the inspection, on

7/24/03, the licensee voluntarily performed a simulator exercise of an event which

caused all 11 SRVs to open. During this exercise, simulator RPV level instruments

indicated that Core Spray would be capable of maintaining level above the top of active

fuel. However, the licensee did not provide any objective evidence (e.g., specific

calculation or analysis) which demonstrated that, assuming worst-case fire damage in

Fire Area 2104, the limited set of equipment available would be capable of mitigating

the event in a manner that satisfies the shutdown performance goals specified in

Appendix R, section L.1 .e to 1OCFR 50.

_ r

7

The licensee's failure to implement the design input requirements of one-out-of-two

taken twice logic for DCR 91-134 resulted in the following problem. The logic installed

for the SRVs was a two-out-of-two coincident taken twice logic in addition to a one-out-

of-two coincident taken twice logic. The team determined that the two-out-of-two

coincident logic input from trip unit master relays K31OD and K335D represented a

common cause failure for both group "A"SRVs for a fire in fire area 2104. Specifically,

cable ABE01 9C08 associated with pressure transmitter 2B21-N127B current loop, and

cable ABE019CO9 associated with pressure transmitter 2B21-N127D current loop, are

both routed in the same cable tray in fire area 2104. Both shielded twisted pair

instrument cables are unprotected from the effects of a fire in this fire area. Fire

-induced insulation damage to both cables could result in leakage currents which causes

the instrument loops to fail high. This failure mode simulates a high nuclear boiler

pressure condition which would initiate SRV backup actuation of group "A"SRV 2B21-

F013F and 2B21-FO13G. Spurious actuation of both SRVs for a fire in fire area 2104

defeats the capability to manually control these SRVs as is required per the SSAR.

Analysis: This finding is greater than minor because it affected the availability and

reliability objectives and the equipment performance attribute of the mitigating systems

cornerstone. In order to achieve safe shutdown conditions for a fire in any of the fire

areas chosen for review, manual control of two SRVs is required. For Path 1 group "A

SRVs 2B21-FO13B and 2B21-FO13F are required to remain manually operable.

Additionally, for Path 2 group "A"SRVs 2B21-F013D and 2B21-F013G are required to

remain manually operable. These actions are necessary to ensure that the suppression

pool temperature will not exceed the heat capacity temperature limit (HCTL) for the

suppression pool. One SRV ( per Path) is opened to manually control depressurization

approximately two and a half hours after event initiation in order to maintain the

suppression pool below the HCTL. The second SRV is opened approximately four

hours to allow use of the alternate shutdown cooling mode of operation.

Enforcement: 10 CFR 50 Appendix R,section L.1.e states that during the post fire

shutdown, the reactor coolant system process variables shall be maintained within

those predicted for a loss of normal AC power. This finding was determined to have

potential safety significance greater than very low significance because of a lack of a'

calculation of record and documentation of the limited set of equipment that would be

credited for safe shutdown under these conditions. Pending completion of the NRC

review of a calculation of record which demonstrates the capability of the Core Spray

system to mitigate spurious actuation of eleven SRVs, this issue is identified as URI 50-

366/2003006-01, Capability of Equipment Credited in SSAR to Mitigate the Spurious

Actuation of Eleven SRVs.

04/05 Operational Implementation of Alternative Shutdown Capability

a. Inspection Scope

The selected fire areas that were the focus of this inspection all involved reactor

shutdown from the control room. None involved abandoning the control room and

alternative safe shutdown from outside of the control room. However, the licensee's