IR 05000244/2010004
Download: ML103070529
Text
UNITED NUCLEAR REGULATORY REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406*1415 November 3, 2010 Mr. John T. Carlin, Vice President RE. Ginna Nuclear Power Plant, LLC Constellation Energy Nuclear Group, LLC 1503 Lake Road Ontario, New York 14519 RE. GINNA NUCLEAR POWER PLANT, LLC -NRC INTEGRATED INSPECTION REPORT 05000244/2010004.
Dear Mr. Carlin:
On September 30,2010, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your R E. Ginna Nuclear Power Plant. The enclosed integrated inspection report documents the inspection results, which were discussed on October 12,2010, with Mr. Eric Larson and other members of your staff. The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. This report documents one NRC-identified and one self-revealing finding of very low safety Significance (Green). These findings were determined to be violations of NRC requirements. However, because of the very low safety significance, and because they were entered into your corrective action program, the NRC is treating these findings as non-cited violations (NCVs) consistent with Section 2.3.2 of the NRC Enforcement Policy. If you contest any NCV in this report, you should provide a written response within 30 days of the date of this inspection report with the basis of your denial, to the Nuclear Regulatory Commission, A TIN: Document Control Desk, Washington D.C. 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, D.C. 20555-0001; and the NRC Resident Inspector at RE. Ginna Nuclear Power Plant. In addition, if you disagree with the cross-cutting aspect assigned to any finding in this report, you should provide a response .within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region I, and the NRC Resident Inspector at RE. Ginna Nuclear Power Plant. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice,* a copy of this letter and its enclqsure, and your response (if any) will be available electronically for public inspection in the . .). " .(". NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html(the Public Electronic Reading Room).
Sincerely,Glenn T. Dentel, Chief Projects Branch 1 Division of Reactor Projects Docket No. 50-244 License No. DPR-18
Enclosure:
Inspection Report No. 05000244/2010004 wI
Attachment:
Supplemental Information cc w/encl: Distribution via Listserv J. 2 NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html(the Public Electronic Reading Room).
Sincerely. IRA! Glenn T. Dentel, Chief Projects Branch 1 Division of Reactor Projects Docket No. 50-244 License No. DPR-18 Inspection Report No. 05000244/2010004 wI
Attachment:
Supplemental Information Distribution w/encl: W. Dean. (R10RAMAIL RESOURCE) J. Hawkins, DRP M. Dapas, DRA (R10RAMAIL RESOURCE) N. Floyd, DRP D. Lew. (R10RAMAIL RESOURCE) G. Hunegs, DRP, SRI J. Clifford, (R1 DRPMAIL RESOURCE) L. Casey, DRP, RI D. Roberts, DRS (R1 DRSMAIL RESOURCE) M. Rose, DRP, OA P. Wilson, DRS (R10RSMAIL RESOURCE) D. Bearde, DRS G. Miller, RI RidsNrrPMREGinna Resource G. Dentel, .ROPreportsResource@nrc.gov N. Perry, DRP SUNSI Review Complete: _______(Reviewer's Initials) ML 103070529 DOCUMENT NAME: G:\DRP\BRANCH1\Ginna\Reports\2010-0Q4\Ginna 2010-004.doc After declaring this document "An Official Agency Record" it will be released to the Public. To receive a copy of this document, indicate in the box: "C" =Copy without attachmenVenclosure "E" = Copy with attachmentlenclosure "N" = No copy OFFICE RIIDRP Ilhp RIIDRP I RI/DRP I NAME via NPerry/np GDentellgd phonew/np DATE 11/01/10 11/01/10 11/03/10 OFFICIAL RECORD COpy Docket No.: License No.: Report No.: Licensee: Facility: Location: Dates: Inspectors: Approved by: 1 U.S. NUCLEAR REGULATORY COMMISSION REGION I 50-244 DPR-18 05000244/2010004 Constellation Energy Nuclear Group. LLC R. E. Ginna Nuclear Power Plant. LLC Ontario, New York July 1. 2010 through September 30, 2010 G. Hunegs. Senior Resident Inspector L. Casey. Resident Inspector F. Arner, Senior Reactor Inspector N. Perry. Senior Project Engineer S. Pindale. Senior Reactor Inspector K. Young, Senior Reactor Inspector R. Rolph, Health Physicist Glenn T. Dentel. Chief Projects Branch 1 Division of Reactor Projects Enclosure 2
SUMMARY OF FINDINGS
........................................................................................................
REPORT DETAILS
.................................................................................................................... REACTOR SAFETy ...........................................................................................................
1R01 Adverse Weather Protection ............................................................................. 1R04 Equipment Alignment. ......................................................................................... 1R05 Fire Protection ...................................................................,............................... 1R11 Licensed Operator Requalification Program ...................................................... 1R12 Maintenance Effectiveness ................................................................................ 1R13 Maintenance Risk Assessments and Emergent Work Control .......................... 1R15 Operability Evaluations ................................................................................... 1Ria Plant Modifications ........................................................................................... 1R19 Post-Maintenance Testing ............................................................................... 1R22 Surveillance Testing ........................................................................................ 1EP6 Drill Evaluation
RADIATION SAFETY
....................................................................................................... 2RS01 Radiological Hazard Assessment and Exposure Controls ............................... 2RS02 Occupational ALARA Planning and Controls .................................................. OTHER ACTiViTIES ......................................................................................................... 40A1 Performance Indicator (PI) Verification ............................................................ 40A2 Problem Identification and Resolution .............................................................. 40A3 Followup of Events and Notices of Enforcement Discretion ............................. 40A5 Other Activities ................................................................................................40A6 Meetings, Including Exit.. ................................................................................. ATTACHMENT:
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
...................................................................................................
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
.......................................................
LIST OF DOCUMENTS REVIEWED
............ : ..........................................................................
LIST OF ACRONYMS
- ...... .......................................................................................................Enclosure
- OF [[]]
- FINDIN [[]]
- GS [[]]
- LLC [[(Ginna), Maintenance Risk Assessments and Emergent Work Control, Post-Maintenance Testing. The report covered a three-month period of inspection by resident inspectors and region-based inspectors. Two Green non-cited violations (NCVs) were identified. The significance of most findings is indicated by their color (Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, "Significance Determination Process" (SDP). The cross-cutting aspect for each finding was determined using]]
- NRC 's program for overseeing the safe operation of commercial nuclear power reactors is described in
- NUREG -1649, "Reactor Oversight Process," Revision 4, dated December 2006. Cornerstone: Mitigating Systems Green. The inspectors identified a very low safety significance (Green) non-cited violation (
- 10 CFR 50.65, "Maintenance Rule," paragraph (a)(4), when Ginna did not perform an accurate risk assessment prior to removing the technical support center (
- TSC was less than 1.0E-6. This finding has a cross-cutting aspect in the area of human performance, work control, in that Ginna operators were not fully apprised of the work status of the]]
- XVI , "Corrective Action," was determined based on Ginna's failure to identify that vibration data exceeded the inservice testing (1ST) acceptance criteria for five pumps. On June 30,2009, Ginna identified that the 'B'
ST criteria for the previous four surveillance tests due to vibration data being incorrectly measured and analyzed. Ginna's apparent cause evaluation (ACE) documented that an extent of condition review was completed which identified all the additional components that were unknowingly in the 1ST alert or required action range from May 2008 to June 2009. On August 4, 2010, Ginna tested Enclosure
the 'A' motor-driven auxiliary feedwater (MDAFW) pump and determined that it was in the alert range for inboard bearing vibration. During their analysis, Ginna discovered that during the last comprehensive test in October 2008, the same vibration point was in the
- 1ST [[alert range. This had not been identified during Ginna's previous extent of condition review. Subsequently, Ginna performed another extent of condition review and identified that four other components were outside the vibration acceptance criteria and in the alert range. Ginna's immediate corrective actions included entering this issue into their]]
- ST [[acceptable range. This finding is more than minor because it was repetitive and it affected a number of pumps. The finding is associated with the equipment performance attribute of the Mitigating Systems Comerstone and adversely affected the objective of ensuring the capability of systems that respond to initiating events to prevent undesirable consequences. The inspectors determined that the finding was of very low safety significance (Green) because it was not a design or qualification deficiency, did not represent a loss of safety function, and did not screen as potentially risk significant due to seismic, flooding, or severe weather. This finding has a cross-cutting aspect in the area of problem identification and resolution (PI&R), corrective action program, in that Ginna did not thoroughly evaluate]]
- 1ST program vibration data during their extent of condition review conducted in 2009 as a result of the'S' residual heat removal pump exceeding the 1
- REPORT [[]]
- R.E. Ginna Nuclear Power Plant (Ginna) began the inspection period operating at full rated thermal power and operated at full power for the entire period. 1.
- SAFETY -One sample) External Flood Protection Measures a. Inspection Scope The inspectors performed a review of the external flood preparation and mitigation program. To perform this review, the inspectors toured the auxiliary building and emergency diesel generator (]]
- SC. [[2, "High Water (Flood) Plan," Revision 00702, and the updated final safety analysis report (UFSAR) as reference material. The purpose of the walkdown was to verify Ginna personnel could implement procedures that were developed to mitigate the consequences of an external flood condition and to verify flood protection equipment was installed in accordance with]]
- UFSAR. [[b. Findings No findings were identified. 1 R04 Equipment Alignment (71111.04) Partial System Walkdown (71111.04Q -Three samples) a. Inspection Scope The inspectors reviewed the alignment of system valves and electrical breakers to ensure proper in-service or standby configurations as described in plant procedures, piping and instrument drawings (P&]]
- UFSAR. During the walkdown, the inspectors evaluated the material condition and general housekeeping of the system and adjacent spaces. The inspectors also verified that operators were following plant technical specifications (
TSs) and system operating procedures. The inspectors performed a partial walkdown of the following systems: The standby auxiliary feedwater (AFW) system while the 'A' train of motor-driven auxiliary feedwater (MDAFW) was out of service (OOS) for planned maintenance; The 'A' train of the residual heat removal (RHR) system while the '8' train was OOS for planned maintenance; and Attachment
.1 The 'A' and 'B'
- OOS s were inspected against Ginna's licensing basis and industry standards. In addition, the passive fire protection features were inspected including the ventilation system fire dampers, structural steel fire proofing, and electrical penetration seals. The following plant areas were inspected: Auxiliary Building Operating Floor (Fire Zane]]
- SH [[). b. Findings No findings were identified . . 2 Annual Inspection (71111.15A -One sample) a. Inspection Scope The inspectors observed an announced test of Ginna's fire brigade on August 18, 2010. The test involved a simulated main transformer fire. The inspectors observed fire brigade personnel obtain their protective equipment, travel to the simulated fire location, and demonstrate how they would extinguish a main transformer fire. Fallowing the drill, the inspectors observed the post-drill critique and verified that performance issues were discussed and documented in Ginna's corrective action program (CAP). The inspectors evaluated the performance of the brigade using the criteria outlined in the following procedures:]]
SC-3.4.1, "Fire Brigade Captain and Control Roam Personnel Responsibilities," Revision 03901; and FRP-32.0, "Transformer Yard," Revision 6. The fire brigade successfully completed the objectives of the drill. Enclosure
Findings No findings were identified. 1R11 Licensed Operator Requalification Program (71111.110 -One sample) Inspection Scope On July 27,2010, the inspectors observed a licensed operator simulator scenario, Cycle Evaluation-1, "Abnormal Operating Exam No.1," Revision
- O. The inspectors reviewed the critical tasks associated with the scenario, observed the operators' performance, and observed the post-evaluation critique. The inspectors also reviewed and verified compliance with Ginna procedure
- OTG [[-2.2, "Simulator Examination Instructions," Revision 43. Findings No findings were identified. 1 R12 Maintenance Effectiveness (71111.120 -Three samples) Inspection Scope The inspectors evaluated work practices and follow-up corrective actions for selected systems, structures, and components (SSCs) for maintenance effectiveness. The inspectors reviewed the performance history of those]]
- SSC s and assessed condition determinations for those issues with potential common cause or generic implications to evaluate the adequacy of corrective actions. The inspectors reviewed Ginna's problem identification and resolution (
- PI&R ) actions for these issues to evaluate whether Ginna had appropriately monitored, evaluated, and dispositioned the issues in accordance with procedures and the requirements of
- 10 CFR Part 50.65, "Requirements for Monitoring the Effectiveness of Maintenance." In addition, the inspectors reviewed selected
SSC classifications, performance criteria and goals, and corrective actions that were taken or planned to verify whether the actions were reasonable and appropriate. The following issues were reviewed: * Equipment deficiencies associated with the EDG room ventilation system: * Fire protection system components scoped in the maintenance rule; and * Reactor protection system. No findings were Enclosure
R13 Maintenance Risk Assessments and Emergent Work Control (71111.13 -Four samples) a. Inspection Scope The inspectors evaluated the effectiveness of Ginna's maintenance risk assessments required by
- 10 CFR [[Part 50.65(a)(4). The inspectors discussed the use of Ginna's online risk monitoring software with control room operators and scheduling department personnel. The inspectors reviewed equipment tracking documentation and daily work schedules, and performed plant tours to verify that actual plant configuration matched the assessed configuration. Additionally, the inspectors verified that risk management actions, for both planned and emergent work, were consistent with those described in]]
- OOS [[]]
- TSC ) batteries while Rochester Gas & Electric (RG&E) was performing work in station 13A (August 5, 2010); Emergent work on circuit 767 in Ginna's transformer yard due to erroneous voltmeter indications while
- RHR and testing of the containment recirculation fans units (September 8, 2010); and Planned maintenance on the
- TSC [[inverter and emergent work on fire system S23, transformer 12B automatic deluge system, which removed the auto start function of the diesel fire pump from service (September 13, 2010). b. Findings Introduction: The inspectors identified a very low safety significant (Green). non-cited violation (]]
- 10 CFR 50.65, "Maintenance Rule," paragraph (a)(4), when Ginna did not perform an accurate risk assessment prior to removing the
- TSC battery charger and fire system S01, suppression for auxiliary building basement cable trays, from service. Description: On September 13, 2010, the work week schedule had
- TSC inverter work planned for the day that would place the plant in a yellow risk condition with a core damage frequency (
- CDF ) probabilistic risk factor of 4.1 for the duration of the maintenance. The work week schedule did not take into account any emergent work activities for the day. On September 13, in addition to the
- TSC [[inverter work, emergent work for the day included removal of the auto start function of the diesel fire pump as well as removal of fire system S01 for maintenance. The inspectors identified that . Ginna's real-time risk model showed a green risk with a probabilistic risk factor of 1.9, despite in progress]]
- SOFTWA [[]]
RE, "Control Room Software Operation," Revision 01000, and procedure, 52.12, "Nonfunctional Equipment Important to Safety," Revision 06302, require operators to control and update this risk model as components are removed and returned to service. Enclosure
The inspectors reviewed the maintenance procedure for the
- TSC battery charger unavailable. This battery charger is credited in Ginna's risk model to provide backup power to the station batteries during
- 10 CFR 50, Appendix R, fire events, The battery charger was not removed from service in the plant risk model. The plant risk was yellow at 4.1 with the
- TSC [[battery charger 005 based on the Ginna risk software. The inspectors noted that operators believed that plant risk was green and had the control room posted as such. Therefore, operators did not have accurate risk awareness. Additionally with the belief that plant risk was green, operators had removed fire system S01 from service while the]]
- TSC battery charger and 501 are both needed for a fire in the auxiliary building basement. Operators, however, did not realize the resultant risk with both S01 and the
- ODS [[as an increased medium (yellow) probabilistic risk factor of 8.1. The inspectors also noted that several risk management tools were not utilized by Ginna operations staff. Specifically, Ginna did not complete procedure A-52.12 documentation for removing the]]
- CNG [[-OP-1.01-100, "Operations Log Keeping and Station Rounds," Revision 00200, requires narrative log entries to be made by the control room supervisor at the start of risk significant activities describing plant risk due to activity initiation and compensatory measures. Ginna did not update the standard logs to reflect the risk associated with this maintenance as required by this procedure. Ginna's corrective actions included immediately updating their risk model to reflect the actual plant configuration. This condition is documented in]]
- CR 2010-5607. Analysis: The performance deficiency associated with this finding is that Ginna did not perform an accurate risk assessment prior to removing the
- IMC [[0612, "Power Reactor Inspection Reports," Appendix E, Example 7.e, the finding is more than minor because if the overall risk had been correctly assessed, it would have placed Ginna into a higher risk category. This finding is associated with the configuration control attribute of the Mitigating Systems Cornerstone and affects the Cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. The inspectors determined that the finding was of very low safety Significance (Green) using]]
- IMC [[0609, Appendix K, "Maintenance Risk Assessment and Risk Management Significance Determination Process," Flow chart 1, because the incremental core damage probability deficit was less than 1.0E-6. This finding has a cross-cutting aspect in the area of human performance, work control, in that Ginna operators were not fully apprised of the work status of the]]
- 10 CFR [[50.65, paragraph (a)(4),"Maintenance Rule," states. in part, that before performing maintenance activities, the licensee shall assess and manage the increase in risk that may result from the proposed maintenance activities. Contrary to the above, on September 13, 2010, Ginna failed to accurately assess the increase in risk prior to removing the]]
TSC battery charger and fire system S01 from service for maintenance. Ginna's immediate corrective actions included promptly updating their risk model to reflect the actual plant configuration. Because this finding was determined to Enclosure
be of very low safety significance and was entered into Ginna's
- NRC [[Enforcement Policy. (NCV 05000244/2010004*01, Failure to Adequately Assess the Risk of Technical Support Center Inverter Maintenance) 1 R15 Operability Evaluations (71111.15 -Five samples) a. Inspection Scope The inspectors reviewed operability evaluations and/or condition reports (CRs) in order to verify that the identified conditions did not adversely affect safety system operability or plant safety. The evaluations were reviewed using criteria specified in]]
- NRC [[Inspection Manual Sections on Resolution of Degraded and Nonconforming Conditions and on Operability" and Inspection Manual Part 9900, "Operability Determinations and Functionality Assessments for Resolution of Degraded or Nonconforming Conditions Adverse to Quality or Safety." In addition, where a component was inoperable, the inspectors verified the]]
- TS limiting condition for operation implications were properly addressed. The inspectors performed field walkdowns, interviewed personnel, and reviewed the following items:
- SW [[) to the component cooling water (CCW) heat exchanger (HX) that may result in accident analysis flows not being met when aligned to the alternate discharge; Engineering Change Package (ECP) 10-000653, Evaluation of July 6, 2010, Offsite Power Inoperability; and]]
- TDAFW System Lube Oil Pressure Switch Housing. b. Findings No findings were identified. 1 R18 Plant Modifications (71111.18 -One sample) Temporary Modification a. Inspection Scope The inspectors reviewed
ECP installed a jumper in rack R1 of channel one of the reactor protection system in order to restore operability to the channel when a sliding linkage providing circuit continuity broke during planned maintenance. The inspectors reviewed Enclosure
the
- ECP to determine whether the temporary change adversely affected system availability or a function important to plant safety. The inspectors reviewed the associated system design bases including the
- TS [[, and assessed the adequacy of the safety determination screening and evaluation. The inspectors also assessed configuration control of the temporary change by reviewing selected drawings and procedures to verify whether appropriate updates had been made. The inspectors compared the actual installation with the temporary modification documents to determine whether the implemented change was consistent with the approved, documented modification. b. Findings No findings were identified. 1 R19 Post-Maintenance Testing (71111.19 -Six samples) a. I nspection Scope The inspectors observed portions of post-maintenance testing (]]
- PMT [[) activities in the field to determine whether the tests were performed in accordance with approved procedures. The inspectors assessed each test's adequacy by comparing the test methodology to the scope of maintenance performed. In addition, the inspectors evaluated the test acceptance criteria to verify that the tested components satisfied the applicable design and licensing bases and]]
- TS requirements. The inspectors reviewed the recorded test data to determine whether the acceptance criteria were satisfied. The following
- AFW Pump Cooling Water Strainer Bypass Solenoid," and C90215885, "Replace 4000C with a Nozzle Check Valve per
- PRESS -940, "Calibration of Safety Injection (SI) Accumulator 'A' (Loop 'B') Pressure Loop 940," Rev. 800, to test Slaccumulator 'A' pressure indicator 940 after its replacement under
- CMM -11-05-PAC07A, "Ingersoll-Rand, Type 4 X 13 Low Pressure, Centrifugal Pump Maintenance for Spent Fuel Pool (SFP) Recirculation Pump 'A'." Rev. 00301, to perform maintenance and testing of the 'A'
- WO C90780705, "SFP Recirculation Pump 'A' Minor Preventive Maintenance (PM) Inspection," (August 19, 2010);
- STP -O-17.2, "Process Radiation Monitors R-11 thru R-18, R-20 thru R-22, and Iodine Monitors R-10A and R-10B Source Check, Alarm Setpoint Verification, and Functional Test," Rev. 0, to test radiation detector R-20A,
- SFP [[]]
- SFP [[]]
- RHR [[]]
- WO C90835831, "Perform Inspection of the Stem and Bushings of V-9519E," (September 28, 2010). b. Findings Introduction: A very low safety significant (Green) self-revealing
- XVI , "Corrective Action," was determined based on Ginna's failure to identify that vibration data exceeded the 1
- ST [[criteria for the previous four surveillance tests due to vibration data being incorrectly measured and analyzed. Ginna's apparent cause evaluation (ACE) documented that an extent of condition review was completed which identified all the additional components that were unknowingly in the]]
- 1ST alert or required action range from May 2008 to June 2009. As a part of their extent of condition, Ginna identified that the 'A'
- EDG fuel oil transfer pump was also in the alert range. Other corrective actions included changing all of the vibration analyzer display units, training operators on how to take the vibration measurements, and updating
- CR 4517. The inspectors documented this issue as a licensee-identified violation in inspection report 05000244/2009005. On August 4, 2010, Ginmi tested the 'A'
- MDAFW pump and determined that it was in the alert range for inboard bearing vibration. During their analysis, Ginna determined that during the last comprehensive test in October 2008, the same vibration point unknowingly had been in the 1
- ST [[alert range. This had not been identiFied during Ginna's previous extent of condition review. Subsequently, Ginna performed another extent of condition review and identified that four other components were outside the vibration acceptance criteria and in the alert range. These pumps included the 'B']]
- 1ST acceptable vibration range, Ginna performed an engineering evaluation that determined the previous higher than acceptable vibration readings were due to inadequate vibration measurement techniques. The 'A'
- 1ST alert range and is required to be tested at an increased periodicity. Ginna's corrective actions included immediately verifying that all other 1
- CR 2010-4853. Analysis: The performance deficiency associated with this finding is that during a previously conducted extent of condition review, Ginna did not identify that the
IMC 0612, "Power Reactor Inspection Reports," Appendix E, Example 2.c, the finding is more than minor because it Enclosure
was repetitive and it affected a number of pumps. This finding was associated with the equipment performance attribute of the Mitigating Systems Cornerstone and adversely affected the cornerstone objective of ensuring the capability of systems that respond to initiating events to prevent undesirable consequences. The inspectors determined that the finding was of very low safety significance (Green) using
- IMC [[0609, Attachment 0609.04, "Phase 1 -Initial Screening and Characterization of Findings." Specifically, the finding was not a design or qualification deficiency, did not represent a loss of safety function, and did not screen as potentially risk significant due to seismic, flooding, or severe weather. This finding has a cross-cutting aspect in the area of]]
- 1ST program vibration data during their extent of condition review conducted in 2009 as a result of the 'B'
- XVI , "Corrective Action," states, in part, that conditions adverse to quality shall be promptly identified and corrected. Contrary to the above, Ginna did not promptly identify that five pumps were in the
- 1ST acceptable range. Because this finding was determined to be of very low safety significance and was entered into Ginna's
- NCV [[05000244/2010004-02, Failure to Identify Five Pumps in the Inservice Testing Alert Range) 1 R22 Surveillance Testing (71111.22 -Six samples) a. Inspection Scope The inspectors observed the performance and/or reviewed test data for the following surveillance tests that are associated with selected risk-significant]]
- TS [[s were followed and that acceptance criteria were properly specified. The inspectors also verified that proper test conditions were established as specified in the procedures, no equipment preconditioning activities occurred, and acceptance criteria were met.]]
- STP -E-2.3.1Q, "Containment Recirculation Fan Testing -Quarterly," Rev. 00001 (September 9,2010). b. Findings No findings were identified. Enclosure
- EP [[6 Drill Evaluation (71114.06 -One sample) a. Inspection Scope On July 29, 2010, the inspectors observed portions of a scheduled drill of Ginna's emergency preparedness organization. Following the drill, the inspectors observed the post-drill critique and assessment of]]
- TSC performance during the drill. The drill scenario included an unisolable secondary side line break with a steam generator tube rupture. The inspectors verified that emergency classification declarations and notifications were completed in accordance with
- CFR Part 50 Appendix E, and emergency plan implementing procedures. The inspectors verified that the
- RADIAT [[]]
- ION [[]]
- RS [[01 Radiological Hazard Assessment and Exposure Controls (71124.01 -One sample) a. Inspection Scope From September 27 to 30, 2010, the inspectors performed the following activities to verify that Ginna properly assessed the radiological hazards in the workplace and implemented appropriate radiation monitoring and exposure controls during routine operations. Implementation of these controls was reviewed against the criteria contained in]]
TSs, and Ginna procedures. Radiological Hazard Assessment The inspectors reviewed work activities for the clean-up of the waste hold up tank, auxiliary building floor drains, auxiliary building sump, and the sump tank. The inspectors also reviewed activities in progress for the independent spent fuel storage installation. The inspectors verified that appropriate pre-work surveys were performed and that appropriate hazards were properly identified. The inspectors verified air samples were collected and analyzed in accordance with Ginna procedures. The inspectors observed work in progress and verified that portable air sampling was representative of the individuals' breathing zone. Enclosure
Instructions to Workers The inspectors verified that workers would be informed of changing conditions by the radiological controls technician providing continuous job coverage. Contamination and Radioactive Material Control The inspectors verified that Ginna has not established a de facto "release limit" by altering the instrument's typical sensitivity through altering energy discrimination or placing instruments in high background radiation areas. Radiological Hazards Control and Work Coverage There were no opportunities to observe work in areas with significant dose gradients during this inspection period. Ginna has no posted airborne radiation areas. Therefore, the inspectors had no opportunities to observe work in such areas and could not evaluate controls for those areas. b. Findings No findings were identified.
- ALARA [[Planning and Controls (71124.02 -One sample) a. I nspection Scope From September 27 to 30,2010, the inspectors performed the following activities to verify that Ginna was properly implementing operational, engineering, and administrative controls to maintain personnel exposure as low as reasonably achievable (ALARA) for activities performed during routine operations. Implementation of these controls was reviewed against the criteria contained in]]
- 10 CFR [[20, applicable industry standards, and Ginna's procedures. Inspection Planning The inspectors reviewed pertinent information regarding cumulative exposure history, current exposure trends, and ongoing activities. The inspectors reviewed the site's 3-year rolling average dose and compared the site's average with industry's average. The inspectors reviewed Ginna's trend in collective exposure and the site's source term measurements. Verification of Dose Estimates and Exposure Tracking Systems The inspectors reviewed]]
ALARA packages from the previous outage. The inspectors verified the exposure estimates for accuracy. Enclosure
The inspectors verified that Ginna has established measures to track, trend, and set trigger points to prompt additional
- ALARA planning and controls. The inspectors performed an evaluation of Ginna's method of adjusting exposure estimates when unexpected changes occur. b. Findings No findings were identified. 4.
- OTHER [[]]
- ACTIVI [[]]
- TIES [[40A1 Performance Indicator (PI) Verification (71151) .1 Cornerstone: Mitigating Systems (71151 -Three samples) a. Inspection Scope The inspectors completed a review of mitigating systems performance index (MSPI) data including a review of Ginna's train/system unavailability data, monitored component demands, and demand failure data. As part of this review, Ginna's]]
- PI Guideline," Revision 6, were examined. To verify the accuracy of the data, the inspectors reviewed monthly operating reports,
- NRC inspection reports, and Ginna event reports from August 2009 to August 2010. The inspectors also reviewed
- OOS [[logs, operating logs, and maintenance rule information for the period of August 2009 to August 2010 to determine the accuracy and completeness of the reported unavailability data. For the selected systems, a review of maintenance and test history confirmed the accuracy of demand failure data for the identified active components for the most recent 12 quarters. The]]
AFW). b. Findings No findings were identified. Enclosure
Cornerstone: Public Radiation Safety (71151 -One sample) Radiological Effluent Technical Specification/Offsite Dose Calculation Manual Radiological Effluent Occurrences Inspection Scope The inspectors reviewed relevant effluent release reports for the period September 1, 2009, through August 31, 2010, for issues related to the public radiation safety
- PI [[, which measures radiological effluent release occurrences that exceed 1.5 millirem/quarter whole body or 5.0 millirem/quarter organ dose for liquid effluents; 5 millirads!quarter gamma air dose, 10 millirads/quarter beta air dose, and 7.5 millirads/quarter for organ dose for gaseous effluents. No findings were identified . Cornerstone: Occupational Radiation Safety (71151 -One sample) Occupational Exposure Control Effectiveness Inspection Scope The inspectors reviewed implementation of Ginna's occupational exposure control effectiveness]]
- PI program. Specifically, the inspectors reviewed recent action reports, and associated documents, for occurrences involving locked high radiation areas, very high radiation areas, and unplanned exposures against the criteria specified in
- NEI 02, Regulatory Assessment Performance Indicator Guideline, Revision 6, to verify that all occurrences that met the
NEI criteria were identified and reported as performance indicators. Findings No findings were identified. 40A2 Problem Identification and Resolution .1 Continuous Review of Items Entered into the Corrective Action Program Insgection Scope As specified by Inspection Procedure 71152, "Identification and Resolution of Problems," and in order to help identify repetitive equipment failures or specific human performance issues for follow-up, the inspectors performed a daily screening of items entered into Ginna's CAP. This review was accomplished by reviewing electronic copies of eRs, periodic attendance at daily screening meetings, and accessing Ginna's computerized database. Enclosure
b. Findings No findings were identified . . Annual Sample: Review of Incore Flux Mapping System Drive Failures (71152 -One sample) a. Inspection Scope
- CR [[2009-5450 documented that while performing flux mapping of the core on August 7, 2009, the '8' detector intermittently stopped during insertion. The detector needs to operate smoothly in order to obtain meaningful flux mapping data during performance of the associated]]
- TS [[surveillance. Ginna determined that the most likely cause of the 'B' drive intermittent operation was a fault in the encoder/decoder system. However, the cause could not be definitively identified during troubleshooting. The inspectors also reviewed several]]
- CR [[s documenting other failures of the incore flux mapping system. Ginna determined that the cause of increasing system failures appeared to be related degradation of the system. Ginna placed the incore flux mapping system on the top 10 material condition list because of past system performance history and to ensure that it received proper attention for issue resolution. The inspectors assessed Ginna's problem identification threshold, cause analyses, extent-of-condition reviews, operability determinations, and the prioritization and timeliness of corrective actions to determine whether Ginna was appropriately identifying, characterizing, and correcting problems associated with these issues and whether the planned or completed corrective actions were appropriate to prevent recurrence. Additionally, the inspectors performed walkdowns of accessible system components to assess if abnormal conditions existed. The inspectors also interviewed plant personnel regarding the identified issues and implemented corrective actions. b. Findings and Observations No findings were identified. Ginna appropriately implemented their corrective action process regarding the initial discovery of the reviewed issues. The]]
- ACE , operability determinations, extent-of-condition reviews, and implemented and planned corrective actions. In addition, the elements of the
- ACE [[were detailed and thorough. Interim corrective actions such as performing system maintenance and having spare system parts available onsite to perform system repairs were appropriate to minimize potential failures of the incore flux mapping system pending system upgrades. The corrective actions for the various system failures included developing a troubleshooting plan with vendor support, reviewing preventive/corrective maintenance practices with vendor support, developing a failure modes and effects analysis identifying potential failure modes of the system/components, and developing contingency plans including implementing standing]]
WOs to perform system repairs if necessary. Additionally, Ginna had long-term corrective action plans in place to replace the incore thimbles and to replace the incore flux mapping system electronics. The inspectors verified that at no time was invalid flux Enclosure
mapping data obtained or were
- TS leakage from the piping and/or components that provide pressurized nitrogen to operate the pressurizer power-operated relief valves (]]
- PORV s). This source of nitrogen, which includes an accumulator, provides the motive source to operate the
- PORV [[s in the overpressure protection mode (during shutdown conditions), and for loss of heat sink and steam generator tube rupture scenarios. The inspectors reviewed Ginna's associated evaluations and corrective action reports. The inspectors also interviewed plant personnel and reviewed troubleshooting results to evaluate the performance of the components and the effectiveness of Ginna's corrective actions. In addition, the inspectors reviewed Ginna's]]
- UFSAR to assess the potential adverse impact of leakage and the associated configuration on plant operations. b. Findings and Observations No findings were identified. The inspectors noted that the
- PORV [[nitrogen accumulator challenges were most recently associated with the 'B' train, but have historically occurred on both trains. The impact of the nitrogen leakage and associated pressure reduction resulted in frequent accumulator fill activities by the operators. This action was necessary to keep the]]
- PORV [[and actuation train operable (greater than 400 pounds per square inch gauge (psig>>. The aJarm annunciates at 725 psig, requiring operator response. The frequency of filling the accumulators has varied between several hours to several weeks.]]
- CR 2009-8455 documented the adverse trend in the 'B' overpressure protection accumulator refills. The inspectors reviewed the actions associated with
- CR [[2009-8455, which included a systematic troubleshooting activity to identify the possible sources of leaks. The troubleshooting ultimately concluded that the primary source of the leakage was from a flanged connection in the nitrogen regulator. As the existing regulators have been part of a removaVrefurbishment rotation, Ginna decided to procure new regulators as an action to abate the leakage. For the interim, condition monitoring is expected to identify continued challenges and institute corrective actions (refill) to ensure that]]
- PORV operability is not challenged. Ginna plans to install the new regulators in the next refueling outage, scheduled for spring 2011. Ginna's evaluation also considered the impact of the
- PO [[]]
RV nitrogen accumulator challenges to plant operators. Accordingly, the frequent accumulator charging was added to Ginna's operator challenges list. The inspectors confirmed that Ginna was adequately monitoring and trending relevant parameters so that worsening conditions Enclosure
.4 20 could be identified and addressed in a timely fashion. The inspectors found that Ginna's actions to evaluate and correct the
- PORV [[challenges were appropriate . Annual Sample: Assessment of Corrective Actions Associated with the Pressurizer Power-Operated Relief Valve Block Valves, 515 and 516 (71152 -One sample) a. Inspection Scope This inspection was performed to assess Ginna's evaluation and corrective actions for grease degradation and stem factor calculation discrepancies associated with the 515 and 516]]
- PORV [[block valves. Additionally, the inspectors reviewed Ginna's evaluation of a bent stem associated with block valve 516 to ensure the proposed corrective actions were reasonable to correct the identified cause and prevent recurrence of the issue. During testing and maintenance work performed on the block valves in September 2009, Ginna determined that degraded grease conditions existed with both the 515 and]]
- 516 PORV [[block valves. The inspectors reviewed the degraded grease apparent cause analysis to verify corrective actions completed and proposed were reasonable to ensure efficient transfer of valve actuator torque to thrust was maintained within expected design assumptions. This review included corrective actions such as providing additional training to plant staff on the proper method of grease application and revisions . to]]
- PORV [[block valve test data and reviewed revised stem factor assumptions within design calculations to ensure that design margins were maintained. Additionally, the inspectors reviewed Ginna's operability review associated with a slightly bent stem for the 516 valve to ensure that the conclusion was reasonable based on test data and analysis. b. Findings and Observations No findings were identified. The inspectors found that the issues had been accurately documented within the]]
- CAP [[and appropriate extent-of-condition reviews had been performed to assess. the potential impact on other valves. The inspectors found the completed and proposed corrective actions for the grease degradation, stem factor discrepancies, and bent stem issue to be reasonable based on the information reviewed within Ginna's]]
- PORV [[block valve 516, the inspectors identified an error of minor significance in a Ginna stem thread wear and coefficient of friction evaluation. Ginna had performed this evaluation through a review of actual valve test data to assess stem thread wear, coefficient of friction margin, and the adequacy of the test frequency going forward. The inspectors noted that incorrect inputs were used in the 516 valve spreadsheet for overall actuator ratio, stem thread type, and thread pitch. Ginna entered this issue into the]]
- CR [[2010-5789, performed an extent-of-condition review, and verified that two other valves had a similar deficiency with incorrect spreadsheet inputs. Ginna revised the inputs and reevaluated the coefficient of friction and stem thread wear margins for the affected valves and found margins remained acceptable with no impact on valve operability. The inspectors evaluated the deficiency noted above for potential significance in accordance with the guidance in]]
IMC 0612, Appendix B, "Issue Enclosure
Screening," and Appendix E, "Examples of Minor Issues," and determined that the was not a finding of more than minor significance since there was no impact on 40A3 Followup of Events and Notices of Enforcement Discretion (71153 -One sample) 1. Power to
- TSC Inverter Loads was De-energized During Inverter Maintenance a. Inspection Scope On September 14, 2010, power to the
- TSC inverter loads was inadvertently energized during scheduled maintenance. The cause was a result of an incorrect step the maintenance procedure,
- TSC [[inverter loads resulted in a loss of the plant process computer normal control room telephones, radiological emergency communication telephone line, "blue" control room outside telephone lines, and the control room base station. The inspectors responded to the control room to monitor and operator response. The inspectors compared operator actions with procedures and reviewed emergency action level (]]
- EAL ) technical basis section 7.3, "Loss of Indications/Alarms/Communication Capability," to assess appropriate
- NRC [[emergency system telephone and/or hardwired shift manager communications which b. Findings . No findings were identified. , 40A5 Other Activities Inspection Results for Temporary Instruction (Tn 2515/179 a. Inspection Scope From September 27 to 30,2010, the inspectors performed the following activities to confirm that inventories of materials possessed by Ginna were appropriately reported and documented in the national source tracking system in accordance with 10]]
CFR 20.2207. This inspection activity completes the requirements for closeout of this TI. Inventory Verification The inspectors obtained a copy of Ginna's national source tracking system inventory for comparison and performed a physical inventory. The inspectors verified the information listed on Ginna's inventory record. Enclosure
Determine the Location of Unaccounted for Nationally Tracked The inspectors verified there were no unaccounted for nationally tracked Review of Other Administrative The inspectors reviewed the administrative information with Ginna personnel to that the information was up to date. No findings were Meetings. Including Exit Exit Meeting Summary On October 12, 2010. the resident inspectors presented the inspection results to Mr. Eric Larson and other members of his staff, who acknowledged the findings. inspectors verified that none of the material examined during the inspection considered proprietary in
- ATTACH [[]]
- MENT [[:]]
- SUPPLE [[]]
- MENTAL [[]]
- INFORM [[]]
- SUPPLE [[]]
- MENTAL [[]]
- KEY [[]]
- POINTS [[]]
- OF [[]]
- J. Carlin Vice President, Ginna J. Bowers General Supervisor, Radiation Protection T. Hedges .Director, Emergency Preparedness E. Larson Plant Manager K. McLaughlin General Supervisor-Shift Operations T.
- S. Snowden Chemistry Supervisor J. Sullivan Manager, Operations P. Swift Manager. Engineering Services
- LIST [[]]
- OF [[]]
- ITEMS [[]]
- AND [[]]
- NCV Failure to Adequately Assess the Risk of Technical Support Center Inverter Maintenance (Section 1 R13) 05000244/2010004-02 Range (Section 1 Ri9)
- LIST [[]]
- OF [[]]
- REVIEW [[]]
ER-SC.2, High Water (Flood) Plan, Rev. 00702 SC-3.i7, Auxiliary Building Flood Barrier Installation/Removal/Inspection, Rev. 00100 Condition Reports 2008-8213 2008-8947 2009-1557
2009-3873 Attachment
Section 1 R04: Equipment Alignment Drawing 33013-1238, Standby
- 17 SC [[-3.4.1, Fire Brigade Captain and Control Room Personnel Responsibilities, Rev. 03901 Drawings 33013-2552, Fire Response Plan Auxiliary Building-Operating Floor Elevation 271 feet, Rev. 6 33013-2546, Fire Response Plan Auxiliary Building-Intermediate Floor Elevation 253 feet, Rev. 4 33013-2571. Fire Response Plan Screen House above Elevation 253 feet 6 inches, Rev. 6 33013-2559, Fire Response Plan Control Building Plan Views, Rev. 13 Section 1R11: Licensed Operator Requalification Program Document Cycle 10-5, Simulator vs. Plant Differences, July 23, 2010 Procedures]]
- 01300 OTG -2.2, Simulator Examination Instructions, Rev. 43 Section 1R12: Maintenance Effectiveness Documents AutoLog Entries from 01/01/2007 to 811212010 for
- EDG Room Ventilation System Health Report, 2nd Quarter 2010 Fire Protection System Train Performance Criteria
- EV ents Reactor Protection System Health Report, 2nd Quarter 2010 System Report for Fire Protection System Drawing 33013-1873, Ventilation for
ID, Rev. 3 Attachment
Condition Reports 2007-1858 2007-8162 2008-9254 2009-2207 2007-6994 2007-8588 2009-0417 2009-9361 2007-6999 2008-6060 2009-1476 2007-8151 2008-9084 2009-2190 Section 1R13: Maintenance Risk Assessments and Emergent Work Control Document AutoLog Entries for All Logs 8/5/2010 Procedure A-52.12, Nonfunctional Equipment Important to Safety, Rev.
- AUTO -SOFTWARE, Control Room Software Operation, Rev. 01000 Condition Reports 2010-4804 2010-4858 Section 1R15: Operability Evaluations Document
- ID , Sheet 2 of 3, Rev. 39 Condition Reports 2009-4517 2010-4835 2010-5015 2010*2598 2010-4853 2010-3514 2010-4859 Section 1R18: Plant Modifications Document
- ECP 10-000557, Add Temporary Jumper to Bypass Broken Test Switch Section 1R19: Post-Maintenance Testing Procedures
- SFP [[]]
- SI Accumulator 'A' (Loop 'B') Pressure Loop 940, Rev. 800 P-9, Radiation Monitoring System, Rev. 09802
- STP -O-17.2, Process Radiation Monitors R-11 thru R-18, R-20 thru R-22, and Iodine Monitors R-10A and R-10B Source Check, Alarm Setpoint Verification, and Functional "Fest, Rev.
- AFW [[]]
- AFW Pump Instrumentation Upgrade, Rev. 4 Condition Reports 2010-4839 2010-4913 2010-4915 2010-5944 Work Orders C90691808 C90819192 C90835831 C90828034 C90780705 C90803731 C90215885 C90732595 Section 1R22: Surveillance Testing Procedures
- CCW [[]]
- P& [[]]
ID, Rev. 31 Condition Reports 2010-05558 2010-05507 2010-05523 Work Order C090803795 Attachment
Section
- 2RS 1: Radiological Hazard Assessment and Exposure Controls Procedures A-1.1, Access Control to Locked High Radiation and Very High Radiation Areas, Rev. 04700
- TI [[]]
ON, Performance of Radiation Surveys, Rev. 00800 Condition Reports 2009-7621 2009-7622 2009-3836 2009-5297 2009-2748 2009-2889 2009-2934 2009-3412 2009-4067 2009-4122 2009-4441 Radiation Work Permits 10-5001
10-5003 10-6007 Section
- PI Guideline, Rev. 6 Section 40A2: Problem Identification and Resolution Documents 86-1234820-03, Low Temperature Overpressure Analysis Summary, dated 9/19/97
- ACE , During Valve Actuator Maintenance on Valve 516 the Valve Operating Stem was Bent, dated 11110109
- DA [[-NS-92-014, Reactor Coolant System (RCS) Overpressurization Protection System Nitrogen Accumulator Tanks.]]
- MOV s 515 and 516, Rev. 0 Incore Flux Mapping System Complex Troubleshooting Plan and Data Sheet Associated with
- WO C90211 012 Maintenance Rule Status Report Operator Challenges List, dated 5/5/10 Plant Health Committee Issues List System
SYS32, Incore Instrumentation System RGE-32, Training System Description, Rev. 11 Attachment
Top 10 Material Conditions List
- MOV Stem Nut Wear, Rev. 0 M-52.1, Installation of Detector and Cable and Maintenance on Miniature Detector Flux Mapping System, Rev. 01900
- PORV [[Operability Verification, Rev. 00100 Drawings 22832, Panel Assembly Drive Control, Sheet 1,1/9/68 22389, Panel Assembly Common Control, Sheet 1,3/21/68 22400, Control Assembly Flux Mapping, Sheet 1, Rev. A 22400, Control Assembly Flux Mapping, Sheet 2, Rev. A 22400, Schematics Tubing Control System Flux Mapping, Sheet 3, 5/17/68 22411, Drive Assembly Incore Defector Insertion, Flux Mapping System, Sheet 1, 3/5/69 22427, Schematic Cable Drive System, Rev. 000, 2/16/68 Condition Reports 2008-4367 2009-6791 2009-7356 2010-0966 2009-4708 2009-6843 2009-8428 2010-4544* 2009-5450 2009-7161 2009-8455 2010-5789* 2009-1890 2009-7188 2009-8459 2009-5797 2009-7304 2009-8460 *initiated as a result of this inspection. Work Orders C20500832 C20801372 C90644717 C20602732 C20802266 C20602986 C20803632 Health Reports 2n, 3id , 4th Quarter 2009 Incore Flux and Temperature Monitoring 1st Quarter 2010 Incore Flux and Temperature Monitoring Section 40A3: Followup of Events and Notices of Enforcement Discretion Procedure]]
PPCS OOS, Rev. 04402 Attachment
Condition Attachment
- ACE [[]]
- ADAMS [[]]
- AFW [[]]
- CDF [[]]
- CFR [[]]
- CCW [[]]
- CR [[]]
- EAL [[]]
- ECP [[]]
- HX [[]]
- ST [[]]
- MDAFW [[]]
- MOV [[]]
- MSPI [[]]
- NEI [[]]
- NCV [[]]
- NRC [[]]
- OOS [[]]
- PARS [[]]
- P&ID [[]]
- PI [[]]
- PI&R [[]]
- PM [[]]
- PMT [[]]
- RCS [[]]
- RG&E [[]]
- RHR [[]]
- SDP [[]]
- SFP [[]]
- SI [[]]
- SSC [[]]
- SW [[]]
- TDAFW [[]]
- TS [[]]
- TSC [[]]
- UFSAR [[]]
- ST performance index Nuclear Energy Institute non-cited violation U.S. Nuclear Regulatory Commission out of service Publicly Available Records piping and instrument drawing performance indicator problem identification and resolution preventive maintenance post-maintenance testing power-operated relief valve pounds per square inch guage reactor coolant system Rochester Gas & Electric residual heat removal significance determination process spent fuel pool safety injection system. structure, and component service water turbine-drive auxiliary feedwater technical specification technical support center updated final safety analysis report work order Attachment]]