ML050540511
| ML050540511 | |
| Person / Time | |
|---|---|
| Site: | Hatch |
| Issue date: | 08/31/2003 |
| From: | NRC/RGN-II |
| To: | |
| References | |
| FOIA/PA-2004-0277, IR-03-006 | |
| Download: ML050540511 (39) | |
See also: IR 05000321/2003006
Text
SUMMARY OF FINDINGS
IR 0500032112eeSee 05000366/20e~e6-.
7/7-11/2003 and 7/21-25/2003;
Hac
ula lnUisIad TinilFire
Protection
The report covered a two-week period of inspection by three regional inspectors anda
-contractor from Brookhaven National Laboratory. Three Green non-cited violations (NCVs) and
Q~c 4hiree unresolved items with potential safety significance greater than Green were identified.
The significance of most findings is indicated by their color (Green, White, Yellow, Red) using
IMC 0609, "Significance Determination Process" (SDP). Findings for which the SDP does not
apply
may
be
Green
or
be
assigned
a
severity
level
after
NRC
management
review.
The
NRC's program for overseeing the safe operation of commercial nuclear power reactors is*
described in NUREG-1 649, "Reactor Oversight Process," Revision 3, dated July 2000.
A.
NRC-Identified and Self-Revealing Findings
Cornerstone: Mitigatin. Systems
URI. The team identified an unresolved item in that a local manual operator action, to
prevent spurious opening of all eleven safety relief valves (SRVs) during a fire event,
would not be performed in sufficient time to be effective. Also, licensee reliance on this
manual action for hot shutdown during a fire, instead of physically protecting cables from
fire damage, had not been approved by the NRC.
This finding is unresolved pending completion of a significance determination.-+-
.
r~esponse o-this-ee
tial
he iene
pr~tly moved the manuai action
sto
---
the front of the Fire Procedtrt -
dtle upelui to accompish l11e c
liui m
oone- rnga-reeven!.
e
risiwas-deternd lo lave -
utentl
- d
,
sknix, fcarncd greater than very lower sinnifi
u because or the uise of manuh mtionna In
Jieucphysical quocio
Js
-eqC
Appenoix K, Secmtmlll.G.2.-
(Section 1R05.K$b.1) O
Tyendn
~
Vi pe
ing
fCl rciwoie
~luo~-f
recoghW44de~nsfates-t
t-ef.he- Gore-&prey-systemn to iiat h
-
7*- ;
II
,C4=
ee
tll:-l
0
-le-o
,
, 0
A/S-1
I
eer"
./
0
i
1
V4
V04
. ,
. ,
t4l',
j. 4
L'olV
rlo
Jeff
p 114
-L
lllc-
6,51,
r4 VV
5
m
. ra-x4
p
-7
/-~ tz:
rl
74
'l-
-5i
1 Es
Q.
o
-.
os b. /
~ l ~
e 7
A
( S EtCAVI&
+a!F
70
.3
... 'I7...
_
7
0
-
Co*
,e
r4".117
It-
/' '
4,
' -2-laV eo-3,c -
D-e
tooo,
record
/Ied~L XL--
I'v
z
Talnt .k
/740
4f -
ir
C
p.I-I,
/.,Cie.,0 p
Il
A4
Ik$~ e
/~/- *:
'
5/
sp
-
w
r-
lack
-*I-,S
-:F-
s"--eag
.Y
SC
-7I a'
yvm
'a! s!ecs
Ale o
FIA-
LI.'
7/
go7
-
"
W
.a 00,=
7v~ &6
s4t~
1-9
(f,.
-j C 7 eole
41,
~46.
j
4,--
4t"p
fv-
TentThisfindng ;
d~er
tototnidi
aety significance greater-
-than vcr; low cign
nbec
teint
ofrcod n:
docurrren
rnhat-weutd4be-cr
edit:
(u
f shutdo
ec~ecion 1R.05. 3.b)
URI: The team identified an unresolved item in connection with the implementation of
design change request (DCR)91-134, SRV Backup Actuation via Pressure Transmitter
Signals. The installed plant modification failed to implement the one-out-of-two taken
twice logic that was specified as design input requirements in the design change'.
package. Additionally, implementation of a two-out-of-two coincident taken twice logic,.
has introduced a potential common cause failure of all eleven SRVs because of fire
induced damage to two instrumentation circuit cables in close proximity to each other.
This finding is unresolved pending completion of a significance determination. This-
finding is greater than minor because it impacts the mitigating system cornerstone. This
finding has the potential for defeating manual control of Group WAW
SRVs that are
required for ensuring that the suppression pool temperature will not exceed the heat
capacity temperature limit (HCTL) for the suppression pool. (Section 1 R21.01 .b)
Green. The team identified a finding with very low safety significance in that a local
manual operator action to operate safe shutdown equipment was too difficult and was
also unsafe. The licensee had relied on this action instead of providing.physical
protection of cables from fire damage or preplanning cold shutdown repairs. However;
the team judged that some operators would not be able to perform the action.
This finding involved a violation of 10 CFR 50, Appendix R, Section IL.G.1 and
Technical Specification 5.4.1. The finding is greater than minor because it affected the
availability and reliability objectives and the equipment performance attribute of the
mitigating systems cornerstone. Since the licensee could have time to develop and
implement cold shutdown repairs to facilitate accomplishment of the action, this finding
did not have potential safety signift
ce
eater than very low safety significance.
'Section IRO
5
Green. The team identified a n g with very low safety significance in that the
licensee relied on some manual operator actions to operate safe shutdown equipment,
instead of providing the required physical protection of cables from fire damage, and
without NRC approval.
This finding involved a violation of 10 CFR 50, Appendix R, Section III.G.2. The finding
is greater than minor because it affected the availability and reliability objectives and the
equipment performance attribute of the mitigating systems cornerstone. Since the
actions could reasonably be accompli hed by operators in a timely manner, this finding
did not have potential safety significa ce greater than very low safety significance.
(Section 1 RO 05.b.3)
.
..i
- '
' .
.
.
-*
Green. The team identified a finding with very low safety significance in that emergency
lighting was not adequate for some manual operator actions that were needed to
support post-fire operation of safe shutdown equipment.
This finding involved a violation of 10 CFR 50, Appendix R, Section III.J. The finding is
greater than minor because it affected the reliability objective and the equipment
performance attribute of the mitigating systems cornerstone. Since operators would be
able to accomplish the actions with the use of flashlights, this finding did not have
-
potential safety significance greater than very low safety significance. (Section
1 R05.07.b)
B.
Licensee-Identified Violations
None
- -~
U. S. NUCLEAR REGULATORY COMMISSION
REGION II
Docket Nos.:
License Nos.:
Report No.:
50-321, 50-366
05000321/2003006 and 05000366/2003006
Licensee:
Facility:
Southern Nuclear Operating Company
E. l. Hatch Nuclear Plant
Location:
Dates: -
.
Inspectors:
Accompanying
Personnel:
Approved by:
P. o. Box 2010 -
Baxley, GA. 31513
July 7-11, 2003 (Week 1)
July 21-25, 2003 (Week 2)
C. Smith, P E., Senior Reactor Inspector, (Lead Inspector)
R. Schin, Senior Reactor Inspector
G. Wiseman, Fire Protection Inspector
K. Suliivan, Consultant, Brooknaven National Laburaiury
S. Belcher, Nuclear Safety Intern, Week I
Charles R. Ogle, Chief
Engineering Branch I
Division of Reactor Safety
Enclosure
4% :91
-
I
CONTENTS
SUMMARY OF FINDINGS ...................
- ._
REPORT DETAILS ...............
REACTOR SAFETY
FIRE PROTECTION
Systems Required to Achieve and Maintain Safe Shutdown .......................................
Fire Protection of Safe Shutdown Capability ...............................
- ........ .
Post-Fire Safe Shutdown Capability ................................ ;
Operational Implementation of Alternative Shutdown Capability..........
Communications.........................................................................................................
Emergency Lighting .............
..
Cold Shutdown Repairs...........................................................................................
Fire Barriers and Fire Area/Zone/Room Penetration Seals ....... ;;
Fire Protection Systems, Features, and Equipment .
SAFETY SYSTEM DESIGN AND PERFORMANCE CAPABILITY
DCR 91-134, SRV Backup Actuation via Pressure Transmitter Signals
.
..............
OTHER ACTIVITIES
Identification and Resolution of Problems.....................................................................
Meetings Including Exit ..................................
Supplemental Information ..................................
List of Items Opened, Closed, and Discussed ................................. ;
List of Documents Reviewed.........................................................................................
I
V
I
1.
IR
REPORT DETAILS
REACTOR SAFETY
Cornerstones: Initiating Events, mitigating Systems and Barrier Integrity
05 FIRE PROTECTION
The purpose of this inspecti
was to review the Hatch Nuclear Plant fire protection
program (FPP) for select
risk-significant fire areas. Emphasis was placed on
verification that the po fire safe shutdown (SSD) capability and the fire protection
features provided for nsuring that at least one redundant train of safe shutdown
systems is maintaied free of fire damage. The inspection was performed in
accordance with) e Nuclear Regulatory Commission (NRC) Reactor Oversight Program
using a risk-infgmed approach for selecting the fire areas and attributes to be
inspected. T1Je team used the licensee's Individual Plant Examination for External
Events and flplant tours to choose four risk-significant fire areas for detailed inspection
and review. The fire areas chosen for review during this inspection were-
- \\
Fire Area 2016, West 600 V Switchgear Room, Control Building, Elev
~j~/
feet.
Fire Area 2104, East Cableway, Turbine Building, Elevation 130 feet.
Fire Area 2404, Switchgear Room 2E, Diesel Generator Building, Ele,
feet.
.
/
Fire Area 2408, Switchgear Room 2F, Diesel Generator Building, Ele,
feet.
L6-
'ation 130
vation 130
vation 130
The team evaluated the licensee's FPP 4 *inst applicable requirements, including
Operating License Condition 2.C.(3)(a), Fire Protection; Title 10 of the Code of Federal
Regulations, Part 50 (10 CFR 50), Appendix R; 10 CGFR 50.48; Appendix A of Branch
Technical Position (BTP) Auxiliary and Power Conversion Systems Branch (APCSB)
9.5-1; related NRC Safety Evaluation Reports (SERs); the Hatch Nuclear Plant Updated
Final Safety Analysis Report (HNP-FSAR); and plant Technical Specifications (TS). The
team evaluated all areas of this inspection, as documented below, against these
requirements.
a.
Documents reviewed by the team are~i
d in the attachment
Systems Required to Achieve and Post-Fire Safe Shutdovn
Insoection Scope
The licensee's Safe Shutdown Analysis Report (SSAR) was reviewed to determine the
components and systems necessary to achieve and maintain safe shutdown conditions
2
in the event of fire in each of the selected fire areas. The.objectives of this evaluation..
were as follows:
(a)
Verify that the licensee's shutdown methodology has correctly identified
.\\
(a -
the components and systems necessary to achieve and maintain a safe
(b
/2shutdown
condition.
Ia
(b)
Confirm the adequacy of the systems selected for reactivity control,
.
- e~ ;reactor
coolant makeup, reactor heat removal, process monitoring and
z~~g
~' x
' support system functions.
..
.;
(c)
Verify that a safe shutdown can be achieved and maintained without off-'
d -site
power, when it can be confirmed that a postulated fire in any of the
selected fire areas could cause the loss of off-site power.
-
(d)
Verify that local manual operator actions are consistent with the plant's
fire protection licensing basis.
t
Findings '-'-
- ;
The team identified a potential concern in that the licensee used manual actions to
disconnect terminal board sliding links in order to isolate two 4-20 milli-amp (ma)
instrumentation loop control circuits in order to prevent the spurious actuation of eleven
SRVs. This issue is discussed in section 1R05.03.b of the report.
.02
Fire Protection of Safe Shutdown Capability
Inspection Scone
For the selected fire areas, the team evaluated the frequency of fires or the potential for
fires, the combustible fire load characteristics and potential fire severity, the separation'
of systems necessary to achieve safe shutdown (SSD), and the separation of electrical.
components and circuits located within the same fire area to ensure that at least one
SSSD path was free of fire damange. The team a!so inspected the ftea protecticn features
to confirm they were installed in accordance with the codes of-record to'satisfy the
applicable separation and design requirements of 10 CFR 50, Appendix R, Section III.G,
and Appendix A of BTP APCSB 9.5-1. The team reviewed the following documents,
which established the controls and practices to prevent fires and to control combustible
fire loads and ignition sources, to verify that the objectives established by the
NRC-approved fire protection program (FPP) were satisfied:
Updated Final Safety Analysis Report (UFSAR) Section 9.1-A, Fire Protection
Plan
Administrative Procedure 40AC-ENG-008-OS, Fire Protection Program
Administrative Procedure 42FP-FPX-01 8-OS, Use, Control, and Storage of
Flammable/Combustible Materials
Preventive Maintenance Procedure 52PM-MEL-012-0, Low Voltage Switchgear
Preventive Maintenance
3
The team toured the selected plant fire areas to observe whether the licensee had
properly evaluated in-situ fire loads and limited transient fire hazards in a manner
consistent with the fire prevention and combustible hazards control procedures. In
addition, the team reviewed the licensee's fire safety inspection reports and corrective
action program (CAP) condition reports (CRs) resulting from fire, smoke, sparks, arcing,
and overheating incidents for the years 2000-2002 to assess the effectiveness of the fire
prevention program and to identify any maintenance or material condition problems
related to fire incidents.
The team reviewed fire brigade response, fire brigade qualification training, and drill
program procedures; fire brigade drill critiques; and drill records for the operating shifts
- from January 1999 - December 2002. The reviews were performed to determine
whether fire brigade drills had been conducted in high fire risk plant areas and whether
- fire brigade personnel qualifications, drill response, and performance met the
requirements of the licensee's approved FPP.
The team walked down the fire brigade equipment storage areas and dress-out locker
areas in the fire equipment building and the turbine building to assess the condition of
fire fighting and smoke control equipment. Fire brigade personal protective'equipment
located at both of the fire brigade dress-out areas and fire fighting equipment storage
area in the turbine building were reviewed to evaluate equipment accessibility and
functionality. Additionally, the team observed whether emergency exit lighting was
provided for personnel evacuation pathways to the outside exits as identified in the
National Fire Protection Association (NFPA) 101, Life Safety Code, and the
Occupational Safety and Health Administration (OSHA) Part 1910, Occupational Safety.
and Health Standards. This review also included examination of whether backup*
emergency lighting was provided for access pathways to and within the fire brigade
.equipment
storage areas and dress-u locker areas in support of fire brigade
operations should power fail during a fire emergency. The fire brigade self-contained
breathing apparatuses (SCBAs) were reviewed for adequacy as well as the availability
of simp!ementel breath'
, .,d t
, .p 'I
&
,
S
L4
The team reviewed fire fighting pre-fire plans for the selected areas to determine if
appropriate information was provided to fire brigade members and plant operators to
facilitate suppression of a fire that could impact SSD. Team members 'also walked down
the selected fire areas to compare the associated pre-fire plans and drawings with as-
built plant conditions. This was done to verify that fire fighting pre-fire plans and
drawings were consistent with the fire protection features and potential fire conditions
described in the Fire Hazards Analysis (FHA).
The team reviewed the adequacy of the design, installation, and operation of the manual
suppression standpipe and fire hose system for the control building. This was
accomplished by reviewing the FHA, pre-fire plans and drawings, engineering
mechanical equipment drawings, design flow and pressure calculations and NFPA 14
for hose station location, water flow requirements and effective reach capability. Team
members also walked down the selected fire areas in the control building to ensure that
4
hose stations were not blocked and to verify that the requ ired fire hose lengths to reach-
the safe shutdown equipment in each of the selected areas were available.: Additionally,
the team observed placement of the fire hoses and extinguishers to assess consistency'
with the fire fighting pre-fire plans and drawings.
b.
Findin
~ o fidings f sigifiace were Identified.
.03
PotFr
aeSudwn Cagabiliyv
Inspection Scope
~
~
On a sample basis, in wre~icnv~s crfr.
A4
~-r'egy that systems and equipment
identified in the licensee's SSAR as being required to achieve and maintain hot
shutdown conditions would remain free of fire ,damage in the event of fire in the selected
fire areas. The evaluation included a review of cable routing data depicting the location'
of power and control cables associated with SSID Path I and Path 2 components of the
RCIC and HPCI systems. Additionally, on a sample basis, the team reviewed the
licensee's analysis of electrical protective device (e.g., circuit breaker, fuse, relay)
coordination. The following motor operated valves (MOVs) and other components were
reviewed:
.
Findi
.
Spurious Actuation of Elevn
t he team identified a potential co
e
in that the licensee used manual
action t
ate two 4 to 20 ma instrumenta
n loop control circuits associated with
eleve
in lieu of providing the required. Tis did neot aipu e rto be
consistent with
the pnt1ensing basi~por 10 CFR 50 Appendix R.____
wit
The
fi
Rstates patae
24 could
dcauie
all eleven SRVs
to spur usy actuate as a result of fire damage to two cables Ih46located in close
proximity in this area. The specific circuits that could cause this event have been
identified by the licensee (circuit no's.: ABE019CO8 and ABE019CO9). Each of these
two circuits provides a 4 to 20 ma instrumentation signal from SRV high-pressure
W~V ',t
.~Ž '~~ .A.
..--
'Ae
.03
~os-Fir~af
Shudow Capbilty,,.
- l
actuation transmitter (2B21-N127B and 2B21-N127D) to masterip units 2B21-N697B
and 2B21-N697D, r spectively. The purpose of this circuitry is t provide an electrical
backup to the mec anical trip capability of the individual SRVs. n the event of high
reactor pressure, he circuits would provide a signal to the master trip units which would
cause all eleven SRVs to actuate (open). The pressure signal from each transmitter is
conveyed to its ;espective master trip unit through a two-conductor, instrument cable
that is routed
rough this fire area (two separate cables). Each cable consists of a
single twistqE pair of insulated conductors, an uninsulated drain wire that is wound
around the 'twisted pair of conductors, and a foil shield. In Fire Area 2104 the two
cables are located in close proximity, in the same cable tray. Actuation of the SRV
electrical backup is completely "blind"AWKIe operators. That is, unlike ADS, it does not
provide any pre-actuation indication
.g., actuation of the ADS timer) or an inhibit
capability (e.g., ADS inhibit switch). Since the operators typically would not initiate a
manual scram until fire damage significantly interfered with control of the plant, its
possible that all eleven SRVs could open at 100% power, prior to scramming the
reactor. This scenario could place the plant in an unanalyzed condition.
Unlike a typical control circuit, a direct short or "hot short" between conductors of a 4 to
20 ma instrument circuit may not be necessary to initiate an undesired (false high)
signal. For cables that transmit low-level instrument signals, afdegradation of the
insulation of the individual twisted conductors due to fire dam
e may be sufficient to
cause leakage currents to be generated between the two conductors. Such leakage
current would appear as a false high pressure signal to the trip units. If both cables
were damaged as a result of fire, false signals generated as a result of leakage current
in each cable, could actuate the SRV electrical backup scheme which would cause all
eleven of the SRVs to open. The conductor insulation and jacket material of each cable
is cross-linked polyethylene (XLPE). Since both cables are in the same tray and
-pored to the same heatinn rate, there is a reasonaqhle likelihood that hoth
instrumentation cables
suffer insulation damage at the same time and both
circuits could fail high
ul
The licensee's SSAR recognizes the potential safety significance of this event and
describes methods that have been developed to prevent its occurrence and/or mitigate
its impact on the plant's post-fire safe shutdown capability should it occur. To prevent
this scenario, the licensee has developed procedural guidance which directs operators
to open link BB-10 in panel 2H11;P27 and link BB-10 in panel 2H11-P928. These
panels are located in the xxxxLocxxx . Opening of these links would prevent actuation
of the SRV trip units by removing the 4 to 20 ma signal fed by the pressure transmitters
to the master trip units. In the event the SRVs were to open prior to operators
completing this action, the SSAR credits core spray loop A to mitigate the event.
The inspection team had several concerns regarding the licensee's approach to this
potential spurious actuation of the SRVs. Specific concerns identified by the team
included:
- 6
- 1.
The links may not be opened in time to preclude inadvertent actuation of
the SRVs.
2.
The use of links to avoid inadvertent actuation of the SRVs did not
appear to be consistent with the current licensing basis.
3.
No objective evidence existed to demonstrate that the post-fire safe
shutdown equipment could adequately mitigate a fire in Fire Area 2104, if
the SRVs were to open. .
4.
The operations staff is unable to manually control the groupthat
are credited for mitigating a fire in Fire Area 2104 beca
f spuriousIl
actuati
ire induced damage.
With regard to the timing of operator actions to prevent fire damage from causing all
SRVs to open, during the inspection, the licensee performed an evaluation which
estimated that approximately thirty minutes would pass from the time of fire detection to
the time an operator would implement procedural actions to open the links. The
inspectors independently arrived at a similar time estimate based on their review of the
procedure. In response to inspector's concerns that this interval may be too lengthy to
preclude fire damage to the cables of interest and subsequent actuation of the SRVs,
the licensee agreed to enhance its existing procedures so that the action would be
taken immediately following confirmation6
f fire in areas where the spurious actuation
could occur.
r UsA,
- 5s
a
S
..
o¶/oS6/
,/
A
e
The'team also considered
opening terminal board links
K
in compliance with the plant's licensing basis; Current licensing basiwuments,
specifically Georgia Power request for exemption dated May 16, 19
d a subsequent
NRC Safety Evaluation Report (SER) dated January ,1987, charac tefzed the
ening
of links as a repair activity that is not permitted as
eans of complying withYction
!!1.G of Appendin. R. T6^ In,!ces
crncuded I
L, the
L
pening f i~ifl'swas considelred
a repair by both the licensee and the NRC staff in 1987. The licensee could not provide
any evidence to justify whv these actions ar/not characterized as a repair activity in its
rersp
~rs onse
thlis-insip-fi
fining the licensee initiated a Condition
Repor (CR 2003800152, dated 7124103) to evaluate actions to open links, in order to)
determine if they are necessary to achieve hot shutdown, and if an exemption from
Appendix R is required.
Additionally, because there is a potential for all SRVs to spuriously actuate as a result of
fire in Fire Pfenp 2104 at a time when RHR is not available, the SSAR credits the use of
op A to accomplish the reactor coolant makeup function. During the
inspection, the licensee performed a simulator exercise of an event which caused all 11
SRVs to open. During this exercise, simulator RPV level instruments indicated that core
spray would be capable of maintaining level above the top of active fuel. However, the
licensee did not provide any objective evidence (e.g., specific calculation or analysis)
which demonstrated that, assuming worst-case fire damage in Fire Area 2104, the
7
limited set of equipment available would be capable of mitigating the event in a manner
that satisfies the shutdown performance goals specified in Appendix R, Section L.1.e to
1OCFR 50.
Finally, the licensee's failure to implement the design input requirements of one-out-of-
two taken twice logic for DCR 91-134 resulted in the followip plant problem. The logic
that was installed by DCR 91-134 for the SRVs was a tw -out-of-two coincident taken
twice logic in addition to a on -out-of-two coincident Ken twice logic. The team
determined that the two-out-of-cwo coincident log
nput from trip unit master relays
K31OD and K335D represented
common capee failure for group "A7 SRVs for a fire in
Fire Area 2104. Specifically, cabl ABE01I 08 associated with pressure transmitter
2B21-N127B current loop, and cabl
A
19CO9 associated with pressure transmitter
ZI-N127D current loop, ar route
close proximity to each other in the same cable
ay in Fire Area 2104. Both s ie cisted pair instrument cables are unprotected
from the effects of a fire in this
e area. Fire induced insulation damage to both cables
could result in leakage curre s which ca
es the instrument loops to fail high. This
failure mode simulates a
h nuclear boile
ressure condition and would initiate SRV
backup actuation of all
e group "A" SRVs.
henever a SRV lifts, it will remain open
until pressure reduc
to about 85% of its ove ressure lift setpoint The instrument
loops having failed igh, however, will ensure that the trip unit master relays and the trip
unit slave relavs con
to energize th
ot valve of the individual
nd keep the.
0Ccs
fassociamode prevents the operators from manually controlling toS
sopAS: s srqie
er the SSAR.
-2
Pending additional review by the Nith issue is identified as URI 50-366/2003006-
01, Concerns Associated with Pote
pening of SRVs
Anal sis: This issue has the potential to
pact availabi:and reliabil
objectiv
as
i1
al
eq ipment perfor ance attribute
the
mitigating
stem corn stone.
Ho ever, analy f this issue emains incomrteiend
e
NR.
- -*
0 Alternate Shutdown Capabilitv/Oerational ImDlementation of Alternative Shutdown
AWCaoabilitv/-M°
a.
Inspection Scone
- ,
5
n
The selected fire areas that were the focus of this inspectn all involved reactor
shutdown from the control room. None involved abandoni
the control room and
alternative safe shutdown from outside of the control room. However, the licensee's
plans for SSD following a fire in the selected areas involved many local manual operator
actions that would be performed outside of the control area of the control room. This
section of the inspection focused on those local manual operator actions.
The team reviewed the operational implementation of the SSD capability for a fire in the
selected fire areas to determine if: (1) the procedures were consistent with the Appendix
s
\\
- F
X
v At-
l
tK
A:.'. Or: .N..',< . By :.
i;
.,
.,
.
.
-
.
I.!
....
......
- " ':':;
.
.
-
'
'
';
.
,
.
,
-
-
.
.
.:
-
. -
....
..
...
-\\ So' #
,
.
...
,:
-
.
...
..
-. -,
.
,
.
............
- .
-:
.
r
,
- .
'.,.:
,,
- .-. .
,:
.. ,..,
-:
4 . .- , -.
-
-
.
..
-.
.
...........
...
..
.
..
...
.
.
......
.
.
- ..-
...
.:
- , :, ',
'. .:..'
- "
.
-
.
..
.
.
.;
.......
.,
,
.
,
.
-
.
- ...
.;:
-
.
.
..
-
-
.,
.
, .:
. .
.
-,
-: ' -*: :'.',
r ' ' , -
' :
.
<
...
,
.
.-
-.
-
.
- .
.
.
.
s
.
.
.
.
.
.
.
- .:
.
.
.
,
..
..
.
-
..
.
-
.
-.-
.
- .
,,
-
...
.
.
.
.
.
.
..
.
. ;-E .
- ':
.
.
..
..
.
.
.
.
.
..
.
.
.
.;,
,:
.
.
.
b.
-
,
...
..
-
,
.
-
.
.
..
.
.
.
.
.
.
.,,-'-' .
- 1-
..
..
....
',:
- :-
.
.
.
.
..
.
..
..
.
.
.
.
. ,:
--
.',
..
.
.
.
.
..
..
_
8
R safe shutdown analysis (SSA); (2) the procedures were written so that the operator
actions could be correctly performed within the times that were necessary for the actions
to be effective; (3) the training program for operators included SSD capability; (4)
personnel required to achieve and maintain the plant in hot standby could be provide
from the normal onsite staff, exclusive of the fire brigade; and (5) the licensee
periodically performed operability testing of the SSD equipment.
The team walked down SSD manual operator actions that were to be performed outside
of the control area of the main control room for a fire in the selected fire areas and.
discussed them with operators. These actions were documented in Abnormal Operating
Procedure (AOP) 34AB-X43-001-2, Version 10.8, dated May 28, 2003. The team
evaluated whether the local manual operator actions could reasonably be performed,
using the criteria outlined in NRC Inspection Procedure (IP) 71111.05, Enclosure 2. The
team also reviewed applicable operator training lesson plans and job performance
measures (JPMs) and discussed them with operators. In addition, the team reviewed
records of actual operator staffing on selected days.
Findinas
Untimely
Introducti
opening c
Licensee
physically
and UnapDroved Manual Operator Action for Fire Safe Shutdown
ion: The team found that a local manual operator action to prevent spurious
of all eleven SRVs would not be performed in sufficient time to be effective.
reliance on this manual action for hot shutdown during a fire, 'instead of
Iy protecting cables from fire damage, had not been approved by the NRC.
Descriotion: The team noted that Step 9.3.2.1 of AOP 34AB-X43-001-2, Fire
Procedure, Version 10.8, dated May 28, 2003, stated: 'To prevent all eleven SRVs from
opening simultaneously, open links BB-10 in Panel 2H11-P927 and BB-10 in Panel
The team noted that spurious opening of all eleven SRVs would be
considered a large loss of coolant accident (LOCA), and that a LOCA must be
prevented from occurring during a fire event. Additionally, the team observed that this'
step was sufficiently far back in the procedure that it may not be completed in time to
prevent potential fire damage to cables from causing all eleven S
uriously
open.
The licensee had no preplanned estimate of how long ituld take operators to
complete this step during a fire event. There was n
vent time line or operator training
!P on this step. The team noted that, dun g a
event, operators could be using
many other procedures concurrent with theyr
ocedure. For example, they could be
using other procedures to communicate wit th
ire brigade about the fire, respond to a
reactor trip, deal with a loss of offsite power, and provide emergency classifications and
offsite notifications of the fire event. During the inspection, licensee operators estimated
that, during a fire event, it could take about 30 minutes before operators would
accomplish Step 9.3.2.1. The team concurred with that time estimate. However, NRC
fire models indicated that fires could potentially cause damage to cables in as little as
about five to ten minutes. Consequently, th
am concluded that during a fire event the
licensee's procedures would not ensure that
ep 9.3.2.1 would be accomplished in time,-
to prevent potential spurious opening of all eleven SRVs..
The team also identified other issues with Step 9.3.2.1. There was no emergency
'-
lighting inside the panels, hence if the fire caused a loss of normal lighting (e.g., by
causing a loss of offsite power), operator/would need to use flashlights to perform the
actions inside the panels. Consequen( the team considered the emergency lighting.-.
for Step 9.3.2.1 to be inadequate (see rection 1 R05.07.b). In addition, labeling of the
links inside the panels was so poor that operators stated that they would not fully rely on
the labeling. Also, the tool that operators would use to loosen and slide the links inside
the energized panels was made of steel and was not professionally electrically
insulated. Further, licensee reliance on this operator action, instead of physically
protecting the cables as required by 10 CFR 50, Appendix R, Section III.G.2, had not
been approved by the NRC.
The licensee stated that cable damage to two instrument cables, for reactor pressure
signals, would be needed to spuriously open all eleven SRVs. Since the licensee stated
that the two cables werg in the same cable tray in fire area 2104, the Unit 2 east
cableway, the team con idered that a fire in that area could potentially cause all eleven
SRVs to spuriously open (see section 1R21.01.b).
In response o th'
the licensee initiated CR 2003008203 and pr
ly
r rocedu e before the end of the inspection, moving the action of tep
be3..
inning > be
of the procedure. The procedure change enabled the a ons
be accomplished much sooner during a fire in the Unit 2 east cableway or in other ire
as that were vulnerable to the potential for spuriously opening all eleven SRVs.
A
s
he team determined that this pe
rrissue is, related to associated circuits.
As described in NRC Inspection Procedure (IP) 71111.05, Fire Protection, inspection of
associated circuits is temporarily limited. Consequentry. the team did not pursue the-
cable routing or circuit analysis that would be necessary to evaluate the possibility, risk,
or potential safety significance of Group B and C SRVs spuriously opening due to fire'
damage to the instrument cables. The team did, however, perform a circuit analysis of
Group A SRVs for which the licensee takes credit for a fire in fire area 2104. (see
section IR21.0
Enforcement: 10 C
, Appendix R,Section III.G.2 requires that where cables or
equipment, incluW g associated non-safety circuits that could prevent operation or
cause mal-oper ion due to hot shorts, open circuits, or shorts to ground, of redundant
trains of syst es necessary to achieve and maintain hot shutdown conditions are
located withir he same fire area outside of the primary containment, one of the
following me ns of ensuring that one or the redundant trains is free of fire damage shall
be provided: 1) a fire barrier with a 3-hour rating; 2) separation of cables by a
horizontal distance of more than 20 feet with no intervening combustibles and with fire
4t'-
zal
Z
/4t1
,0
.
Pz
.
sizable
7AA
H
i:z;= I
'I- H I
-'r
71
--
By-f-And
.X/14
a
e
I
4
I1 .. pi
v
.
,
.
.1
7 ---
54
v
d}
--"-Apollo",,
.all/
yntl
I -
r62d~A67-~
/7lng-
/444/9
re-e
1'71/2IA
4-9240,
z
9 I
4 I
Y14"
1;
- 2-vr-
a.
e
D5
)In
(-L~
1 r
C C ~ I-4'4 4
0<4
5sO
herx~
Ply-.1-01
74/
/Z
z/
,*-
-
-.
00-1I
i
,Speyer
_________~
ivNItzzpe
le /Tyson.
r
'.
10
detectors and automatic fire suppression; or 3) a fire barrier with a 1-hour rating with fire
detectors and automatic suppression.
The licensee had not provided physical protection against fire damage for the two
-
instrument cables by one of the prescribed methods. Instead, the licensee had relied on'
manual operator actions to prevent the spurious opening of all eleven SRVs. Licensee
personnel contended that fire damage to two cables was outside of the Hatch licensing
basis and consequently that there was no requirement to protect the instrument cables.
However, the licensee could provide no evidence to support that position.
This potential issue will rem, On unreso~ved pending the6dRcompletion of a
significance determination .This
Gpete~Wal issue is identified as URI 50-366/03-06-02,'
Untimely and Unapproved Manual Operator Action for Fire Safe Shutdown.
2.
Local Manual Ogerator Action was Too Difficult and Unsafe
Introduction: A finding of very low safety significance was identified In that a local
manual operator action to operate SSD equipment was too difficult and was also unsafe.
The team judged that some operators would not be able to perform the action. This
finding involved a violation of NRC requirements.
Description: The team observed that Steps 4.15.8.1.1 and 9.3.5.1 of the Fire Procedure
were relied on instead of providing physical protection for cables or providing a
procedure for cold shutdown repairs. Both steps required the same local manual
operator action: 'Manually OPEN 2E1 1-FO15A, Inboard LPCI Injection Valve, as
required." This action was to be taken in the Unit 2 drywell access, which was a locked
high radiation, contaminated, and hot area with temperatures over 100 degrees F.
Valve 2E1 1 -F01 5A was a large (24-inch diameter) motor-operated gate valve with a
three-foot diameter handwheel. The main difficulty with manually opening this valve was
lack of an adequate place to stand. An operator showed the team that to perform the
action he would have to climb up to and stand on a small section of pipe lagging (a
curved area about four inches wide by 12 inches long), and then reach back and to his
right side, to hold the handwheel with his right hand, while reaching forward and to his
right to hold the clutch lever for the motor operator with his left hand. He would not have
good balance while performing the action. The foothold, which was large enough to
support only one foot, was well flattened and appeared to have been used in the past to
manually operate this valve. The foothold was about six to seven feet above a steel
grating, and the team observed that space available for potential use of a ladder to
better access the 2E1 1-FO15A valve handwheel was not good.
Other difficulties with manually opening the valve included the heat; the need to wear
full anti-contamination clothing, a hardhat, and safety glasses; and inadequate
11
emergency lighting (see Section 1 R05.07). Also, there was no note or step in the
procedure to ensure that the RHR pumps were not running before attempting to
manually open the 2E1 1-FOI5A valve. If an RHR pump were running, it could create a
differential pressure across the valve which could make manually opening it much more
difficult. If the operator did not have sufficient agility, strength or stamina, he would be
unable to complete the action. Also, the team judged that inability to remove sweat from
his eyes, due to wearing gloves that could be contaminated, would be a limiting factor
for the operator. In addition, if the operator slipped or lost his balance, he could fall and
become injured. Considering all of the difficulties, the team judged that this action was
unsafe and that some operators would not be able to pyrorm it.
The licensee had no operator training obpcrfii
e
J
M JP
for performing
this action and could not demonstrate that all operators could perform the action. One
experienced operator, who appeared to be in much better physical condition that an
average nuclear plant operator, stated that he had manually operated the valve in the
past, but that it had been very difficult for him.
The team judged that, since this action was not required to maintain hot shutdown and
was required for cold shutdown following a fire in one of the four selected fire areas,
licensee personnel could have time to improve the working conditions after a fire. They
could have time to install scaffolding or temporary ventilation; improve the lighting; and
assign multiple operators to manually open the valve. They could have'time to perform
a 'cold shutdown repair.' However, the licensee had not preplanned any cold shutdown
repairs for opening this valve.
Analvsis: This finding is greater than minor because it affected the availability and
reliability objectives and the equipment performance attribute of the mitigating systems
cornerstone. Since the licensee could have time to develop and implement cold
shutdown repairs to facilitate accomplishment of the action, this finding did not impact
the effectiveness of one or more of the defense in depth elements. Hence this finding
did not have potential safety significance greater than vary low safety signifinanr.e
(Green).
Enforcement: 10 CFR 50, Appendix R, Section III.G.1 requires that fire protection
features shall be provided for systems important to safe shutdown and shall be capable
of limiting fire damage so that systems necessary to achieve and maintain cold
shutdown from either the control room or emergency control stations can be repaired
within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. In addition, TS 5.4.1 requires that written procedures shall be
established, implemented, and maintained covering activities including fire protection
program implementation and including the applicable procedures recommended in
Regulatory Guide 1.33, Revision 2, Appendix A, February 1978. Regulatory Guide 1.33
recommends procedures for combating emergencies including plant fires and
procedures for operation and shutdown of safety-related BWR systems. The fire
protection program includes the SSAR which requires that valve 2E1 1 -FO1 5A be
opened for SSD following a fire in Fire Area 2104, the Unit 2 east cableway. AOP
34AB-X43-001-2, Fire Procedure, Version 10.8, dated May 28, 2003, implements these
T
12
requirements in that it provides information and actions necessary to mitigate the
consequences of fires and to maintain an operable shutdown train following fire damage
to specific fire areas. Also, AOP 34AB-X43-001-2 providet teps 4.15.8.1.1 and 9.3.5:1
for manually opening valve 2E11-FO15A following a fire in fire area 2104.
Contrary to the above, the licensee had no procedure for repairing any related fire.
damage within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. Instead, the licensee relied on local manual operator actions,
as described in Steps 4.15.8.1.1 and 9.3.5.1 of AOP 34AB-X43-001-2. However, those
procedure steps were inadequate in that some operators would not be able to perform
them because the required actions were tbo difficult and also were unsafe. In response'
to this issue, the licensee initiated CR 203008202. Because the identified inadequate
operator actions are of very low safety significance and the issue has been entered into
the licensee's corrective action program, this violation is being treated as an NCV,
consistent with Section VI.A.1 of the NRC's Enforcement Policy: NCV 50-366/03-06-03,
Inadequate Procedure for Local Manual Operator Action for Post-Fire Safe Shutdown
Equipment.
3.
Unapproved Manual ODerator Actions for Post-Fire Safe Shutdown
Introduction: A finding of very low safety significance was identified in that the licensee
relied on some manual operator actions to operate SSD equipment, instead of providing
the required physical protection of cables from fire damage. This finding involved a
violation of NRC requirements.
Description: The team observed that AOP 34AB-X43-001-2, Fire Procedure, included
some local manual operator actions to achieve and maintain hot shutdown that had not
been approved by the NRC. Examples of steps from the procedure included:
Step 4.15.2.2; ...if a loss of offsite power occurs and emergency busses energize
..."Place Station Service battery chargers 2R42-S026 (2R42-S029), 2R42-S027
(2R42-S030) AND 2R42-S028 (2R42-S031) in service per 34.S0-R42-0On1-2."
(g
Step 4.15.4.5; ...If HPCI fails to automatically trip on high RPV level... OPEN the
following links to energize 2E41-F124, Trip Solenoid Valve,' AND to fail 2E41-
F3025 HPCI Governor Valve, in the CLOSED position:
TT-75 in panel 2H1 1-P601
TT-76 in panel 2HI1-P601"
Step 4.15.4.6; ... lf HPCI fails to automatically trip on high RPV level... "OPEN
breaker 25 in panel 2R25-S002 to fail 2E41-F3052, HPCI Govemor Valve, in the
CLOSED position."
The team walked downd ese actions using the guidance contained in Inspection
Procedure 71111.05T nd judged that they could reasonably be accomplished by
operators in a timely manner. However, the team determined that these operator
.
, : -
a , I ,
I .
1.
actions were being used instad of physically protecting cables from fire damage that
could cause a loss of statfn service battery chargers or a HPCI pump runaway.
Analysis: The finding'
greater than minor because it affected the availability and
reliability objectives
he equipment performance attribute of the mitigating systems
cornerstone. Since the actions could reasonably be accomplished by operators in a
timely manner, this finding did not have potential safety significance greater than very
low safety significance.
Enforcement: 10 CFR 50, Appendix R, Sec
.G.2 requires that where cables or
equipment, including associated non-safety c uits that could prevent operation or
cause maloperation due to hot shorts, ope
ircuits, or shorts to ground, of redundant
trains of systems necessary to achieve
d maintain hot shutdown conditions are
located within the same fire area outsi e of the primary containment, one of the
following means of ensuring that one orthe redundant trains is free of fire damage shall
be provided: 1) a fire barrier with a 3-hour rating; 2) separation of cables by a
horizontal distance of more than 20 feet with no intervening combustibles and with fire
detectors and automatic fire suppression; or 3) a fire barrier with a 1-hour rating with fire
detectors and automatic suppression.
Contrary to the above, the licensee had not provided the required physical protection
against fire damage for power to the station service battery chargers or for HPCI
electrical control cables. Instead, the licensee relied on local manual operator actions,
without NRG approval. In response to this issue, the licensee initiated CR2003800166
dated 7125:2003. Because the issue had very low safety significance and has been
entered into the licensee's corrective action program, this violation is being treated as an
NOV, consistent with Section VL.A.1 of the NRC's Enforcement Policy: NCV 50-366/03-
06-04, Unapproved Manual Operator Actions for Post-Fire Safe Shutdown.
.06-
Communications
I"17
a.
Inspection Scope
The team reviewed the plant communications systems that would be relied upon to
support fire brigade and safe shutdown activities. The team walked down portions of
the safe shutdown procedures to verify that adequate communications equipment would
be available for personnel performing local manual operator actions. In addition, the
team reviewed the adequacy of the radio communication system used by the fire
brigade to communicate with the main control room.
b.
Findings
No findings of significance were identified.
.07
Emeraency Lighting
14
a.
Inspection Sco.
The team inspected the licensee's emergency lighting systems to verify that 8-hour
emergency lighting coverage was provided as required by 1 0 CFR 50, Appendix R,
Section lII.J., to support local manual operator actions that were needed for post-fire -
operation of SSD equipment. During walkdowns of the po'st-fire SSD operator actions
for fires in the selected fire areas, the team checked if emergency lighting units were
installed and if lamp heads were aimed to adequately illuminate the SSD equipment, the
equipment identification tags, and the access and egress routes thereto, so that
operators would be able to perform the actions without needing to use flashlights.,
b.
Findings
Inadequate Emergency Lighting for Operation of Safe Shutdown Eguipment
Introduction: A finding with Very low safety significance was identified in that emergency.
lighting was not adequate for some manual operator actions that were needed to'-
support post-fire operation of SSD equipment. This finding involved a violation of NRC,
requirements.
Descri-tion: The team observed that emergency lighting was not adequate for some:
manual operator actions that were needed to support post-fire operation of SSD
equipment. Examples included the following operator actions in procedure 34AB-X43-
001-2, Fire Procedure, Version 10.8; dated May 28, 2003:
Step 4.15.2.2; ... if a loss of offsite power occurs and emergency busses e~nergize
"..Place Station Service battery chargers 2R42-S026 (2R42-S029), 2R42-S027
(2R42-S030) AN
2R42-S028 (2R42-S031) in service per 34SO-R42-001-2."
Step 4.15.4.5; ...
i
f HPCI fails to automatically trip on high RPV level... "OPEN the'
following links to energizs
2E41 -Ft 24, Trip Solenoid Valve, AND to fall 2E41
F3025 HPCI Governor Valve, in the CLOSED position:
TT-75 in panel 2H11-P601
TT-76 in panel 2H-11-P601",
Step 4.15.5; "iF 2R25-65, Instrument Bus 2Bf , is DE-ENERGIZED perform the
Intrfollowing manual actions to maintain 2C32-R655, Reactor Water Level
Instrument, operable:
4.1 5.5.1; At panel 2H-11 -P612, OPEN links AAA-1i 1 and AAA-1 2.
4.15.5.2; At panel 2HI11~-P601, CLOSE links HH-48 and HH-49."
Steps 4.15.8.1.1 and 9.3.5.1; "Manually OPEN 2E1 1-1FO15A, Inboard LPCI
Injection Valve, as required.
Steps 4.15.8.1.2 and 9.3.5.2; t "Manually CLOSE 2E1 1 -Fo ae8A, RHR Pump A
Minimum Flow Isolation Valve, as required."
- 6
1.5
/
Step 9.3.2.1; "To prevent all 1 1 SRVs from opening simultaneously, open links
- '
BB-10 in Panel 2H11-P927 and BB-10 in Panel 2H11-P928."
. /
Step 9.3.3; "At Panel 2H11-P627, open links AA-19, AA-20, AA-21, and AA-22,
to prevent spurious actuation of SRVs 2B21-F013D AND 2B21-F013G."
Step 9.3.6; "OPEN link TB9-21 in Panel 2H1 1-P700 to open Drywell Pneumatic
<
System Inboard Inlet Isolation, 2P70-F005."
Step 9.3.7; "OPEN link TB1-12 in Panel 2H1 1-P700 to open Drywell Pneumatic
System Outboard Inlet Isolation, 2P70-F005."
.
Step 9.3.9.1; "Confirm OR manually CLOSE RHR Shutdown Cooling Valve
.
Step 9.3.9.2; "Manually OPEN Shutdown Cooling Suction Valve 2E11-F008, IF
required..."
The team verified that flashlights were readily available and judged that operators would
be able to use the flashlights and accomplish the actions, with two exceptions. One '
exception was the action to open terminal board links in two panels tqjprevent all eleven
SRVs from spuriously opening, which was judged to be untimely (see)ection.
1R05.05.b.1). The other exception was the action to open 2E11-FO15A, which was
judged to be too difficult (see
ction 1 R05.05.b.2). For all of these actions, the lack of
adequate emergency lighting could make the actions more difficult to complete in a
timely manner and increase the chance of operator error.
Analysis: This finding is greater than minor because it affected the reliability objective
and the equipment performance attribute of the mitigating systems cornerstone. Since
op W
would be able to accomplish the actions with the use'of flashlights, this finding
dad
im
impact the effectiveness of one or morc of the defCnse in depth elements.
H cthi finding did not have potential safety significance greater than very low safety
sifice
(Green).
Enforcement: 10 CFR 50, Appendix R, Section III.J. requires that emergency lighting
units with at least an 8-hour battery power supply shall be provided in all areas needed
for operation of safe shutdown equipment and in access and egress routes thereto.
Contrary to the above, emergency lighting units were not adequately provided in all
areas needed for operation of safe shutdown equipment. In response this issue, the
licensee initiated CRs 2003008237 and 2003008179. Because the identified lack of
emergency lighting is of very low safety significance and has been entered into the
licensee's corrective action program, this violation is being treated as an NCV,
consistent with Section VI.A.1 of the NRC's Enforcement Policy: NCV 50-366/03-06-05,
Inadequate Emergency Lighting for Operation of Safe Shutdown Equipment.
-
(-w
- '
I; z
6 d e
- -I
X
-
f
i
\\
- .
.08
.
.
.
.
.
.,
..
. -; .
. .
. -.
.
.
.
.
.
-
-
...
............
.
.
.
.
.
-,
.- ,.
...
.'
.'
..
- 09
.,
.
.
.
- a.
.,
.
.
. ICold Shutdown Repairs
16
The licensee had identified no needed cold shutdown repairs. Also, with the exception
of the potential need for a cold shutdown repair to open valve 2E1 1 -F01 5A (see section
1 R05.05.b.2), the team identified no other need for cold shutdown repairs.
Consequently, this section of IP 71111.05 was not performed.
I
I
Fire Barriers and Fire Area/Zone/Room Penetration Seals
Inspection Scope
.
.
The team reviewed the selected fire areas to evaluate the adequacy of the fire
-resistance of fire area barrier enclosure walls, ceilings, floors, fire barrier mechanical
and electrical penetration seals, fire doors, and fire dampers. The team selected
several fire barrier features for detailed evaluation and inspection to verify proper
installation and qualification. This was accomplished by observing the material condition
and configuration of the installed fire barrier features, as well as construction details and
supporting fire endurance tests for the installed fire barrier features, to verify the as-built
configurations were qualified by appropriate fire endurance tests. The'team also
reviewed the FHA to verify the fire loading used by the licensee to determine the fire
resistance rating of the fire barrier enclosures. The team also reviewed the installation
instructions for sliding fire doors, the design details for mechanical and electrical
penetrations, the penetration seal database, Generic Letter (GL) 86-10 evaluations, and
the fire protection penetration seal deviation analysis for the technical basis of fire
barrier penetration seals to verify that the fire barrier installations met design
requirements and license commitments. In addition, the team reviewed completed
surveillance and maintenance procedures for selected fire barrier features to verify the
fire barriers were being adequately maintained.
The team evaluated the adequacy of the fire resistance of fire barrier electrical raceway
fire barrier system (ERFBS) enclosures for cable protection to satisfy the applicahle
separation and design requirements of 10 CFR 50, Appendix R, Section III.G.2.
Specifically, the team examined the design drawings, construction details, installation
records, and supporting fire endurance tests for the ERFBS enclosures installed in Fire
Area 2104, the Unit 2 East Cableway. Visual inspections of the enclosures were
performed to confirm that the ERFBS installations were consistent with the design
drawings and tested configurations.
II
Ob.
The team reviewed abnormal operating fire procedures, selected fire fighting pre-plans,
fire damper location and detail drawings, and heating ventilation and air conditioning
(HVAC) system drawings to verify that access to shutdown equipment and selected
operator manual actions would not be inhibited by smoke migration from one area to
adjacent plant areas used to accomplish SSD.
Findings
f;
.
T
17
No findings of significance were identified.
.10
Fire Protection Systems. Features, and Equipment
a.
lns.ection Scooe
The team reviewed flow diagrams, cable routing information, and operational valv e-,
lineup procedures associated with the fire pumps and fire protection water supply
system. The review evaluated whether the common fire protection water delivery and'
supply components could be damaged or inhibited by fire-induced failures of electrical
power supplies or control circuits. Using operating and test procedures, the team toured
the fire pump house and diesel driven fire pump fuel storage tanks to observe the
system material condition, consistency of as-built configurations with engineering
drawings, and determine correct system controls and valve lineups. Additionally, the
team reviewed periodic test procedures for the fire pumps to assess whether the.
surveillance test program was sufficient to verify proper operation of the fire protection
- water supply system in accordance with the program operating requirements specified
in Appendix B of the FHA.
The team reviewed the adequacy of the fire detection systems in the selected plant fire
areas in accordance with the design requirements in Appendix R, lll.G.1 and Ml.G. 2..
The team walked down accessible portions of the fire detection systems In the selected
fire areas to evaluate the engineering design and operation of the installed
configurations. The team also reviewed engineering drawings for fire detector types
.
spacing, locations and the licensee's technical evaluation of the detector locationsfor
the detection systems for consistency with the licensee's FHA, engineering evaluations
for NFPA code deviations, and NFPA 72E. In addition, the team reviewed surveillance
procedures and the detection system operating requirements specified in Appendix B of
the FHA to determine the adequacy of fire detection component testing and to ensure
that the detection systems could function when needed.
The team performed in-plant walk-downs of the Unit 2 East Cableway automatic wet
pipe sprinkler suppression system to verify the proper type, placement and spacing of
the sprinkler heads as well as the lack of obstructions for effective functioning. The
team examined vendor information, engineering evaluations for NFPA code deviations,
and design calculations to verify ihat the required suppression system water density for
the protected area was available. Additionally, the team reviewed the physical
configuration of electrical raceways and safe shutdown components in the fire area to
determine whether water from a pipe rupture, actuation of the automatic suppression
system, or manual fire suppression activities in this area could cause damage that could
inhibit the plant's ability to safely shutdown.
The team reviewed the adequacy of the design and installation of the manual 002 hose
reel suppression system for the diesel generator building switchgear rooms 2E and 2F
(Fire Areas 2404 and 2408). The team performed in-plant walk-downs of the diesel
generator building 002fire suppression system to determine correct system controls
A
'I
18
and valve lineups to assure accessibility and functionality of the system, as well as
associated ventilation system fire dampers. The team also reviewed the licensee's
actions to address the potential for 002 migration to ensure that fire suppression and
post-fire safe shutdown actions would not be impacted. This was accomplished by the
'review of engineering drawings, schematics, flow diagrams, and evaluations associated
with the -diesel generator building floor drain system to determine whether system's and
operator actions required for SSD would be inhibited by 002 migration through the floor
drain system.
b:
.
Findings
No findings of significance were identified.
p Compensatory Measures
Inspection Scope
The team reviewed Appendix B of the FHA and applicable sections of the fire protection
program administrative procedure regarding administrative controls to identify the need
for and to implement compensatory measures for out-of-service, degraded, or
'
inoperable fire protection or post-fire safe shutdown equipment, features, and systems.
The team reviewed licensee reports for the fire protection status of Unit 1, Unit 2 and of
shared structures, systems, and components. The review was performed to verify that
the risk associated with removing fire protection and/or post-fire systems or
components, was properly assessed and implemented in accordance with the approved
fire protection program. The team also reviewed Corrective Action Program Condition
Reports generated over the last 18 months for fire protection features that were out of
service for long periods of time. The review was conducted to assess the licensee's
effectiveness in returning equipment to service in a reasonable period of time.
b.
Findings
No findings of significance were Identified.
1 1R21
SAFETY SYSTEM DESIGN AND PERFORMANCE CAPABILITY
1;:1.44.
S
Backup Actuation 3A Pressure Transmitter Signals
- nsgection Scope(
The team performed anindependent designreview of plant modificationo
DCt I 1-134 in
order tor evaluate the techniedl adequacy of the design change packag e a,
nies
-shar=Wed 10
rcr
sys5temsluzation. The scope of the review and circuit analysis
performed by the team was limited to the group "A' SRVs for which the licensee takes
credit in mitigating a fire in the fire areas selected for the inspection.
19
A
-
b.
.in:nc:
An inadequate plant modification, Reine IClul- .e~u 1,)Hes*CRY9 1-134, failed to
implement the design input requirements of one-out-of-two taken twice logic for the
SRVs backup actuation using pressure transmitter signals.
Description:
DCR 91-1 34 was implemented in response in to concerns raised in General Electric
Report NEDC-3200P, Evaluation of SRV Performance during January-Febr'uairy 1991
Turbine Trip Events for Plant Hatch Units I and 2. In order to ensure that individual -
SRV(s) will actuate at or near the appropriate set point and within allowable limits, a
backup mode of operation for the SRVs was implemented by this DCR. The design'
was intended to mitigate the effects of corrosion-induced set point drift of the Target
Rock SRVs.
Automatically controll
t~ 'stage SR Vs are installed on the main steam lines inside.
containment for the p r~e of relieving nuclear boiler pressure either by normal
mechanical action or by automatic action of an electro-pneumatic control system'..'Each
SRV can be manually controlled by .use of a two position switch located in the main
control room. When placed in the 'Open" position, the switch energizes the pilot valve.
of the individual SRV and causes it to go open. When the switch is placed, in the "Auto"
position the SRV is opened upon rece'ipt-of either an Auto Depressurization System
(ADS), or Low-Low Set (LLS) control logic signal. Either signal will initiate opening of.
the valve. DCR 91-1 34 provided a backup mode for initiation of electrical trip of the pilot
valve solenoid, which was independent of ADS or LLS logic. The backup mode required
no operator action to initiate opening of the SRVs and was considered a "blind control
loop" to the operators, ie. there are no instruments that provide the operators
information concerning the open/close status of the SRVs.
The scope of the plant modification involved the installation of four Rosemount pressure
transmitters (Model No. 1154GP9RJ), 0-3000 psig, in the 2H21-P404 and P405
instrument racks at Elevation 158 of the reactor building. Each pressure transmitter
fomd part of a 4-20 ma current loop and p~~dteaao rpsga o R
actuation within the following set point rou'
SRV Groua
SRV Identification Tags
SRV Set Point
A
2921-FOw3B, 0, F, and G
1120 psig
B
21E21-FOl3A, C, K, andPM
n J
193psig
C
C21B21-F013E, H, and D
- 1140 psig
20
Pressure transmitters (PTs) 2B21-N127A and 2B21-N127C were wired to ATTS
cabinets 2H1 1-P927. Pressure transmitter 2B21-N127A instrument loop components
consisted of a trip unit master relay K308C and trip unit slave relays K321C and K332C.
The loop components for pressure transmitter 2B21-N127C consisted of a trip unit
master relay K335C in addition to trip unit slave relays K336C and K363C. These two
instrument loops constituted a wDivision" pressure monitoring channels and were'
intended to provide the one-out of two logic signal from this Division for initiating SRV
backu atation.The desi'gn objective of having two instrument channels was to assure .
compliance with HNP-2-FSAR, Section 15.1.6.1, Application of Single Failure Criteria.
g
This criteria requires for anticipated operational occurrences (AOOs) that the protectiori2
sequences within mitigation systems be single component failure proof. A failure of one
-
_ instrument channel in a division will therefore not eliminate the protection provided by
eihe of
theinstruent channels.'.;
Additionally, pressure transmitters 2B21-N127B and 2B21-N127D were wired to ATTS
cabinet 2H11-P928.. Pressure transmitter 2B21-N127B instrument loop components
consisted of a trip unit master relay K31OD and trip unit slave relays KK312D and
K332D. The loop components for pressure transmitter 2B21-N127D consisted of a trip
unit master relay K335D in addition to trip unit slave relays K336D and K363D. These
two instrument loops constituted a separate 'Division' pressure monitoring'channels and
'were intended to provide the one-out of two logic signal from this Division'for initiating
SRV backup actuation.
mw
-assure onmplinr~ewith
NPF-AR
ion1.
The following table identifies the Division; pressure transmitter loops and the associated
trip unit master and slave relays:
Division
PT Loops
Trip Unit Master Relays
Trig Unit Slave Relays
'A
K308C
K321C and K332C
K335C
K336C and K363C
.
B
K310D
K312D and K332D
K335D
K336D and K363D
The Group A" SRVs were provided I
nput signals from the trip unit master relays.
The Group UB and C" SRVs were
ovided logic input signals from the trip unit slave
relays. The total of 12 relays de ribed above, (6 in ATTS cabinet 2H1 1-P927 and 6 in
ATTS cabinet 2H1 1-P928), wer intended to be wired to provide none-out-of-two taken
twice logic" for actuatjon of th SRVs. The design objective was to assure that a single
relay failure in eitheriivision would not cau e an inadvertent SRV actuation.
Coincident logic inpu is required from both Iivision instrument loops in order to initiate a
SRV backup actuation using the pressure tr nsmitter signals. This occurs when the
circuit that is used to energize the individual SRV pilot valve to open the SRV, is enabled
by receiving simultaneous logic inputs from either instrument loop in both division.
21.
The team performed a circuit analysis of SRV2B21-FO13F (Path 1) and SRV 2
1-
F01 3G (Path 2) in order to verify that the design objectives of implementing a o e-out-
of-two taken twice logic had been achieved. Based on this review the team de rmined
that the design objective of implementing a one-out-of-two taken twice logic h
not
been installed for the SRVs. The logic installed for the SRVs was a two-out-o two
coincident taken twice logic in addition to a one-out-of-two coincident taken
ice logic. :
-
-
The coincident logic implemented using trip unit master relays K310D and K35D
result in spurious actuation of group KA"
SRVs for a fire in Fire Area 2104.
defeats
- --
the c pability to manually control these SRVs. Whenever a SRV lifts, it will remain open
until nuclear boiler pressure is reduced to about 85% of its overpressure lift setpoint
However, because the instrument loops have failed high, the trip unit master relays and
the trip unit slave relays willjcontinue to energize the pilot valve of the individual SRV
--
and keep the SRV open
Tis failure mode prevents the operators from manually
controlling the
SRVs as is required per the SSAR.
Analvsis:This finding is greater than minor because it affected the availability and
reliability objectives and the equipment performance attribute of the mitigating system
cornerstone. The team determined that the finding had potential safety significance
greater than very low safety significance because it prevented the operators from
manually controlling group A SRVs which the licensee credits with mitigating a fire in
Fire Area 2104. Manual control of the group A SRVs is required to ensure that the
suppression pool temperature will not exceed the HCTL for the suppression pool.
Failure to ensure that the suppression pool temperature will not exceed the HCTL could
result in loss of net positive suction head for the Core S ay pumps which the licenses
credits for mitigatin thivent.
h/*
I-erv
Enforcement
10 CFR 50, Appendix B, Criterion l1l, requires that design control
measures shall provide for verifying or checking the adequacy of design.
DCR 91-1 34 specified design input requirements for the sensor initiated logic that
electrically activates the SRVs to be a one-out-of-two logic scheme. It also identifie.d tile
potential worst case failure mode of this logic modification as a short in the logic which
would results in an inadvertent opening of a SRV. It concluded that the modification is
designed so that the actuation logic will not fail to cause inadvertent opening of a SRV
I
nor prevent a SRV from lifting upon ADS/LLS activation. Contrary to the above the logic
implemented by the licensee for DCR 91-134 was different from the specified design
input requirements. The independent design review performed for DCR 91-134 failed to
identify this error in the logic scheme. Additionally, the Appendix R Impact Review
performed for DCR 91-134 failed to identify the potential failure mode of all eleven SRVs
because of fire induced damage in Fire Area 2104.
The plant modification installed for DCR 91-134 failed to correctly implement the one-
out-of-two taken twice logic that was specified in the SRV backup actuation via pressure
transmitter signals design change package. This failure has created a condition where
fire induced failures of two instrument circuit cables, (within close proximity to each
other), could result in spurious actuation of all eleven SRVs with the eleven SRVs
22
assuming a stuck open mode of operation, based on the logic input from trip unit master
unit relays K31 OD, and K335D and their associated trip unit slave relays. Pending
completion of an significance determination by the NRC, this item is identified as URI
50-366/03-06-06, Implementation of DCR 91-134 Results in Spurious Actuation of
Eleven SRVs because of Fire Induced Faults.
4.
OTHER ACTIVITIES
40A2 Identification and Resolution of Problems
a.
Inspection Scope
The team reviewed a sample of licensee audits, self-assessments, and condition reports
(CRs) to verify that items related to fire protection and to SSD were appropriately
entered into the licensee's CAP in accordance with the Hatch quality assurance program
and procedural requirements. The items selected were reviewed for classification and
appropriateness of the corrective actions taken or initiated to resolve the issues. In
addition, the team reviewed the licensee's applicability evaluations and corrective*
actions for selected industry experience issues related to fire protection. The operating
experience (OE) reports were reviewed to verify that the licensee's review and actions
were appropriate.
The team reviewed licensee audits and self-assessments of fire protection and safe
shutdown to assess the types of findings that were generated and to verify that the
findings were appropriately entered into the licensee's corrective action program.
b.
Findings
No findings of significance were identified.
OA6
eetinqs. Including Exit
he team presented the inspection results to Mr. R. Dedrickson, Assistant General
Manager, and other members of your staff at the conclusion of the inspection on July
25, 2003 The licensee acknowledged the findings presented. Proprietary information is
not included in the inspection report.
Licensee personnel:
M. Beard
V. Coleman
M. Dean
B. Duval
R. Dedrickson
M. Googe
J. Hamnmonds
D. Javorka
R. King
I. Luker
T. Metzer
A. Owens.
J. Payne
D. Parker
J. Rathod
K. Rosanski
M. Raybon
J. Vance
R. Varnadore
NRC personnel:
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Acting Engineering Support Supervisor
Quality Assurance Supervisor
Nuclear Specialist, Fire Protection
Chemistry Superintendent
Assistant General Manager for Plant hatch
Maintenance Manager/
Operations Manager
Administrative Assistant, Senior
Acting Engineering Support Manager
Senior Engineer, Licensing
Acting Nuclear safety and Compliance Manager
Senior Engineer, Fire Protection
Senior Engineer, Corrective Action Program
Senior Engineer, Electrical
Bechtel Engineering Group Supervisor
Oglethorpe Power Corporation Resident Manager
Summer Intern
Senior Engineer, Mechanical & Civil
Outages and Modifications Manager
r
Attachment
I
a
r
'.
N. Garret,
Senior Resident Inspector
C. Payne
Fire Protection Team Leader
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Opened
50-366/03-06-01,
Concerns Associated with Potential Opening of SRVs (Section-
-
1 R05.03.b)
50-366/03-06-02
Untimely and Unapproved Manual Operator Action for Post-Fire
Safe Shutdown (Section 1R05.05.b.1)
50-366/03-06-06,
Implementation of DCR 91-134 Results in Spurious Actuation of
Eleven SRVs because of Fire Induced Faults (Section.1 R21.01.b)
Opened and Closed
50-366/03-06-03
Local Manual Operator Action for Post-Fire Safe Shutdown
Equipment was Too Difficult and Unsafe (Section 1 R05.05.b.2)
50-366/03-06-04
Unapproved Manual Operator Actions for Post-Fire Safe
Shutdown (Section 1R05.05.b.3)
50-366/03-06-05
Inadequate Emergency Lighting for Operation of Post-Fire Safe
Shutdown Equipment (Section 1R05.07.b)
Discussed
None
Attachment
2
AOP 34AB-X43-002-0, Fire Protection System Failures, Version 1.3
SOP 34S0-C71-001-2,1I20VAC RPS Supply System, Version 10.2
34S-N40-001-2, Main Generator Operation, Version 10.8
SOP 34S0-R42-001-2S, 125V DC and 125/250 VDC System, Version 7.1
SOP 34SO-S22-001-2, 500 KV Substation Switching, Version 5.2
31 EO-EOP-01O0-2S, RC RPV Control (Non-ATWS), Rev. 8, Attachment 1
31 EO-EOP-01 2-2S, PC-1 Primary Containment Control, Rev. 4, Attachment 1
31 EO-EOP-013-2S, PC-2 Primary Containment Control, Rev. 4, Attachment I
31 EO-EOP-01 4-2S, SC - Secondary Containment Control, Rev. 6, Attachment I
31E0-EOP-01 6-2, CP-2 RPV. Flooding, Rev. 8,Attachment I
Procedure 34AB-X43-001-2S, Rev.10ED3, uFire Procedure," dated 5/28/03.
Calibration Procedure 57CP-CAL-097-2, Rosemount 1153 and 1154 transmitters, Revision No
19.9..
Drawings
H-1 1814, Fire Hazards Analysis, Control Bldg. El. 130'-0", Rev. 5
H-1 1821, Fire Hazards Analysis, Turbine Bldg 'El. 130'-O0w, Rev. 0
H-1 1846, Fire Hazards Analysis, Diesel Generator Bldg., Rev. 2
H-26014, R.H.R. System P&ID Sheet 1, Rev. 49
H-2015 RH.R. System P&ID Sheet 2, Re'.4
H-605
R
v. 46:
H-26018, Core Spray System P&ID, Rev. 29
B-I 0-1 326, Rectangular Fire Damper Schedule, Rev. 2
B-I10-1329, Rectangular Fire Damper, Rev. I
H-I 1033, Fire Protection Pump House Layout, Rev. 47
H-11035, Fire Protection Piping and Instrumentation Diagram, Rev. 22
H-1 1226, Piping-Diesel Generator Building Drainage, Rev. 6
H-1 1814, Fire Hazards Analysis Drawing, Control Building, Rev. 5
H-11821, Fire Hazards Analysis Drawing Turbine Building, Rev. 11
H-1 1846, Fire Hazards Analysis Drawing, Diesel Generator Building, Rev. 2
H-1- 1894, Fire Detection Equipment Layout-Diesel Generator Building, Rev. 2
H- 1915, Fire Detection Equipment Layout-Control Building, Rev. 2
H-: 3006,'Conduit and Grounding, Fire Pump House, Rev. 9
H-I1361 5, Wiring Diagram, Fire Pump House, Rev. 13.
H-I6054, Control Building HVAC System, Rev. 19
H-41509, Diesel Generator Building C02 System-P&ID, Rev. 5
H-43757, Penetration Seals-Type, Number, and as-Built Location, Rev. 3
Calculations. Analyses. and Evaluations
E. -. Hatch Nuclear Plant Units
r
and 2 Safe Shutdown Analysis Report, Rev. 20.
Edwin I. Hatch Nuclear Plant Fire Hazards Analysis and Fire Protection Program, Rev. 20
Calculation SMFP88-001, Hydraulic Analysis of Sprinkler Systems in Control Building East
Cableway, dated 03/11/1 988
Calculation SMNH94-046, FCF-F-OB-006, Fire Resistance of Concrete Block at HNP, dated
09/30/1994
Calculation SMNH94-048, FCF-FiOB-006, Cable Tray Combustible Loading Calculation, dated
Attachment
3
- 09/30/1994
Calculation SMVNH-98-023, HT-98617, Fire Protection Penetration Seal Deviation Analysis,
dated 10/28/1998
Calculation SMNHOO-01 1, HT-00606, Hose Nozzle Pressure Drop Analysis, dated 09/08/2000
Evaluation HT-91722, Fire Protection Code Deviation Resolution, dated 04/22/1992
Hatch Response to NRC IN 1999-005, dated 05/04/1 999
Hatch Response to NRC IN 2002-024, dated 09/20/2002
Calculation SENH 98-003, Rev. 0, plot K, protective relay settings 4kV bus 2E
- 'Calculation
85082MP, Plot 29, 600V Switcfigear 2C
- Calculation SENH 94-004, Attachment A, Sheets 7&8, 600/208 Reactor Building MCC 2C
Calculation SENH 91 -01 1, Attachment P, Sheet 6, Reactor Building DC MCC 2A
Calculation SENH 94-013, Sheets 28 and 29, 600V Reactor Building MCC 2E-B
Calculation SENH 91 -01 1, Attachment P, Sheet 16, Reactor Building 25OVDC MCC 2B3
- Audits and Self-Assessments
Audit No. 01-FP-1, Audit of the Fire Protection Program, dated April 12, 2001
Audit No. 02-FP-1, Audit of the Fire Protection Program, dated February 28, 2002,
Audit No. 03-FP-1, Audit of Fire Protection, dated April 21, 2003
- *1999-001106,
Lighting in Fire Equipment Bu~ilding
2002-000629, Inordinate Number of Buried Piping Leaks
2002-002127, Inadequate Bunker Gear
2002-002129, Health Physics Support and Participation for Fire Brigade
2003-000735, Impact on Cold Weather on Operating Units
Audit Report 01-FP-1, Audit of Fire Protection Program, dated 04/12/2001
- Audit Report 02-FP-1, Audit of Fire Protection Program, dated 02/28/2002
Audit Report 03-FP-1, Audit of Fire Protection Program, dated 04/21/2003.
CRs Reviewed
CR 2000007119, Fire Procedure 34AB-X43-001 1S Needs to be Enhanced
CR 2001002032,.Fire Procedure 34AB-X43-O01-2S Needs Actions for Diesel Fuel Oil Pumps
CR 2003004377, Fire Procedure 34AB-X43-001-1 Enhancements
CR 2003004379, Fire Procedure 34AB-X43-001-2 Enhancements
CR 2003004382, SSAR Discrepancies
CRs Generated During this Inspection
CR 2003007129, No Fire Procedure Actions for a Fire in the 2C Switchgear Room
CR 2003007719, Use of Link Wrench
CR 2003007978, Fire Damper Corrective Action
- CR 2003008141, Breaker Maintenance Handle
CR 2003008165, SSAR Section 2. 100
CR 2003008179, Drywell Access Emergency Lights
CR 2003008181, Link Labeling
Attachment
Fi
S
V-t
-
44
CR2003008202, Manually Opening MOV221 l-FO15A
CR 2003008203, SRV Manual Action Steps in Fire Procedure
CR 2003008237, Emergency Lights and Component Labeling for Manual Actions
CR 2003008238, 002 Migration Through Floor Drains
CR 20038001 32, SSAR Error for Position of 2E 1 -1-F04A
CR 2003800151, Instruments for Manual Actions
CR 2003800152, Sliding Links in SSAR
CR 2003800153, Promat Test Report
CR 2003008250, Communications for Post-Fire SSD
CR 2003800166, Review Fire Procedure Step-34AB-X43-001-2 Steps to Verify Compliance
- with Appendix R.
Design Criteria and Standards
Design Philosophy for Fire Detectors at E. I: Hatch Nuclear Plants, Rev. 2
Completed Surveillance Procedures and Test Records
42SV-FPX-021-OS, Surveillance of Swinging Fire Doors, Task # 1-3367-1 (completed on
01/09/2003)
42SV-FPX-024-OS, Fire Hose Stations, Task # 1-3359-1 (completed on 06/2712003)j
-42SV-FPX-030-OS, Fire Emergency Self Contained Breathing Apparatus Inspection and Test,'-
Task # 1-4200-3 (completed on 07/07/2003)
42SV-FPX-032-OS, Automatic Sliding Fire Door Surveillance, Task # 1-3361-2 (completed on
08/13/2002
Promatec Technologies Installation Inspection Report for Fire Area 2104. MWO 2-98-00881.
Record 09367-2289, dated 09/03/1998
Technical ManualsNendor Information
Dow Corning Fire Endurance Test on Penetration Seal Systems in Precast Concrete F
Using Silicone Elastomers, dated 10/28/1975
Dow Corning 561 Silicone Transformer Fluid Technical Manual,10-453-97, dated 1997
S-80393, Mesker Instructions for Installing d&H 'Pyromatic" Automatic Sliding Fire Door Closer
S-27874B, General Electric Instruction Book GEK-26501, Liquid-Filled Secondary Unit
Substation Transformers, Rev. 2
Attachment
'1-
S-52429A, Bisco, Fire Rated Penetration Seal Qualification Data, dated 08/16/1990
S-52480, Factory Mutual, Fire Rated Penetration Seal Qualification Data-Chemtrol Design FC-
225, dated 08/31/1990
S-54875B, Promatec, Fire Barriers-Unit 2 East Cableway, Rev. 2
Omega Point Laboratories, SR90-005, Three Hour Wall Test, dated 06/06/1990
Promatec Technologies Inc., PS1-001, Issue 1, General Construction Details, dated 07/21/1998
Promatec Technologies Inc., IP-2031, Installation Inspection for Promat's Three Hour Solid
Wall/Ceiling Protection System, Issue C, dated 06/16/1998
System Information Document No. Sl-LP-01401-03, Main Steam and Low Low Set System,
dated 4/3/2000
Applicable Codes and Standards
ANSI N45.2.11-1974, Quality Assurance Requirements for the Design of Nuclear Power Plants
NFPA 12, Standard for Carbon Dioxide Systems,'1973 Edition.
NFPA 13, Standard for the Installation of Sprinkler Systems, 1976 Edition.
NFPA 14, Standard for the Installation of Standpipe and Hose Systems, 1974 Edition.
NFPA 20, Standard for the Installation of Centrifugal Fire Pumps, 1973 Edition.
NFPA 72D, Standard for the Installation, Maintenance, and Use of Proprietary Protection
Signaling Systems, 1975 Edition.
NFPA 72E, Standard on Automatic Fire Detectors, 1974 Edition
NFPA 80, Standard on Fire Doors and Windows, 1975 Edition.
NUREG-1552, Supplement 1, Fire Barrier Penetration Seals in Nuclear Power Plants, dated
January 1999
OSHA Standard 29 CFR 1910, Occupational Safety and Health Standards,
Underwriters Laboratory, Fire Resistance Directory, January 1998
Attachment
....
6
Other Documents
Design Change Package 91-009, Retrofill Dielectric Fluid on Unit 2 Transformers, Rev. i
Fire Protection Inspection Reports for the period 2001-2002
Fire Service Qualification Training, FP-LP-10003, Fire Fighter Safety, dated 01/14/2002
Fire Service Qualification Training, FP-LP-1 0004, Fire Fighter Personal Protective Equipment,
dated 01/14/2002
Fire Service Qualification Training, FP-LP-10014, Fire Streams, dated 01/22/2002
Fire Service Qualification Training, FP-LP-10018, Fire Fighting Principles and Practices, dated
01/22/2002
Hatch Response to NRC Information Notice 1999-05, Inadvertent Discharge of Carbon Dioxide
Fire Protection System and Gas Migration, dated 05/04/1999
Hatch Response to NRC Information Notice 2002-24, Potential Problems with Heat Collectors
on Fire Protection Sprinklers, dated 09/20/2002
1OCFR21-001, ELECTRAK Corporation, Software Error within TRAK2000 Cable Management
and Appendix R Analysis System, dated 03/07/2003
U. S. Consumer Product Safety Commission, Invensys Building Systems Announce Recall of
Siebe Actuators in Building Fire/Smoke Dampers, dated 10/02/2002
Pre-fire Plan A-43965, Power-Block Areas Methodology, Rev. 0
Pre-fire Plan A-43966, Fire Area 2404, Diesel Generator Building Switchgear Rsoin 2E, Rev. 2
Pre-fire Plan A-43966, Fire Area 2408, Diesel Generator Building Switchgear Room 2F, Rev. 2
Pre-fire Plan A-43965, Fire Area 2016, W 600V Switchgear Room 2C, Rev. 4
License Basis Documents
Hatch UFSAR Section 3.4, Water Level Flood Design, Rev. 20
Hatch UFSAR Section 9.1-A, Fire Protection Plan, Rev. 18C
Hatch UFSAR Section 17.2, Quality Assurance During the Operations Phase, Rev.'20B
Hatch Fire Hazards Analysis, Appendix B, Fire Protection Equipment Operating and
Attachment
7
Surveillance Requirements, Rev'. 12B
Hatch Fire Hazards Analysis, Appendix H, Application of National Fire Protection Association
Codes, Rev. 12B
Hatch SER dated April 18, 1994
Safe Shutdown Analysis Report for E.I. Hatch Nuclear Plant Units I and 2, Rev. 26
Fire Hazards Analysis for E. 1. Hatch Nuclear Plan't Units
and 2, Rev.18C, dated 7/00.
NRC Safety Evaluation Report dated 0110211987; Re: Exemption from the requirements of
Appendix R to 1 0 CFR Part 50 for Hatch Units I and 2 (response to letter dated May 16, 1986).
Letter dated 05/16/86, From L. T. Guewa (Georgia Power) to D. Muller, NRCINRR; Re: Edwin I
Hatch Nuclear Plant Units I and 2 10 CFR 50.48 and Appendix R Exemption Requests
Design Change Request Documents
DCR No. 91-1 34, SRV Backup Actuation via' Pressure Transmitter Signals, Revision 0.
Drawing No. H-26000, Nuclear Boiler System P&ID, Sheet 1, Revision 39
Drawing No. H-27403, Automatic Depressurization System 2B21C Elementary Diagram, Sheet
6 of 6, Revision 2
Drawing No. H-27472, Automatic Depressurization System 2B21C Elementary Diagram, Sheet
3 of 6, Revision 2
Drawing No. H-27473, Automatic Depressurization System 2B21C Elementary Diagram, Sheet
4 of 6, Revision 2
Drawing
No.
H-24427,
Elementary
Diagram,
System
2A70
Sheet
27
of
35,
Revision
3
Drawing No. H-24428, Elementary Diagram, AtTS System 2A70 Sheet 28 of 35, Revision 3
Drawing No. H-24429, Elementary Diagram, ATTS System 2A70 Sheet 29 of 35, Revision 5
Drawing No. H-24430, Elementary Diagram, ATTS System 2A70 Sheet 30 of 35, Revision 3
Drawing No. H-24431, Elementary Diagram, ATTS System 2A70 Sheet 31 of 35, Revision 3
Drawing No. H-24432, Elementary Diagram, ATTS System 2A70 Sheet 32 of 35, Revision 6
Attachment
44.
&
8
i
. . ..
i
. .i
i
i
.
i
. .
I
ii
I
I
i
Attachment