ML040050087

From kanterella
Revision as of 22:58, 19 March 2020 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Memo, Fax Transmission, Draft Request for Additional Information
ML040050087
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 12/22/2002
From: Nerses V
NRC/NRR/DLPM/LPD1
To: Darrell Roberts
NRC/NRR/DLPM/LPD1
References
TAC MC0635
Download: ML040050087 (2)


Text

December 22, 2003 MEMORANDUM TO: Darrell J. Roberts, Acting Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Victor Nerses, Sr. Project Manager, Section 2 Project Directorate I /RA/

Division of Licensing Project Management Office of Nuclear Reactor Regulation

SUBJECT:

SEABROOK STATION, UNIT NO. 1, FACSIMILE TRANSMISSION, DRAFT REQUEST FOR ADDITIONAL INFORMATION (TAC NO.

MC0635)

The attached draft RAI was transmitted by facsimile on December 22, 2003, to Mr. Mike OKeefe of FPL Energy Seabrook, LLC (the licensee). This draft RAI was transmitted to facilitate the technical review being conducted by NRR staff. The RAI was related to the licensees August 25, 2003, submittal regarding the installation of a non-safety-related supplemental emergency power system. Review of the RAI would allow the licensee to determine and agree upon a schedule to respond to the RAI. This memorandum and the attachment do not convey or represent an NRC staff position regarding the licensees request.

Docket No. 50-443

Attachment:

Draft RAI

December 22, 2003 MEMORANDUM TO: Darrell J. Roberts, Acting Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Victor Nerses, Sr. Project Manager, Section 2 Project Directorate I /RA/

Division of Licensing Project Management Office of Nuclear Reactor Regulation

SUBJECT:

SEABROOK STATION, UNIT NO. 1, FACSIMILE TRANSMISSION, DRAFT REQUEST FOR ADDITIONAL INFORMATION (TAC NO.

MC0635)

The attached draft RAI was transmitted by facsimile on December 22, 2003, to Mr. Mike OKeefe of FPL Energy Seabrook, LLC (the licensee). This draft RAI was transmitted to facilitate the technical review being conducted by NRR staff. The RAI was related to the licensees August 25, 2003, submittal regarding the installation of a non-safety-related supplemental emergency power system. Review of the RAI would allow the licensee to determine and agree upon a schedule to respond to the RAI. This memorandum and the attachment do not convey or represent an NRC staff position regarding the licensees request.

Docket No. 50-443

Attachment:

Draft RAI DISTRIBUTION PUBLIC J. Clifford V. Nerses M. McConnell PDI-2 Reading Accession Number: ML040050087 *memo form Jenkins OFFICE PDI-2/PM EEIB/SC*

NAME VNerses RJenkins DATE 12/22/03 12/11/03 OFFICIAL RECORD COPY

DRAFT REQUEST FOR ADDITIONAL INFORMATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION FACILITY OPERATING LICENSE NO. NPF-86 FPL ENERGY SEABROOK, LLC SEABROOK STATION DOCKET NO. 50-443 TAC NO. MC0635

!. If a full-load rejection test is performed at power, describe the typical and worst-case voltage transients on the 4160V safety busses as a result of the full-load rejection.

2. Please provide a one-line diagram of the proposed plant configuration (i.e., with the supplemental emergency power system (SEPS) installed).
3. Describe the compensatory measures that will be implemented when the emergency diesel generator (EDG) is removed from service for maintenance utilizing the 14-day extended allowed outage time (AOT).
4. If at any time during the extended EDG AOT the SEPS was to become inoperable, what course of action would be taken and how will the SEPS be returned to operable status (i.e., verified operable)?