From: Mahesh Chawla Sent: Wednesday, October 4, 2023 7:42 PM To: Garcia, Richard M.

Cc: Ravi Grover; Mahmoud Jardaneh; Jennifer Dixon-Herrity; Doug Broaddus

Subject:

LIC-109 Acceptance Review of LAR for Columbia Generating Station -

Application to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling" - EPID:

L-2023-LLA-0128

Dear Mr. Garcia,

Resending to document a revision to the schedule provided in the September 29, 2023, notification (ML23275A009):

By letter dated August 29, 2023 (Agencywide Documents Access and Management System Accession No. ML23241B044), Energy northwest (the licensee) submitted a license amendment request (LAR) for Columbia Generating Station (Columbia). Energy Northwest requests adoption of Technical Specification Task Force (TSTF)-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling. The proposed amendment modifies TS 3.6.2.3, Residual Heat Removal (RHR) Suppression Pool Cooling, to allow two RHR suppression pool cooling subsystems to be inoperable for eight hours.

The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this LAR. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant. Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an application for an amendment to a license (including the TS) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed LAR in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 80 hours9.259259e-4 days <br />0.0222 hours <br />1.322751e-4 weeks <br />3.044e-5 months <br /> to complete. The NRC staff expects to complete this review in approximately 10 months, which is July 31, 2024. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application, and they could change, due to several factors including requests for additional information (RAI), unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me @ 301-415-8371. Thanking you, Sincerely, Mahesh Chawla, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Hearing Identifier: NRR_DRMA Email Number: 2262 Mail Envelope Properties (PH0PR09MB84119FA49B362A08270DC718F1CBA)

Subject:

LIC-109 Acceptance Review of LAR for Columbia Generating Station -

Application to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling - EPID L-2023-LLA-0128 Sent Date: 10/4/2023 7:41:31 PM Received Date: 10/4/2023 7:41:00 PM From: Mahesh Chawla Created By: Mahesh.Chawla@nrc.gov Recipients:

"Ravi Grover" <Ravinder.Grover@nrc.gov>

Tracking Status: None "Mahmoud Jardaneh" <Mahmoud.Jardaneh@nrc.gov>

Tracking Status: None "Jennifer Dixon-Herrity" <Jennifer.Dixon-Herrity@nrc.gov>

Tracking Status: None "Doug Broaddus" <Doug.Broaddus@nrc.gov>

Tracking Status: None "Garcia, Richard M." <rmgarcia@energy-northwest.com>

Tracking Status: None Post Office: PH0PR09MB8411.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3796 10/4/2023 7:41:00 PM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: