Letter Sequence RAI |
---|
EPID:L-2020-LLL-0031, Independent Spent Fuel Storage Installation - 2019 Annual Radiological Environmental Operating Report (Open) |
|
|
|
---|
Category:E-Mail
MONTHYEARML24296B1852024-10-16016 October 2024 NRR E-mail Capture - Final - Request for Additional Information - Columbia - Relief Request for Fourth Ten-Year Interval Inservice Testing - EPID: L-2024-LLR-0039 ML24291A1072024-10-16016 October 2024 NRR E-mail Capture - LIC-109 Acceptance Review - Columbia Generating Station - Application to Revise TS to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements - EPID L-2024-LLA-0132 ML24215A3672024-08-0101 August 2024 NRR E-mail Capture - Final Request for Additional Information - Columbia Generating Station - License Amendment Request to Revise Emergency Plan - EPID L-2024-LLA-0011 ML24183A2392024-07-0101 July 2024 NRR E-mail Capture - LIC-109 Acceptance - Columbia Generating Station - Relief Request for the Fourth Ten-Year Interval Inservice Testing - EPID L-2024-LLR-0039 ML24169A0402024-06-14014 June 2024 NRR E-mail Capture - Final Request for Additional Information - Columbia Generating Station (Columbia) - Relief Requests for the Fifth Ten-Year Interval Inservice Testing - EPIDs (L-2024-LLR-007 Through 0013) ML24103A2022024-04-0909 April 2024 EN 57068 - Transco Products Inc Part 21 Initial Notification of Unverified Critical Characteristics of Darmatt KM-1 Flat Board ML24060A1022024-02-28028 February 2024 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2023 Biological Monitoring Report ML24053A0092024-02-21021 February 2024 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of Relief Requests for the Fifth Ten-Year Interval Inservice Testing - EPIDs L-2024-LLR-0007 Through 00013 ML24008A0022024-01-0505 January 2024 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of License Amendment Request for Application to Revise TS to Adopt TSTF-584, Eliminate Automatic RWCU System Isolation on SLC Initiation - EPID L-2023-LLA-0170 ML23278A0042023-10-0404 October 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia - Application to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling - EPID L-2023-LLA-0128 ML23275A0092023-09-29029 September 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia - Application to Revise Tech Specs to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling - EPID: L-2023-LLA-0128 ML23150A2502023-05-26026 May 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia Generating Station - License Amendment Request to Clean-Up Operating License and Appendix a, Technical Specifications - EPID L-2023-LLA-0062 ML23124A2412023-05-0404 May 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia - Application to Revise TS to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position - EPID L-2023-LLA-0063 ML23124A0062023-05-0303 May 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia Generating Station - Application to Revise Tech Specs to Adopt TSTF-541, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling - EPID L-2023-LLA-0063 ML23065A0422023-02-23023 February 2023 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2022 Biological Monitoring Report ML22343A1802022-12-0808 December 2022 February 2023 Emergency Preparedness Program Inspection - Request for Information ML22349A2002022-12-0101 December 2022 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2022 Priority Pollutant Discharge Monitoring Report ML22312A0042022-11-0707 November 2022 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of Fourth 10 Year ISI RR 4ISI-11 - EPID L-2022-LLR-0071 ML22301A1432022-10-28028 October 2022 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - License Amendment Request to Adopt TSTF-505 - EPID L-2022-LLA-0023 ML22256A2002022-09-13013 September 2022 NRR E-mail Capture - Draft - Additional Audit Question - Columbia Generating Station - Regulatory Audit Question for LAR to Revise TS to Adopt TSTF-505, Revision 2 ML22241A0182022-08-26026 August 2022 NRR E-mail Capture - Draft - Additional Audit Question - Columbia Generating Station - Regulatory Audit Question for LAR to Revise TS to Adopt TSTF-505, Revision 2 ML22235A1052022-08-22022 August 2022 August 2022 Emergency Preparedness Exercise Inspection Request for Information ML22210A0072022-07-28028 July 2022 NRR E-mail Capture - Draft - Additional Audit Question - Columbia Generating Station - Regulatory Audit Question for LAR to Revise TS to Adopt TSTF-505, Revision 2 ML22173A0682022-06-17017 June 2022 Email Concurrence on SE Input for Columbia Pltr LAR ML22166A4122022-06-15015 June 2022 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia Generating Station - Application to Revise TS to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling - EPID L-2022-LLA-0081 ML22144A0342022-05-18018 May 2022 NRR E-mail Capture - Draft - Request for Additional Information - Columbia Generating Station - LAR to Change TS 3.4.11 - Reactor Coolant System Pressure and Temperature Limits - EPID L-2021-LLA-0191 ML22075A3392022-03-15015 March 2022 NRR E-mail Capture - Columbia Generating Station - Audit Questions - Regulatory Audit of License Amendment Request to Adopt 50.69 - Categorization Process - EPID L-2021-LLA-0207 ML22067A0132022-03-0707 March 2022 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of License Amendment Request to Adopt TSTF-505, Revision 2, Provide RISK-INFORMED Extended Completion Times - RITSTF Initiative 4b - EPID L-2022-LLA-0023 A002515, NRR E-mail Capture - (External Sender) Energy Northwest Columbia Generating Station 2021 Priority Pollutant Discharge Monitoring Report2022-01-12012 January 2022 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2021 Priority Pollutant Discharge Monitoring Report ML21348A1852021-12-14014 December 2021 NRR E-mail Capture - LIC-109 Acceptance Review - Columbia - License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors - EPID L-2021-LLA-0207 ML21335A0182021-11-30030 November 2021 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of Requested Licensing Action - License Amendment Request to Change TS 3.4.11 Reactor Coolant System Pressure and Temperature Limits - EPID L-2021-LLA-0191 ML21216A0502021-08-0303 August 2021 NRR E-mail Capture - Final - Request for Additional Information - Columbia - License Amendment Request to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO EPID L-2021-LLA-0259 ML21209A9792021-07-28028 July 2021 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - License Amendment Request to Remove License Condition 2.C.(34) and Revise License Condition 2.C.(35) - EPID L-2021-LLA-0074 ML21162A3062021-06-11011 June 2021 NRR E-mail Capture - LIC-109 Acceptance Review - Columbia Generating Station - License Amendment Request to Adopt TSTF-546, Revise APRM Channel Adjustment Surveillance Requirement - EPID L-2021-LLA-0084 ML21137A0012021-05-14014 May 2021 NRR E-mail Capture - LIC-109 Acceptance Review - Columbia Generating Station - License Amendment Request to Remove License Condition 2.C.(34) and Revise License Condition 2.C.(35) - EPID L-2021-LLA-0074 ML21120A1182021-04-30030 April 2021 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - On-Site Cooling System Sediment Disposal Approval Request - EPID L-2020-LLL-0031 ML21109A2762021-04-0808 April 2021 Email Request for Information for Columbia Generating Station'S PIR Inspection_Redacted ML21068A2842021-03-0404 March 2021 2021002 Inservice Inspection (ISI) Request for Information (RFI) ML21036A2932021-02-0404 February 2021 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2020 Biological Monitoring Report ML20357B1502020-12-22022 December 2020 NRR E-mail Capture - LIC-109 Acceptance Review - Columbia - License Amendment Request - Adoption of TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO, Rev. 2 - EPID L-2020-LLA-0259 ML20336A1852020-11-30030 November 2020 NRR E-mail Capture - Final - RAI - Columbia - One -Time Exemption from 10 CFR 73, App B, Sect VI, Subsection C.3.(l)(1) Regarding Annual Force-On-Force Exercises Due to COVID-19 Pandemic - EPID L-2020-LLE-0172 ML20325A0402020-11-19019 November 2020 NRR E-mail Capture - Draft - RAI - Columbia - One -Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force -On-Force Exercises Due to COVID-19 Pandemic - EPID L-2020-LLE-0172 ML20314A0452020-11-0606 November 2020 NMFS to Energy Northwest, Entrainment Study Results for Columbia Generating Station ML20297A3032020-10-22022 October 2020 NRR E-mail Capture - LIC-109 Acceptance Review of License Amendment Request for Columbia - Application to Revise Tech Specs to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements - EPID L-2020-LLA-0212 ML20267A5162020-09-23023 September 2020 NRR E-mail Capture - Columbia Generating Station - Final - Request for Additional Information - Fourth Ten-Year Interval Inservice Inspection (ISI) Program Relief Request 4ISI-09 - EPID L-2020-LLR-0068 ML20265A3242020-09-20020 September 2020 Email 9-20-2020 - Req_ Kick-Off Call Columbia Generating Station RFI Provided for Roll-Back EP Program Inspection (Week of Nov 2 2020) ML20245E2822020-08-31031 August 2020 NRR E-mail Capture - Columbia Additional Request for Additional Information: Exigent License Amendment Request to Extend Technical Specification 3.8.7, Distribution Systems - Operating, Completion Time ML20239A9702020-08-26026 August 2020 NRR E-mail Capture - Columbia Additional Request for Additional Information: Exigent License Amendment Request to Extend Technical Specification 3.8.7, Distribution Systems - Operating, Completion Time ML20149K4362020-05-26026 May 2020 NRR E-mail Capture - Formal RAIs for Columbia (COVID-19) QA Plan Change Surveillance, Request Response by Tuesday June 2, 2020 ML20136A0112020-05-14014 May 2020 NRR E-mail Capture - Acceptance Columbia Relief Request ISI Reactor Pressure Vessel Feedwater Nozzles, 4ISI-09 2024-08-01
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24296B1852024-10-16016 October 2024 NRR E-mail Capture - Final - Request for Additional Information - Columbia - Relief Request for Fourth Ten-Year Interval Inservice Testing - EPID: L-2024-LLR-0039 ML24215A3672024-08-0101 August 2024 NRR E-mail Capture - Final Request for Additional Information - Columbia Generating Station - License Amendment Request to Revise Emergency Plan - EPID L-2024-LLA-0011 ML24169A0402024-06-14014 June 2024 NRR E-mail Capture - Final Request for Additional Information - Columbia Generating Station (Columbia) - Relief Requests for the Fifth Ten-Year Interval Inservice Testing - EPIDs (L-2024-LLR-007 Through 0013) ML24058A0692024-03-14014 March 2024 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Emergency Plan ML24011A1522024-01-10010 January 2024 March 2024 Emergency Preparedness Exercise Inspection-Request for Information ML23110A2642023-04-20020 April 2023 Request for Information License Renewal Phase 2 Inspection ML22343A1802022-12-0808 December 2022 February 2023 Emergency Preparedness Program Inspection - Request for Information ML22301A1432022-10-28028 October 2022 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - License Amendment Request to Adopt TSTF-505 - EPID L-2022-LLA-0023 ML22242A1082022-08-30030 August 2022 Information Request, Information Request, Security IR 2022404 ML22235A1052022-08-22022 August 2022 August 2022 Emergency Preparedness Exercise Inspection Request for Information IR 05000397/20224012022-06-0606 June 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000397/2022401 ML22144A0342022-05-18018 May 2022 NRR E-mail Capture - Draft - Request for Additional Information - Columbia Generating Station - LAR to Change TS 3.4.11 - Reactor Coolant System Pressure and Temperature Limits - EPID L-2021-LLA-0191 ML22041A4572022-02-10010 February 2022 Notification of NRC Design Bases Assurance Inspection (Team) (05000397/2022010) and Request for Information ML21277A3572021-10-12012 October 2021 CGS Brq RFI Letter, Columbia Generating Station - Notification of Inspection (NRC Inspection Report 05000397/2021004) and Request for Information ML21216A0502021-08-0303 August 2021 NRR E-mail Capture - Final - Request for Additional Information - Columbia - License Amendment Request to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO EPID L-2021-LLA-0259 ML21209A9792021-07-28028 July 2021 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - License Amendment Request to Remove License Condition 2.C.(34) and Revise License Condition 2.C.(35) - EPID L-2021-LLA-0074 ML21120A1182021-04-30030 April 2021 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - On-Site Cooling System Sediment Disposal Approval Request - EPID L-2020-LLL-0031 ML21068A2842021-03-0404 March 2021 2021002 Inservice Inspection (ISI) Request for Information (RFI) ML20336A1852020-11-30030 November 2020 NRR E-mail Capture - Final - RAI - Columbia - One -Time Exemption from 10 CFR 73, App B, Sect VI, Subsection C.3.(l)(1) Regarding Annual Force-On-Force Exercises Due to COVID-19 Pandemic - EPID L-2020-LLE-0172 ML20325A0402020-11-19019 November 2020 NRR E-mail Capture - Draft - RAI - Columbia - One -Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force -On-Force Exercises Due to COVID-19 Pandemic - EPID L-2020-LLE-0172 ML20267A5162020-09-23023 September 2020 NRR E-mail Capture - Columbia Generating Station - Final - Request for Additional Information - Fourth Ten-Year Interval Inservice Inspection (ISI) Program Relief Request 4ISI-09 - EPID L-2020-LLR-0068 ML20245E2822020-08-31031 August 2020 NRR E-mail Capture - Columbia Additional Request for Additional Information: Exigent License Amendment Request to Extend Technical Specification 3.8.7, Distribution Systems - Operating, Completion Time ML20239A9702020-08-26026 August 2020 NRR E-mail Capture - Columbia Additional Request for Additional Information: Exigent License Amendment Request to Extend Technical Specification 3.8.7, Distribution Systems - Operating, Completion Time ML20149K4362020-05-26026 May 2020 NRR E-mail Capture - Formal RAIs for Columbia (COVID-19) QA Plan Change Surveillance, Request Response by Tuesday June 2, 2020 ML20112F4572020-04-21021 April 2020 NRR E-mail Capture - Official Release of NRC RAIs for Columbia Covid Exigent Due Friday April 24, 2020 ML20034E6082020-02-0303 February 2020 NRR E-mail Capture - RAI Formal Release Columbia TSTF 563 LAR, 30 Day Response Period Due March 3, 2020 ML20028E1512020-01-27027 January 2020 Notification of Evaluations of Changes, Tests, and Experiments Inspection (Inspection Report 05000397/2020002) and Request for Information ML19267A1842019-09-24024 September 2019 Request for Information for Upcoming Open Phase Condition Inspection at Columbia Generating Station ML19232A2282019-08-20020 August 2019 NRR E-mail Capture - Formal Release of RAIs Ref: Columbia Exigent Amendment - One Electrical RAI, ML19183A4752019-07-0202 July 2019 NRR E-mail Capture - Formal Release of RAIs Ref: Columbia HVAC LAR L-2019-LLA-0034 ML18088A0152018-03-29029 March 2018 Notification of NRC Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/ Staffing/Multi-Unit Dose Assessment Plans (05000397/2018010) and Request for ML17341B0272017-12-0707 December 2017 NRR E-mail Capture - RAI Associated with Columbia Amendment Request Revise Tech Spec 5.5.12 for Permanent Extension of Type a and Type C Containment Testing Frequencies for MF9469, EPID: L-2017-LLA-0197, ILRT, LLRT LAR - New RAI Response Da ML17292A0572017-10-18018 October 2017 NRR E-mail Capture - New RWCU RAI Due Date Now November 24, 2017 ML17249A6882017-09-0606 September 2017 NRR E-mail Capture - RAIs for Columbia Relief Request RAI (MF8925), 3ISI-19 ML17205A3152017-07-20020 July 2017 Notification of Evaluations of Changes, Tests, and Experiments Inspection (05000397/2017004) and Request for Information ML17193A2192017-07-12012 July 2017 NRR E-mail Capture - Columbia RWCU LAR MF8318, Formal Release of RAIs ML17144A1702017-05-24024 May 2017 NRR E-mail Capture - NRC RAIs for Columbia Relief Request MF8922, 3ISI-16 ML17047A7492017-02-16016 February 2017 Response to Request for Additional Information, Columbia Mur LAR Evib Rais ML17006A0902017-01-0404 January 2017 NRR E-mail Capture - Non Proprietary Request for Additional Information Regarding Columbia Mur Power Uprate ML17006A0922017-01-0404 January 2017 NRR E-mail Capture - Eicb RAIs for Columbia Mur ML16356A1382016-12-21021 December 2016 NRR E-mail Capture - Columbia Mur LAR Evib RAIs Non - Proprietary Version - Revise Operating License and Technical Specifications for Measurement Uncertainty Recapture Power Uprate ML16342C4322016-12-0707 December 2016 NRR E-mail Capture - Columbia Measurement Uncertainty Recapture Power Uprate LAR Rais: Human Performance: MF8060, Formal Release for Response on Monday January 9, 2017 ML16327A1842016-11-22022 November 2016 NRR E-mail Capture - Non Proprietary Request for Additional Information Regarding Columbia Mur Power Uprate ML16323A1192016-11-16016 November 2016 NRR E-mail Capture - Eicb RAIs for Columbia Mur ML16218A3902016-08-0808 August 2016 Supplemental Information Needed for Acceptance of Requested Licensing Action, Request for Measurement Uncertainty Recapture (Mur) Power Uprate (from 3486 Mwt to 3544 Mwt) ML16194A3702016-07-11011 July 2016 Notification of NRC Triennial Heat Sink Performance Inspection 05000397/2016003 and Request for Information ML16069A3592016-03-0909 March 2016 NRR E-mail Capture - Second Round Rais: Columbia MF6042 LAR TSTF-425 ML16061A5542016-03-0101 March 2016 Notification of NRC Design Bases Inspection (05000397/2016007) and Initial Request for Information ML16061A5662016-03-0101 March 2016 Notification of Design Bases Inspection (Programs)(Inspection Report 05000397/2016008) and Initial Request for Information ML15254A2572015-09-16016 September 2015 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.1 Seismic Reevaluations 2024-08-01
[Table view] |
Text
From: Chawla, Mahesh Sent: Friday, April 30, 2021 10:24 AM To: 'Garcia, Richard M.'
Cc: Dixon-Herrity, Jennifer; Schwartzman, Adam; Tammara, Rao; Arlene, Briana; Palmrose, Donald; Rikhoff, Jeffrey; Guo, Lifeng; Martinez, Nancy; Hoffman, Robert; Folk, Kevin; Elliott, Robert; Rakovan, Lance; McKenney, Chris; Erwin, Kenneth; Greene, Natasha; Josey, Jeffrey; Hernandez, Nick; Merker, Lindsay
Subject:
FINAL - Request for Additional Information - Columbia Generating Station -
On-Site Cooling System Sediment Disposal Approval Request - EPID L-2020-LLL-0031 Attachments: Columbia Generating Station 10 CFR 20.2002_Final RAIs.docx
Dear Mr. Garcia,
On December 21, 2020 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML20356A172), Energy Northwest (the licensee) submitted to the U.S. Nuclear Regulatory Commission (NRC) a 10 CFR 20.2002 request for approval of onsite disposal of sediments from the circulating water system cooling towers and standby service water system spray ponds at the Columbia Generating Station. In accordance with 10 CFR 20.2002(b), each application should include an analysis and evaluation of pertinent information on the nature of the environment. The NRC staff has reviewed Energy Northwests submittal and determined that additional information is required for the NRC to complete its safety and environmental reviews.
On April 22, 2021, we conducted a clarification teleconference between the NRC staff and the representatives of Energy Northwest to get further clarifications needed for the subject RAIs.
Based on the discussions during the call, it was agreed by the NRC staff to revise the information requested in the RAI SHH-3. The revised final RAIs are provided as an attachment to this email. After the clarification teleconference, you called back and requested 60 calendar days to provide the requested information on the docket. Therefore, please provide the response to the RAIs on the docket within 60 calendar days of the receipt of this email.
Thanking you, Sincerely, Mahesh Chawla, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission ph: 301-415-8371 ODORL/LPL4/PM DORL/LPL4/BC
JDixon-NMChawla Herrity D4/30/2021 4/30/2021
Hearing Identifier: NRR_DRMA Email Number: 1163 Mail Envelope Properties (MN2PR09MB51134254DE6C3CCD49B06A98F15E9)
Subject:
FINAL - Request for Additional Information - Columbia Generating Station -
On-Site Cooling System Sediment Disposal Approval Request - EPID L-2020-LLL-0031 Sent Date: 4/30/2021 10:23:58 AM Received Date: 4/30/2021 10:23:58 AM From: Chawla, Mahesh Created By: Mahesh.Chawla@nrc.gov Recipients:
"Dixon-Herrity, Jennifer" <Jennifer.Dixon-Herrity@nrc.gov>
Tracking Status: None "Schwartzman, Adam" <Adam.Schwartzman@nrc.gov>
Tracking Status: None "Tammara, Rao" <Seshagiri.Tammara@nrc.gov>
Tracking Status: None "Arlene, Briana" <briana.arlene@nrc.gov>
Tracking Status: None "Palmrose, Donald" <Donald.Palmrose@nrc.gov>
Tracking Status: None "Rikhoff, Jeffrey" <Jeffrey.Rikhoff@nrc.gov>
Tracking Status: None "Guo, Lifeng" <Lifeng.Guo@nrc.gov>
Tracking Status: None "Martinez, Nancy" <Nancy.Martinez@nrc.gov>
Tracking Status: None "Hoffman, Robert" <Robert.Hoffman@nrc.gov>
Tracking Status: None "Folk, Kevin" <Kevin.Folk@nrc.gov>
Tracking Status: None "Elliott, Robert" <Robert.Elliott@nrc.gov>
Tracking Status: None "Rakovan, Lance" <Lance.Rakovan@nrc.gov>
Tracking Status: None "McKenney, Chris" <Christepher.McKenney@nrc.gov>
Tracking Status: None "Erwin, Kenneth" <Kenneth.Erwin@nrc.gov>
Tracking Status: None "Greene, Natasha" <Natasha.Greene@nrc.gov>
Tracking Status: None "Josey, Jeffrey" <Jeffrey.Josey@nrc.gov>
Tracking Status: None "Hernandez, Nick" <Nicholas.Hernandez@nrc.gov>
Tracking Status: None "Merker, Lindsay" <lindsay.merker@nrc.gov>
Tracking Status: None
"'Garcia, Richard M.'" <rmgarcia@energy-northwest.com>
Tracking Status: None Post Office: MN2PR09MB5113.namprd09.prod.outlook.com
Files Size Date & Time MESSAGE 1739 4/30/2021 10:23:58 AM Columbia Generating Station 10 CFR 20.2002_Final RAIs.docx 52153 Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Columbia Generating Station 10 CFR 20.2002 Request for Additional Information (RAIs)
On December 21, 2020, Energy Northwest submitted to the U.S. Nuclear Regulatory Commission (NRC) a 10 CFR 20.2002 request for approval of onsite disposal of sediments from the circulating water system cooling towers and standby service water system spray ponds at the Columbia Generating Station. In accordance with 10 CFR 20.2002(b), each application should include an analysis and evaluation of pertinent information on the nature of the environment. The NRC staff has reviewed Energy Northwests submittal and determined that additional information is required for the NRC to complete its safety and environmental reviews.
Historic and Cultural Resources (HCR) Issues The NRC staffs environmental assessment considers a variety of issues related to the impacts from the proposed 10 CFR 20.2002 disposal action, including historical and cultural impacts.
Since this review addresses past, present, and future disposal actions the NRC staff has the following questions regarding historical and cultural considerations that were considered prior to the development of the initial soil disposal area as well as the November 2020 expansion.
HCR-1 Energy Northwests 10 CFR 20.2002 submittal identifies that sediment disposal cell expansion was completed in November 2020. Is the disposal area located in a previously disturbed area or considered an archaeologically sensitive area?
HCR-2 Did Energy Northwest contact or consult with the State Historic Preservation Officer or Federally- or State-recognized tribes regarding the November 2020 disposal cell expansion and any associated ground disturbance? If so, provide a discussion of the consultation(s) conducted.
HCR-3 Did Energy Northwest follow the sites cultural resource protection procedure prior to conducting any ground disturbance of the disposal area? If so, describe the steps taken in accordance with the procedure prior to and when conducting ground disturbing activities of the disposal area.
HCR-4 Did Energy Northwest conduct an archaeological survey of the disposal area prior to conducting ground disturbance? If so, provide a discussion of the survey findings.
Safety and Human Health (SHH) Issues The NRC staff also determined a need for additional details as well as further clarification of statements made in the submittal documents to address technical issues associated with safety and human health-related issues that need to be considered for NRC staff to completely evaluate this alternate disposal request. Specific details regarding the issues of concern and questions whose answers will help to resolve these concerns are provided below.
Issue #1
Background:
The enclosure and supporting attachments do not provide enough details related to the doses to workers associated with disposing of the cooling tower sediments and spray pond sediments in the fenced sediment disposal area and related monitoring activities.
Columbia Generating Station 10 CFR 20.2002 Request for Additional Information (RAIs)
Doses to workers associated with this alternate disposal request are based on an occupational worker scenario with a regulatory limit of 15 mrem/yr. Section 5.1, Sediment Disposal Area Control, notes that the area is only occupied when material is being disposed, during sampling activities, and during the changeout of TLDs and other environmental monitoring activities.
Section 5.5, Radiological Impact Evaluation (Dose Assessment), discusses an approach to dose modeling but does not provide total dose values. Specific details provided also do not differentiate the doses to different types of workers who may be involved with the area.
Regulatory Basis:
This information is needed to ensure that the relevant exposure scenarios and appropriate parameter values are considered when assessing doses associated with this proposed disposal action in accordance with 10 CFR 20.2002.
Path Forward:
SHH-1 Provide specific details describing the different types of workers involved with the activities that occur within the sediment disposal area (i.e., are the workers involved with the disposal actions the same workers involved with the monitoring activities?).
SHH-2 Confirm whether all workers involved with activities occurring within the sediment disposal area qualify as radiation workers under the facilitys radiation protection plan, are members of the public, or a combination of both. If multiple groups are involved, document how each of their doses are calculated.
SHH-3 Provide an assessment of the impacts, including specific doses when available, to members of the public involved with the disposal actions and other operating activities (e.g., monitoring activities) associated with the activities occurring within the Sediment Disposal Area. Include any dose modeling data and results or other references used to evaluate these scenarios.
Issue #2
Background:
The enclosure document and supporting attachment documents do not provide enough detail for NRC staff to gain a complete understanding of the size of the disposal area, the size of the individual disposal cells, the total volume of sediments that have already been deposited in the area, and the volume of sediments that has yet to be disposed.
Multiple sections of the enclosure and attachments submitted to the NRC for review discuss volumes of material associated with this 20.2002 request. Additional details are needed to ensure a clear understanding of which volumes of materials should be considered. Specific sections that need further clarification include:
- 1. Section 1.2, Location - In this section Energy Northwest estimates that approximately 200 cubic yards of total space remains in the two active cells and 1200 cubic yards is available in the future use cell for a total of 1400 cubic yards. Based on an average amount of dry sediment that was disposed from 2010 to 2019, 198 cubic yards per year,
Columbia Generating Station 10 CFR 20.2002 Request for Additional Information (RAIs)
Energy Northwest estimates that this remaining space will be filled in 7 years (198 cubic yards/year X 7 years = 1396 cubic yards).
- 2. Section 5.5.2, Dose Projection Assumptions - This section provides the parameters used for performing the dose modeling. In this section Energy Northwest notes that the total volume of deposited sediment is 2850 cubic yards; 1800 cubic yards of sediment from the cooling tower based on the assumption of 60 cubic yards per year for 30 years and 1050 cubic yards based 35 cubic yards per year for 30 years.
- 3. Section 5.5.2, Dose Projection Assumptions - This section also discusses dimensions of deposited material that was used for modeling, this time using units of meters instead of yards. Although not specifically noted, it appears that Energy Northwest considered identical cylindrical areas of waste with a radius of 15 meters and assumes different depths for the deposited material (1.2 m for the spray pond material and 2 m for the cooling tower material) as a way of performing a more conservative dose assessment.
Regulatory Basis:
This information is needed to ensure that enough details are provided to meet the specific requirements established in 10 CFR 20.2002(b) and (c). This information is also need when evaluating the dose calculations needed to assess the doses (20.2002(d)) associated with this proposed disposal action in accordance with 10 CFR 20.2002.
Path Forward:
SHH-4 Clarify the total area of the sediment disposal area and the volumes of sediment that have previously been disposed of and have yet to be disposed in the sediment disposal area. Is the 3600 ft2 (120 ft X 300 ft) fenced area discussed in the State Environmental Policy Act (SEPA) Environmental Checklist included with Enclosure Attachment 3, the sediment disposal area being considered in this alternate disposal request? If not, provide the area of the sediment disposal area and a reference to these dimensions. Also, based on the information provided in Sections 1.2 and 5.5.2, clarify if the 2850 cubic yards of material includes the 1400 cubic yards of material that has yet to be disposed and if the total volume of material in the sediment disposal area at the time of closure is 2850 cubic yards or 4250 cubic yards (2850 cubic yards + 1400 cubic yards).
SHH-5 Explain why Section 5.5.2, Dose Projection Assumptions, only considers two areas when there are more than two disposal cells. By using separate volumes, does this indicate that the sediments from the cooling towers and the spray ponds remain separate when being placed in the disposal cells (i.e., specific disposal cells for each sediment) or are they mixed within a single disposal cell?
If specific cells are used for each sediment, how many and what are the dimensions of the specific disposal cells? If the sediments are mixed, explain the significance of using a depth of 1.2 m for spray pond sediments and 2 m for cooling tower sediments when performing the dose calculations.
Columbia Generating Station 10 CFR 20.2002 Request for Additional Information (RAIs)
Issue #3
Background:
The enclosure discusses two methods that were used for evaluating doses to workers associated with sediment disposal and environmental monitoring activities in the sediment disposal area. Doses are provided using TLD measurements. These quarterly average doses are reported as mR per standard quarter. Additional details are needed to further understand what quarterly average means. The enclosure also discusses doses that were calculated using RESRAD and Microshield and site-specific parameter values. These values do not appear to have been updated since the original analyses performed in 1995 (i.e., no updated dose analyses were provided). As a result, these doses do not consider the impact from the addition of cooling tower sediments and spray pond sediments that have been added to the sediment disposal area since then.
Section 5.4 indicates that measurements of direct radiation at the sediment disposal pit area are taken using TLD Station 119B as the indicator location and Station 119Ctrl as control location.
According to Figure 4-1 in the 2019 Annual Radiological Environmental Operating Report, the locations of TLD Station 119B and TLD Station 119Ctrl seem to be far away from the sediment disposal area and may not be representative of direct radiation measurement due to the disposal of sediments in the sediment disposal cells. They both seem to be more representative of a background dose. The TLD measurements appear to consider background measurements based on measurements from a control site but no discussion is provided regarding background measurements when calculating doses based on radionuclide concentrations measured in the sediment samples.
Regulatory Basis:
This information is needed to ensure that enough details are provided to meet the specific requirements established in 10 CFR 20.2002(b) and (c). This information is also need when evaluating the dose calculations needed to assess the doses (20.2002(d)) associated with this proposed disposal action in accordance with 10 CFR 20.2002.
Path Forward:
SHH-6 Confirm the process used to establish annual doses based on the measured direct radiation values reported in Table 3, Measurements of direct radiation at the disposal area using TLD Station 119B and TLD Station 119Ctrl and their location relative to the sediment disposal area. What role do the background measurements play and how are net negative values addressed for both the TLD measurements and the radionuclide concentrations measured in the sediment samples? How do these doses compare with the dose values calculated using the individual radionuclide concentrations measured in the sediment samples collected during each disposal and summarized in Table 2 of Section 3.2, Analysis of Sediment, of the enclosure?
SHH-7 Clarify the process used to calculate the quarterly average mean value for the TLD measurement (i.e., the average of 3 months of measurements, the average of 12 months of measurements divided by 4, or some other method).
Columbia Generating Station 10 CFR 20.2002 Request for Additional Information (RAIs)
SHH-8 Without consideration for the TLD control location (TLD Station 119Ctrl), how do the doses associated with the TLD measurements compare with the doses calculated using the radionuclide concentrations measured in the pre-disposal samples?
SHH-9 Considering up-to-date site characteristics for the sediment disposal area and the cumulative impacts from the addition of sediments and radionuclides, provide up-to-date doses to individuals working within the sediment disposal area as well as for current and future reasonably foreseeable land-use scenarios.