E-mail from H. Miller of USNRC to Various, Regarding Issuance of the Salem and Hope Creek Work Environment LetterML060670251 |
Person / Time |
---|
Site: |
Salem, Hope Creek |
---|
Issue date: |
07/30/2004 |
---|
From: |
Miller H NRC Region 1 |
---|
To: |
Anderson C, Barkley R, Blough A, Javier Brand, Arthur Burritt, Paul Cataldo, Leonard Cline, Cook W, Cox M, Dempsey D, Glenn Dentel, Eselgroth P, Florek D, Giles M, Hansell S, Haverkamp T, Keith Heater, Hernandez J, Jeffrey Herrera, Felicia Hinson, Thomas Hipschman, Hunegs G, Todd Jackson, Jaxheimer F, Jenison K, Dante Johnson, Rebecca Junod, Silas Kennedy, David Kern, Knutson E, Kenneth Kolaczyk, Linda Larche, Long C, Kevin Mangan, Marshfield M, Martin R, Brian Mcdermott, O'Daniell C, O'Hara J, Amar Patel, Manan Patel, David Pelton, Neil Perry, Raymond W, Veronica Rodriguez, Schneider M, Daniel Schroeder, Sarah Shaffer, Shanbaky M, Beth Sienel, Casey Smith, Galen Smith, Snell M, Roxanne Summers, Doug Tifft, James Trapp, Venuto K, Christopher Welch, Blake Welling NRC Region 1 |
---|
References |
---|
FOIA/PA-2005-0194 |
Download: ML060670251 (2) |
|
|
---|
Category:E-Mail
MONTHYEARML24016A1612024-01-10010 January 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms - Two Atlantic Sturgeon 1/9/2024 ML24002A7222023-12-29029 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - 2023 Annual Report - Inspection of the Circulating Water Intake Structure (Cwis) Trash Rack Bars ML24002A7242023-12-28028 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - Sturgeon 12/28/2023 ML24002A7252023-12-21021 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Shortnose Sturgeon 12/21/23 ML23355A2732023-12-21021 December 2023 NRR E-mail Capture - (External_Sender) PSEG Response to Questions Associated with Supplement to Salem-Hope Creek Eab Reduction LAR ML23346A0962023-12-0606 December 2023 NRR E-mail Capture - Reminder - Final Report - Completion of Required Additional Protocol (AP) Information in Accordance with the U.S. - IAEA Treaty Obligations ML23311A0792023-11-0101 November 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Atlantic Sturgeon Collected on 10/31/2023 ML23277A0482023-10-0404 October 2023 NRR E-mail Capture - 10/4/2023 Email: Acceptance Review - Hope Creek and Salem 1 and 2 - LAR to Modify Exclusion Area Boundary ML23277A0732023-09-29029 September 2023 NRR E-mail Capture - (External_Sender) 9/29/2023 Email from PSEG: Supplement to Proposed Amendment to PSEG Master Decommissioning Trust Amendment ML23226A0702023-08-11011 August 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form for Sturgeon Collected on 8/10/2023 ML23226A0732023-08-10010 August 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Submittal of Necropsy Reports Regarding Sea Turtles Collected on 06/12/2022 ML23201A0132023-07-20020 July 2023 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Permanent Extension of Type a and Type C Containment Leak Rate Test Frequencies ML23172A0982023-06-21021 June 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemp'S Ridley Sea Turtle Collected on 06/20/2022 ML23164A2062023-06-13013 June 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemp'S Ridley Sea Turtle Collected on 06/12/2023 ML23163A0442023-06-0606 June 2023 NRR E-mail Capture - (External_Sender) Biological Opinion GAR-2020-02842; FIN Clip Analysis Facilities ML23153A1552023-06-0202 June 2023 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 6/1/2023 ML23151A6582023-05-31031 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms Sturgeon 5/30/2023 ML23137A2632023-05-17017 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms Sturgeon 5/16/2023 ML23135A0102023-05-11011 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report Sturgeon 5/11/2023 ML23129A7892023-05-0909 May 2023 NRR E-mail Capture - Acceptance Review - Hope Creek - Revise Trip and Standby Auto-Start Logic Associated with Safety Related HVAC Trains ML23136B2832023-05-0404 May 2023 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 5/3/2023 ML23122A1982023-05-0202 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms for Atlantic Sturgeon 5/1/2023 ML23122A1672023-05-0202 May 2023 NRR E-mail Capture - Acceptance Review - Hope Creek and Salem 1 and 2 - Revise TS to Delete TS Section 5.5 - Meteorological Tower Location ML23117A2722023-04-17017 April 2023 NRR E-mail Capture - (External_Sender) Salem Generating STATION-INCIDENTAL Take of Atlantic Sturgeon Collected on 04/14/2023 ML23079A0032023-03-17017 March 2023 NRR E-mail Capture - Hope Creek, Salem 1 and 2 - Evacuation Time Estimate Review ML23065A0452023-02-23023 February 2023 NRR E-mail Capture - (External_Sender) Salem & Hope Creek Generating STATIONS-ANNUAL Incidental Take REPORT-STATION & REMP ML23033A0302023-02-0808 February 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report Sturgeon 1/24/2023 ML23010A2882023-01-10010 January 2023 NRR E-mail Capture - (External_Sender) Salem Generating STATION-INCIDENTAL Take of Atlantic Sturgeon Collected on 01/09/2023 ML23003A2412023-01-0303 January 2023 NRR E-mail Capture - Final Nvib RAI - Salem Unit 2 Relief Request S2-I4R-211, Fourth Inservice Inspection (ISI) Interval Limited Examinations ML22357A0102022-12-21021 December 2022 NRR E-mail Capture - Final Nphp RAI - Salem Unit 2 Relief Request S2-I4R-211, Fourth Inservice Inspection (ISI) Interval Limited Examinations ML23003A2402022-12-21021 December 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form for Atlantic Sturgeon Collected on 12/20/2022 ML23003A2392022-12-20020 December 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms for Atlantic Sturgeons Collected 12/19/2022 ML22333A9022022-11-29029 November 2022 NRR E-mail Capture - Final Iolb RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22291A3702022-10-18018 October 2022 NRR E-mail Capture - Acceptance Review - Salem 2 - Relief Request Associated with the Fourth Inservice Inspection (ISI) Interval Limited Examinations (L-2022-LLR-0066) ML22290A2202022-10-17017 October 2022 NRR E-mail Capture - Final RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22285A1562022-10-12012 October 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report Atlantic Sturgeon 10/11/2022 (Bottom Trawl) ML22280A1302022-10-0707 October 2022 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report - Sturgeon 10/06/2022 ML22269A4822022-09-26026 September 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report: Kemp'S Ridley Sea Turtle 09/23/2022 ML22269A0352022-09-23023 September 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report: Kemp'S Ridley Sea Turtle 09/22/2022 ML22265A1512022-09-22022 September 2022 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Relocate TS Requirements for Reactor Head Vents to TRM ML22286A2062022-09-14014 September 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report: Kemp'S Ridley Sea Turtle 09/13/2022 ML22244A0422022-09-0101 September 2022 NRR E-mail Capture - Acceptance Review - Salem 2 - Revise and Relocate Reactor Coolant System PT Limits and Pops Limits to PTLR ML22244A1192022-09-0101 September 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report: Kemp'S Ridley Sea Turtle 08/31/2022 ML22206A0262022-07-25025 July 2022 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22206A1032022-07-22022 July 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report: Kemp'S Ridley Sea Turtle 07/21/2022 ML22194A0522022-07-13013 July 2022 NRR E-mail Capture - Acceptance Review - Hope Creek, Salem 1 and 2 - Relocate Staff Qualification Requirements to Licensee Quality Assurance Topical Report ML22188A0762022-07-0707 July 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report: Kemp'S Ridley Sea Turtle 07/06/2022 ML22187A1482022-07-0606 July 2022 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection - Sturgeon 07/05/2022 ML22199A2432022-06-29029 June 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report: Kemp'S Ridley Sea Turtle 06/28/2022 ML22129A0682022-05-0505 May 2022 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report - 2 Sturgeon 05/04/2022 2024-01-10
[Table view] |
Text
, gr wman - Re: Fwd: Issuance of the Salem and Hope Creek Work Environment Letter B.ZUBi.=sBX _ z ,& _
I Page 1 I From: Hubert J. Miller V To: A. Randolph Blough; Amanda Rancourt; Amar Patel; Anne Ford; Arthur Burritt; Beth Sienel; Blake Welling; Brian Fuller; Brian McDermott; Christopher Long; Christopher Welch; Cliff Anderson; Craig Smith; Cynthia O'Daniell; Daniel Schroeder; Dante Johnson; David Kerr; David Pelton; Donald Florek; Douglas Dempsey; Douglas Tifft; Ed Knutson; Ellen Bartels; Felicia Hinson; Frederick Jaxheimer; Galen Smith; Glenn Dentel; Gordon Hunegs; James Trapp; Javier Brand; Jeffrey Herrera; Joe O'Hara; John Richmond; Jorge Hernandez; Justine DeVries; Kathleen Kolek; Kathy Venuto; Keith Heater; Kenneth Jenison; Kenneth Kolaczyk; Kevin Mangan; Leonard Cline; Linda Larche; Manan Patel; Mark Cox; Mark Giles; Mark Marshfield; Max Schneider; Michelle Snell; Mohamed Shanbaky; Neil Perry; Patricia Sauder; Paul Cataldo; Pete Eselgroth; Peter Habighorst; Rebecca Junod; Richard Barkley; Robert Berryman; Robert Summers; Rosemary Martin; Samuel Hansell; Sandra Schmitt; Shani Lewis; Shannine DiMora; Sheryl Farrell; Shriram Iyer; Silas Kennedy; Steve Shaffer; Sue Nelson; Thomas Hipschman;: Tina Newgent; Todd Jackson; Trisha Haverkamp; Veronica Rodriguez; William Cook; William Raymond Date: 7/30/04 5:21PM
Subject:
Re: Fwd: Issuance of the Salem and Hope Creek Work Environment Letter Please, let me add to Randy's note.
Issuance of our letter today is but one small step at the end of a very long process - one that required an enormous amount of hard work by many people spanning numerous branches, divisions and offices.
While much work remains to be done to followup on PSEG improvement efforts, we should all take pride in what we produced as a team.
We have made a real difference to safety in this effort.
Thank you for the competence and hard work required to reach this point.
Hub
>>> A. Randolph Blough 07/30/04 04:35PM >>>
today we issued our final results of the SCWE review at Salem/Hope Creek. As you know, our 'interim results' had been issued in January.
Much work remains to be done, both by the licensee to address the issues and by us to evaluate their efforts.
Nonetheless, this is a signficant step in an NRC activity that has already had high impact toward improving safety, and i am very proud of the fine work by many staff members (too numerous to mention individually right now) to get us to this point.
attached is the letter, as well as our comm plan . Some excerpts of the comm plan's Q&As are pasted below.
regards, randy (P.S> on another subject, I'm looking forward to the mid-cycle assessments next week, and appreciate all the fine teamwork to get in-field inspections, the reports and assessment documents for all plants done with high quality and safety focus.)
- Excerpts about Salem/ hope creek SCWE follow:
In the letter, the NRC noted that no serious safety violations were identified during the review.
Nonetheless, there were numerous indications of weaknesses in corrective actions and management efforts to establish an environment where employees were consistently willing to raise safely concerns.
Weaknesses in leadership and management approaches led to a perception between some staff and managers that the company had emphasized production to the point that negatively impacts handling of emergent equipment issues and associated operational decision making. Management has not been C, 1lR/
Mc3regor...
Bowman - R..wa: assuance of the Salem ania i6pe creek work Erivir6nment Letter 1-
.11-1-11111 .....-
... ---_ -.......... p-0 consistent in its support of station staff identifying concerns and providing alternate views. We also found examples of unresolved conflict and poor communication between management and staff, as well as underlying staff and management frustration with poor equipment reliability. The equipment issues stemmed, in part, from weaknesses in implementation of station processes, such as work management and corrective action.
Several licensee assessments, including on conducted in response to our January letter, had very similar findings.
In their June 25, 2004, letter, PSEG committed to provide quarterly work environment metrics, to conduct periodic cultural assessments for the next several years, and to a meeting with the NRC during the second quarter of 2005. In a July 27, 2004, phone call with the PSEG CNO, the NRC discussed obtained some commitments to add'l PSEG actions.additional actions to enhance these commitments. All of the requested actions were agreed to during the phone call. The NRC also requested that PSEG discuss their perspective on the role and function of QA; procedure adherence and other elements cf human performance; and the quality of engineering products which support operational decision making during the meeting. The second action was to request FPSEG to inform NRC of significant changes to their action plans on a quarterly basis. The third action was for PSEG to obtain a peer assessment to evaluate the effectiveness of their improvement efforts for work environment, corrective action, and wtork management issues at Salem and Hope Creek.
The NRC will continue to closely monitor PSEG performance and their efforts to improve the work environment. Specific plans for inspections and related oversight activities will be provided in our Reactor Oversight Program Mid-Cycle Assessment letter to be issued in several weeks.
CC: A. Randolph Blough; Adam Ziedonis; Alexander Velazquez-Lozada; Andrea Kock; Anna Buseman-Williams; Anne Passarelli; Art Howell; beh; Brett Rini; Brian Holian; Brice Bickett; Bruce Boger; Carey Colantoni; Carl Mohrwinkel; Charles Casto; Chris Miller; Christopher Hunter; Clare Goodman; Cornelius Holden; Cynthia Carpenter; Cynthia Pederson; Daniel Collins; Daniel Holody; Daniel Orr; David Lew; David Vito; Doug Coe; Dwight Chamberlain; Eric Leeds; Ernest Wilson; Eugene Cobey; Fiona Tobler; Frank Costello; Gail Good; George Malone; George Pangbum; Glenn Miller; Gregory Bowman; Harold Christensen; James Andersen; James Clifford; James Linville; James Wiggins; Jason Flemming; Jeffrey Teator; Jennifer Bobiak; John Grobe; John Rogge; John White; Joseph Schoppy; Josephine Talieri; jtwl; Judith Royal; Julius Persensky; Laura Limata; Lauren Quinones; Lawrence Doerflein; Leanne Harrison; Leonard Wert; Lisamarie Jarriel; Marc Ferdas; Mark Satorius; Mel Gray; Nathan Sanfilippo; Nicole Sieller; Patrick Hiland; Raymond Lorson; Richard Conte; Richard Crlenjak; Richard Laufer; Ronald Bellamy; Ronald Cureton; Roy Caniano; Samuel Collins; Scott Barber; Steven Reynolds; Stuart Richards; Theodore Wingfield; Tomy Nazario; Tracy Walker; Victor McCree; W Lanning; Wayne Lanning