ML18017A164

From kanterella
Revision as of 03:09, 8 March 2020 by StriderTol (talk | contribs) (StriderTol Bot change)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

NRR E-mail Capture - Acceptance Review for EPID L-2017-LLA-0433 LAR TSTF-551 Status Accepted
ML18017A164
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 01/17/2018
From: John Klos
Plant Licensing Branch IV
To: Linda Williams
Energy Northwest
References
L-2017-LLA-0433
Download: ML18017A164 (3)


Text

NRR-DMPSPEm Resource From: Klos, John Sent: Wednesday, January 17, 2018 7:56 AM To: 'Williams, Lisa L.'

Cc: Klos, John

Subject:

Acceptance review for EPID L-2017-LLA-0433 LAR TSTF-551 Status accepted

Lisa, By letter dated December 12, 2017, Energy Northwest (the licensee), submitted a license amendment for Columbia Generating Station (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML17346B280. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this license amendment.

The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review.

The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required.

This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 150 hours6.25 days <br />0.893 weeks <br />0.205 months <br /> to complete. The NRC staff expects to complete this review one year from the date of submittal, December 12, 2018. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, and unanticipated addition of scope to the review. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me at the contact information below.

1

John Klos DORL Callaway, Columbia Project Manager U.S. NRC, Office of Nuclear Reactor Regulation, Division of Operating Reactor Licensing, O9D09 NRC/NRR/DORL/LPL4, MS O9E3 Washington, DC 20555-0001 301.415.5136, 301.415.2102 (fax)

John.Klos@NRC.gov 2

Hearing Identifier: NRR_DMPS Email Number: 96 Mail Envelope Properties (CY4PR09MB1447EF8CBC54365FE9E22D46E3E90)

Subject:

Acceptance review for EPID L-2017-LLA-0433 LAR TSTF-551 Status accepted Sent Date: 1/17/2018 7:55:47 AM Received Date: 1/17/2018 7:55:48 AM From: Klos, John Created By: John.Klos@nrc.gov Recipients:

"Klos, John" <John.Klos@nrc.gov>

Tracking Status: None

"'Williams, Lisa L.'" <llwilliams@energy-northwest.com>

Tracking Status: None Post Office: CY4PR09MB1447.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3508 1/17/2018 7:55:48 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: