MONTHYEARML24250A1132024-09-0303 September 2024 Inspection Report 2024004 Radiation Safety Baseline Inspection Information Request ML24250A1922024-08-29029 August 2024 Amendment Nos. 223/206 (1) - Email ML24232A0052024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - LAR and Exemption Request to Remove Tier 1 and Tier 2 Requirements for Vogtle 3 and 4 ML24253A0722024-08-15015 August 2024 Perspectives on Proposed Removal of Tier 1 and Tier 2 Requirements ML24206A0252024-07-20020 July 2024 NRR E-mail Capture - for Your Comments - State of Georgia - Vogtle Unit 1 - Emergency License Amendment Request for Technical Specification 3.7.9 ML24199A1592024-07-17017 July 2024 NRR E-mail Capture - Request for Additional Information - Vogtle 3 and 4 - Exemption for the Requirements in 10 CFR 50.71 Pertaining to the Submittal of Updated Final Safety Analysis Report ML24198A1672024-07-16016 July 2024 NRR E-mail Capture - Acceptance Review Vogtle 3 and 4 - License Amendment Request Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Surveillance Requirement L-2024-LLA-0083 ML24197A1572024-07-15015 July 2024 NRR E-mail Capture - Acceptance Review - Farley and Vogtle 1 and 2, LAR - TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML24197A0172024-07-12012 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley and Vogtle 1 and 2 - Alternative Request for Pressurizer Welds ML24194A0032024-07-11011 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley, Hatch, and Vogtle 1 and 2 - Alternative Request for Code Case N-572 ML24180A0012024-06-26026 June 2024 NRR E-mail Capture - Acceptance Review Farley 1 and 2 and Vogtle 1 and 2 - Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) (L-2024-LLR-0041) ML24170A9362024-06-18018 June 2024 NRR E-mail Capture - Fyi - Change to Estimated Completion Date for the SNC Fleet Physical Barrier Exemptions (L-2023-LLE-0018 and L-2023-LLE-0021) ML24178A3422024-05-16016 May 2024 NRR E-mail Capture - Request for Call - Proposed Vogtle 3 & 4 Tier 1 and Tier 2 Exemptions and LAR ML24120A0262024-04-29029 April 2024 COL Docs - FW Vogtle Electric Generating Plant, Unit 4 - Project Manager Reassignment ML24120A0462024-04-29029 April 2024 COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Power Ascension Tests ML24119A0012024-04-28028 April 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Power Ascension Tests ML24108A0132024-04-16016 April 2024 NRR E-mail Capture - (External_Sender) Responses from Wednesday 4/10/2024 Call with Southern Nuclear Operating Co. Vogtle 3&4 Licensing Actions ML24107A7292024-04-15015 April 2024 Request for Vogtle Electric Generating Plant Units 1 & 2 - Radiation Protection Inspection - Inspection Report 2024-02 ML24107A9322024-04-15015 April 2024 Document Request for Vogtle Electric Generating Plant Units 1 & 2 - Radiation Protection Inspection Report 2024-02 ML24106A0522024-04-12012 April 2024 NRR E-mail Capture - Acceptance Review - Vogtle 1 and 2 - Emergency Diesel Generator (EDG) Voltage and Frequency License Amendment Request (LAR) (L-2024-LLA-0031) ML24100A7842024-04-0909 April 2024 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Vogtle, Units 3 and 4 - Alternative Request for Explosively Actuated Valves (L-2023-LLR-0016) ML24099A0372024-04-0505 April 2024 NRR E-mail Capture - Acceptance Review - Vogtle Unit 3, License Amendment Request (LAR) Technical Specification (TS) 5.5.13, Ventilation Filter Testing Program (VFTP) - L-2024-LLA-0043 ML24095A2412024-04-0404 April 2024 NRR E-mail Capture - Acceptance Review for the Exemption Request Regarding the Final Safety Analysis Report Update Schedule at Vogtle, Units 3 and 4 ML24072A3982024-03-12012 March 2024 NRR E-mail Capture - for Your Action - Second Round Request for Additional Information (RAI) - Vogtle, Unit 1 - SG Tube Inspection Report - 1R24 (L-2023-LRO-0067) ML24061A2372024-03-0101 March 2024 SNC Email Dated March 1, 2024, Regarding SNC Response to NRC Letter for Vogtle 3 & 4 RES Info ML24057A0872024-02-23023 February 2024 NRR E-mail Capture - Acceptance Review - Alternative Request for Explosively Actuated Valves at Vogtle, Units 3 and 4 ML24046A1352024-02-15015 February 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Initial Criticality and Low-Power Testing ML24039A0882024-02-0808 February 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24039A1122024-02-0808 February 2024 COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24039A1922024-02-0808 February 2024 COL Docs - Correction - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24031A0502024-01-31031 January 2024 COL Docs - FW Erroneous Description of Tier 2 Change Process in Construction Lessons-Learned Report ML24017A1122024-01-17017 January 2024 NRR E-mail Capture - Request for Access to Cyber Security Data - Vogtle, Units 3 and 4 ML23360A0042023-12-23023 December 2023 NRR E-mail Capture - Fyi - Office of Nuclear Regulatory Research (RES) Requests for Vogtle 3 & 4 ML23348A0782023-12-13013 December 2023 NRR E-mail Capture - Voluntary Request for Closed Meeting Regarding Cyber Security Assessments at Vogtle, Units 3 and 4 ML23342A0802023-12-0808 December 2023 NRR E-mail Capture - Request for Additional Information (RAI) - Vogtle, Unit 1 - Review of SG Tube Inspection Report for Refueling Outage 24 (L-2023-LRO-0067) ML23331A9992023-11-27027 November 2023 COL Docs - Re Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23331A9492023-11-26026 November 2023 Email Dated November 26, 2023, from Bo Pham to SNC and NRC - Vogtle Seismic Hazard Report ML23331A9622023-11-22022 November 2023 Email Dated November 22, 2023, from SNC to NRC - Vogtle Seismic Hazard Report ML23326A2802023-11-22022 November 2023 COL Docs - Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23320A0342023-11-16016 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23312A2632023-11-0808 November 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Monday, November 13, 2023 - Vogtle Units 3&4, LAR-22-002, TS 3.8.3, Inverters - Operating Completion Time Extension ML23320A2372023-11-0808 November 2023 NRR E-mail Capture - (External_Sender) Proposed LAR Regarding the Ultimate Heat Sink at Vogtle, Units 1 and 2 ML23311A1512023-11-0707 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23304A2272023-10-31031 October 2023 NRR E-mail Capture - Request for State of Georgia Comment by 5pm Monday, Nov. 6, 2023 - License Amendment Request for Vogtle Unit 4 - to Remove Combined License Appendix C ML23289A1362023-10-16016 October 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Friday, October 20, 2023 - Vogtle Units 3&4, LAR-23-006, Rev.1, More Restrictive Action for Tech. Spec. 3.1.9 ML23283A0332023-10-10010 October 2023 COL Docs - FW Vogtle Units 3 and 4 (LAR 23-009) ML23283A0452023-10-0808 October 2023 E-Mail Re Plant Vogtle - Neop Letter Dated October 8, 2023 - Vogtle 3 & 4 - TS 3.7.6 License Amendment Request 2024-09-03
[Table view] |
Text
Vogtle PEmails From: Rankin, Jennivine Sent: Friday, August 2, 2019 8:03 AM To: Leighty, Steven; KRoberts@southernco.com Cc: Patel, Chandu; Dixon-Herrity, Jennifer; Dudek, Michael; Stutzcage, Edward; Vogtle PEmails; Gleaves, Bill
Subject:
Vogtle LAR-19-005 Draft RAI 9696 Attachments: Vogtle LAR-19-005 Draft RAI_9696 (rev_8-1-19).pdf Steve and Kelli, Attached is our management-approved draft RAI on the LAR-19-005. The next step is for SNC to identify if it has questions or comments or, if not, to accept the draft RAI as final by informing Billy of the acceptance.
Please let Billy or myself know by Tuesday morning if a clarification call is needed.
This email is also being sent to public ADAMS capture. If there is sensitive information, please inform me ASAP so that it will prevented from public viewing.
Please let me know if you have any questions.
- Thanks, Jennie Jennie Rankin, Project Manager Licensing Branch 2 Division of Licensing, Siting, and Environmental Analysis Office of New Reactors 1
Hearing Identifier: Vogtle_COL_Docs_Public Email Number: 464 Mail Envelope Properties (BN6PR09MB2227ABBC9F324C793A4824AF98D90)
Subject:
Vogtle LAR-19-005 Draft RAI 9696 Sent Date: 8/2/2019 8:03:29 AM Received Date: 8/2/2019 8:03:34 AM From: Rankin, Jennivine Created By: Jennivine.Rankin@nrc.gov Recipients:
"Patel, Chandu" <Chandu.Patel@nrc.gov>
Tracking Status: None "Dixon-Herrity, Jennifer" <Jennifer.Dixon-Herrity@nrc.gov>
Tracking Status: None "Dudek, Michael" <Michael.Dudek@nrc.gov>
Tracking Status: None "Stutzcage, Edward" <Edward.Stutzcage@nrc.gov>
Tracking Status: None "Vogtle PEmails" <Vogtle.PEmails@nrc.gov>
Tracking Status: None "Gleaves, Bill" <Bill.Gleaves@nrc.gov>
Tracking Status: None "Leighty, Steven" <sleighty@southernco.COM>
Tracking Status: None "KRoberts@southernco.com" <KRoberts@southernco.com>
Tracking Status: None Post Office: BN6PR09MB2227.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 742 8/2/2019 8:03:34 AM Vogtle LAR-19-005 Draft RAI_9696 (rev_8-1-19).pdf 112925 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
DRAFT Request for Additional Information Vogtle Nuclear Site, Units 3 and 4, Dockets 52-0025 and 52-0026 Southern Nuclear Operating Co.
Docket Nos. 52-0025 and 52-0026 Section: 14.03.08 - Radiation Protection Inspections, Tests, Analyses, and Acceptance Criteria Application Section: Tier 1
Background
In LAR-19-005, the licensee requests changes to COL Appendix C and Tier 1, Table 3.3-1, "Definition of Wall Thicknesses for Nuclear Island Buildings, Turbine Building, and Annex Building," and Table 3.3-6, "Inspections, Tests, Analyses, and Acceptance Criteria." The proposed changes include the allowance of construction deviations from the thicknesses of radiation shielding barriers and the structural wall thickness in the nuclear island structures and annex building, if the changes can be made without a "loss of shielding function" and the structures will withstand design bases loads without loss of structural integrity or safety-related function.
Issue The proposed wording in Table 3.3-1, Footnotes 15, 16, and 17, and the Table 3.3-6 ITAAC acceptance criteria for ITAAC 3.3.00.02a.i.a, 3.3.00.02a.i.b, 3.3.00.02a.i.c, 3.3.00.02a.i.d, 3.3.00.02a.ii.e, 3.3.00.02a.ii.f, and 3.3.00.04b do not provide the clarity needed to assure that the proposed changes are designed and implemented consistently. As currently proposed, the criteria for loss of shielding function are unclear with regards to radiation shielding functionality and aggregate impacts (e.g., occupational dose, public dose, environmental qualification, SSC degradation, control room dose, vital area doses, and, as applicable, equipment survivability).
Additionally, the methodologies should be consistent with those used in the design certification.
Similarly, for structures the criteria to assess the resulting structural integrity is unclear and it is indeterminate whether the applicants proposal accounts for the global impacts of all proposed changes so that the changes do not result in a loss of structural integrity or safety-related functions.
The footnotes and associated ITAAC acceptance criteria should clearly define the radiation shielding functional requirements to be met when the licensee deviates from the thicknesses and tolerances that are currently in Table 3.3-1.
For the structural reconciliation of construction deviations mentioned in footnotes 15, 16, and 17 of the LAR enclosure 3, the staff is unclear about the bases used to justify deviations from the Tier 1 values, including details on the evaluation method and acceptance criteria. The staff did not find the supporting information in Tier 2 that provides the methodology to be used; nor did the staff find the associated acceptance criteria.
Question Please clarify or revise, as appropriate, the Table 3.3-1 Footnotes 15, 16, and 17 and the acceptance criteria for ITAAC 3.3.00.02a.i.a, 3.3.00.02a.i.b, 3.3.00.02a.i.c, 3.3.00.02a.i.d, 3.3.00.02a.ii.e, 3.3.00.02a.ii.f, and 3.3.00.04b in Table 3.3-6 to provide criteria that ensures that
radiation shielding function and structural integrity remain appropriate and the facility has been constructed and will be operated in accordance with the design and all relevant requirements.
Regulatory Basis 10 CFR Part 50, Appendix A, General Design Criterion (GDC) 2, Design Bases for Protection against Natural Phenomena, requires that SSCs important to safety shall be designed to withstand the effects of natural phenomena such as earthquakes, tornadoes, hurricanes, floods, tsunami, and seiches without loss of capability to perform their safety functions.
GDC 4, Environmental and Dynamic Effects Design Bases, requires that SSCs important to safety shall be designed to accommodate the effects of and to be compatible with the environmental conditions associated with normal operation, maintenance, testing and postulated accidents, including loss-of-coolant accidents.
GDC 61, requires that the fuel storage and handling, radioactive waste, and other systems which may contain radioactivity shall be designed to assure adequate safety under normal and postulated accident conditions. These systems shall be designed (1) with a capability to permit appropriate periodic inspection and testing of components important to safety (2) with suitable shielding for radiation protection, and (3) with appropriate containment, confinement, and filtering systems.
10 CFR 52.80(a) requires that the application must contain the proposed inspections, tests, and analyses, that the licensee shall perform, and the acceptance criteria that are necessary and sufficient to provide reasonable assurance that, if the inspections, tests, and analyses are performed and the acceptance criteria met, the facility has been constructed and will be operated in conformity with the combined license, the provisions of the Act, and the Commission's rules and regulations.