MONTHYEARCNL-23-069, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML22117A1862022-04-29029 April 2022 Exemptions from the Requirements of 10 CFR Part 26, Section 26.205(d)(7) (EPID L-2022-LLE-0017) (Exemption) ML22117A1852022-04-29029 April 2022 Exemptions from the Requirements of 10 CFR Part 26, Section 26.205(d)(7) (EPID L-2022-LLE-0017) (Letter) CNL-22-054, Request for Exemption from Requirements of 10 CFR 26.205(d)(4), 26.205(d)(6) and 26.205(d)(7), Fitness for Duty Programs - Work Hours2022-04-15015 April 2022 Request for Exemption from Requirements of 10 CFR 26.205(d)(4), 26.205(d)(6) and 26.205(d)(7), Fitness for Duty Programs - Work Hours ML20318A0362020-12-0808 December 2020 Exemption from Annual Force-on-Force Exercise Requirement of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel Subsection VI C.3(l)(1) (EPID L-2020-LLE-0179 (COVID-19)) CNL-20-092, Request for an Exemption Regarding Calendar Year 2020 Force-on-Force Exercise2020-11-0404 November 2020 Request for an Exemption Regarding Calendar Year 2020 Force-on-Force Exercise CNL-20-069, Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force Exercises, Due to COVID-19 Pandemic2020-10-14014 October 2020 Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force Exercises, Due to COVID-19 Pandemic ML19112A0522019-07-25025 July 2019 Federal Register Notice: Watts Bar Nuclear Plant, Units 1 and 2 - Exemption from the Requirements of 10 CFR Section 50.46 and Appendix K to 10 CFR Part 50 ML1000604112010-03-0808 March 2010 FRN: General Notice. Watts Bar Nuclear Plant, Units 1 and 2 - Exemption from the Requirements of 10 CFR Part 73, Section 73.55 NRC-2010-0019, FRN: General Notice. Watts Bar Nuclear Plant, Units 1 and 2 - Exemption from the Requirements of 10 CFR Part 73, Section 73.55 (TAC Nos. ME2601 and ME2602)2010-03-0808 March 2010 FRN: General Notice. Watts Bar Nuclear Plant, Units 1 and 2 - Exemption from the Requirements of 10 CFR Part 73, Section 73.55 (TAC Nos. ME2601 and ME2602) ML0531802632005-12-20020 December 2005 One-Time Exemption from NRC Requirements, EP Scheduler Exemption 2023-12-21
[Table view] Category:Letter
MONTHYEARML23319A2452024-01-29029 January 2024 Issuance of Amendment Nos. 366 and 360; 164 and 71 Regarding the Adoption of TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues ML24008A2462024-01-18018 January 2024 Revision to the Reactor Vessel Material Surveillance Capsule Withdrawal Schedule CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions CNL-24-016, Supplement to Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-01-10010 January 2024 Supplement to Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-23-052, Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability2024-01-0909 January 2024 Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability CNL-23-062, Application to Revise the Technical Specifications Section 3.8.2, AC Sources-Shutdown, to Remove Reference to the C-S Diesel Generator (WBN-TS-23-018)2024-01-0808 January 2024 Application to Revise the Technical Specifications Section 3.8.2, AC Sources-Shutdown, to Remove Reference to the C-S Diesel Generator (WBN-TS-23-018) ML23346A1382024-01-0303 January 2024 Regulatory Audit Summary Related to Request to Increase the Number of Tritium Producing Burnable Absorber Rods CNL-23-069, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000390/20234412023-12-21021 December 2023 Plantfinal Significance Determination for a Security-Related Greater than Green Finding, Nov, and Assessment Follow-up, 05000390-2023441 and 05000391-2023441-Public CNL-23-036, Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08)2023-12-18018 December 2023 Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) IR 05000390/20234042023-12-14014 December 2023 Security Baseline Inspection Report 05000390/2023404 and 05000391/2023404 CNL-23-001, Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications (WBN-TS-23-01)2023-12-13013 December 2023 Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications (WBN-TS-23-01) ML23293A0572023-12-0606 December 2023 Issuance of Amendment Nos. 163 and 70 Regarding Adoption of TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control IR 05000390/20230102023-11-30030 November 2023 RE-Issue Watts Bar Nuclear Plant - Biennial Problem Identification and Resolution Inspection Report 050000390/2023010 and 05000391/2023010 and Apparent Violation CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20230032023-11-13013 November 2023 Integrated Inspection Report 05000390/2023003 and 05000391/2023003 and Apparent Violation ML23312A1432023-11-0808 November 2023 Submittal of Dual Unit Updated Final Safety Analysis Report (UFSAR) Amendment 5 CNL-23-059, Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-2023-09-20020 September 2023 Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision ML23251A2002023-09-11011 September 2023 Request for Withholding Information from Public Disclosure for Watts Bar Nuclear Plant, Units 1 and 2 CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000390/20230052023-08-30030 August 2023 Updated Inspection Plan for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2023005 and 05000391/2023005 ML23233A0042023-08-28028 August 2023 Proposed Alternative to the Requirements of the ASME Boiler and Pressure Vessel Code for Upper Head Injection Dissimilar Metal Butt Welds IR 05000390/20230022023-08-16016 August 2023 Reissue - Watts Bar Nuclear Plant - Integrated Inspection Report 05000390/2023002 and 05000391/2023002 ML23220A1582023-08-0909 August 2023 Integrated Inspection Report 05000390/2023002 and 05000391/2023002 CNL-23-045, License Amendment Request to Revise Technical Specification Table 1.1-1 Regarding the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts (WBN-TS-23-010)2023-08-0707 August 2023 License Amendment Request to Revise Technical Specification Table 1.1-1 Regarding the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts (WBN-TS-23-010) CNL-23-028, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06)2023-08-0202 August 2023 Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06) ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information CNL-23-055, Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills2023-07-25025 July 2023 Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills IR 05000390/20230112023-07-24024 July 2023 Quadrennial Focused Engineering Inspection (FEI) Commercial Grade Dedication Report 05000390 2023011 and 05000391 2023011 CNL-23-053, Tennessee Valley Authority - Radiological Emergency Plan Revisions2023-07-18018 July 2023 Tennessee Valley Authority - Radiological Emergency Plan Revisions CNL-23-020, Application to Revise Technical Specifications to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (WBN-TS-22-06)2023-06-28028 June 2023 Application to Revise Technical Specifications to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (WBN-TS-22-06) CNL-23-049, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan .2023-06-26026 June 2023 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan . ML23122A2322023-06-0707 June 2023 Issuance of Amendment Nos. 162 and 69 Regarding Change to Date in Footnotes for Technical Specification 3.7.11, Control Room Emergency Air Temperature Control System (Creatcs) CNL-23-044, Transmittal of Revision 3 to WCAP-18774-P and WCAP-18774-NP, Addendum to the Rotterdam Dockyard Company Final Stress Report for 173 P.W.R. Vessels TVA III & IV (Report No. 30749-B-030, Rev. 3) - Evaluation of One Closure Stud Out2023-06-0101 June 2023 Transmittal of Revision 3 to WCAP-18774-P and WCAP-18774-NP, Addendum to the Rotterdam Dockyard Company Final Stress Report for 173 P.W.R. Vessels TVA III & IV (Report No. 30749-B-030, Rev. 3) - Evaluation of One Closure Stud Out IR 05000390/20234032023-05-30030 May 2023 Cyber Security Inspection Report 05000390/2023403 and 05000391/2023403 ML23131A1812023-05-23023 May 2023 Correction to Amendment No. 161 to Facility Operating License No. NPF-90 CNL-23-042, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-05-16016 May 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20220032023-05-0909 May 2023 Reissue Watts Bar Nuclear Plant - Integrated Inspection Report 05000390/2022003 and 05000391/2022003 ML23125A2202023-05-0505 May 2023 Issuance of Amendment No. 161 Regarding a Change to Footnotes for Technical Specification Table 1.1-1 Modes (Emergency Circumstances) IR 05000390/20230012023-05-0404 May 2023 Integrated Inspection Report 05000390/2023001 and 05000391/2023001 CNL-23-043, Emergency License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes (WBN-TS-23-09)2023-05-0404 May 2023 Emergency License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes (WBN-TS-23-09) CNL-23-032, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 412023-04-27027 April 2023 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 41 CNL-23-030, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update2023-04-27027 April 2023 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-23-033, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-04-24024 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision CNL-23-029, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-04-11011 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23072A0652023-04-0505 April 2023 Units 1 and 2 Issuance of Amendment Nos. 364 and 358; 160 and 68 Regarding a Revision to Technical Specification 3.4.12 ML23073A2762023-04-0303 April 2023 Individual Notice of Consideration of Issuance of Amendments to Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing (EPID L-2023-LLA-0029) (Letter) CNL-23-023, Annual Insurance Status Report2023-03-30030 March 2023 Annual Insurance Status Report CNL-23-024, TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report2023-03-29029 March 2023 TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report 2024-01-09
[Table view] |
Text
December 20, 2005 Mr. Karl W. Singer Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, Tennessee 37402-2801
SUBJECT:
WATTS BAR NUCLEAR PLANT, UNIT 1 ONE-TIME EXEMPTION FROM THE REQUIREMENTS OF 10 CFR PART 50, APPENDIX E, SECTIONS IV.F.2.b and c (TAC NO. MC8592)
Dear Mr. Singer:
The Nuclear Regulatory Commission (NRC) has approved the enclosed exemption from specific requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix E, Sections IV.F.2.b and c for the Watts Bar Nuclear Plant, Unit 1. This action is in response to your letter dated October 5, 2005. You requested an exemption from the requirements of Appendix E, Sections IV.F.2.b and c, which require a licensee at each site to conduct an exercise of its onsite emergency plan and of its offsite emergency plans biennially with full or partial participation by each offsite authority having a role under the plan. The letter requested that the exercise originally planned for November 2, 2005, be rescheduled for June 7, 2006, due to the impact of Hurricane Katrina. The NRC staff understands that future exercises would be scheduled biennially from the year 2005.
A copy of the exemption is being forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Douglas V. Pickett, Senior Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-390
Enclosure:
Exemption cc w/enclosure: See next page
ML053180263 *No Legal Objection NRR-048 OFFICE LPLII-2 PM:LPLII-2 LA:LPLII-2 BC:LPLII-2 NSIR/EP OGC DORL/DD DORL/D CHolden for NAME MVaaler DPickett RSola MMarshall EWeiss JBonanno* CHaney EHackett DATE 11/15/05 11/17/ 05 11/15 / 05 12/19/ 05 11/30/05 12/6/ 05 12/19/05 12/20/05
Mr. Karl W. Singer Tennessee Valley Authority WATTS BAR NUCLEAR PLANT cc:
Mr. Ashok S. Bhatnagar, Senior Vice President Mr. Glenn W. Morris, Manager Nuclear Operations Corporate Nuclear Licensing Tennessee Valley Authority and Industry Affairs 6A Lookout Place Tennessee Valley Authority 1101 Market Street 4X Blue Ridge Chattanooga, TN 37402-2801 1101 Market Street Chattanooga, TN 37402-2801 Mr. Larry S. Bryant, General Manager Nuclear Engineering Mr. Paul L. Pace, Manager Tennessee Valley Authority Licensing and Industry Affairs 6A Lookout Place Watts Bar Nuclear Plant 1101 Market Street Tennessee Valley Authority Chattanooga, TN 37402-2801 P.O. Box 2000 Spring City, TN 37381 Mr. Robert J. Beecken, Vice President Nuclear Support Mr. Jay Laughlin, Plant Manager Tennessee Valley Authority Watts Bar Nuclear Plant 6A Lookout Place Tennessee Valley Authority 1101 Market Street P.O. Box 2000 Chattanooga, TN 37402-2801 Spring City, TN 37381 Mr. Michael D. Skaggs Senior Resident Inspector Site Vice President Watts Bar Nuclear Plant Watts Bar Nuclear Plant U.S. Nuclear Regulatory Commission Tennessee Valley Authority 1260 Nuclear Plant Road P.O. Box 2000 Spring City, TN 37381 Spring City, TN 37381 County Executive General Counsel 375 Church Street Tennessee Valley Authority Suite 215 ET 11A Dayton, TN 37321 400 West Summit Hill Drive Knoxville, TN 37902 County Mayor P. O. Box 156 Mr. John C. Fornicola, Manager Decatur, TN 37322 Nuclear Assurance and Licensing Tennessee Valley Authority Mr. Lawrence E. Nanney, Director 6A Lookout Place Division of Radiological Health 1101 Market Street Dept. of Environment & Conservation Chattanooga, TN 37402-2801 Third Floor, L and C Annex 401 Church Street Ms. Vanessa E. Quinn, Chief Nashville, TN 37243-1532 Radiological Emergency Preparedness Section Department of Homeland Security Ms. Ann P. Harris 1800 S. Bell Street, Room 850 341 Swing Loop Road Crystal City - Arlington, VA 22202-3546 Rockwood, Tennessee 37854
7590-01-P UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION TENNESSEE VALLEY AUTHORITY WATTS BAR NUCLEAR PLANT, UNIT 1 DOCKET NO. 50-390 EXEMPTION
1.0 BACKGROUND
Tennessee Valley Authority (TVA, the licensee) is the holder of Facility Operating License No. NPF-90, which authorizes operation of Watts Bar Nuclear Plant (WBN), Unit 1.
The license provides, among other things, that the facility is subject to all rules, regulations, and orders of the Nuclear Regulatory Commission (NRC) now or hereafter in effect. The facility consists of one pressurized-water reactor located in Rhea County, Tennessee.
2.0 REQUEST/ACTION Sections IV.F.2.b and c of Appendix E to Title 10 of the Code of Federal Regulations (10 CFR) Part 50 require the licensee at each site to conduct an exercise of its onsite emergency plan and of its offsite emergency plans biennially with full or partial participation by each offsite authority having a role under the plan. During such biennial exercises, the NRC evaluates onsite and the Federal Emergency Management Agency (FEMA) evaluates offsite emergency preparedness activities, including interaction with the various State and local emergency management agencies. TVA successfully conducted an exercise at WBN during the week of November 5, 2003.
The licensee had scheduled a plume exposure pathway exercise for November 2, 2005, however, due to Hurricane Katrina, the Tennessee Emergency Management Agency (TEMA)
was unable to support the exercise. Under the current regulations, the licensee would have had until December 31, 2005, to complete their next exercise. Instead, the licensee will conduct an evaluated exercise on June 7, 2006. Future exercises will be scheduled biennially from the year 2005.
The Commission, pursuant to 10 CFR 50.12(a)(1), may grant exemptions from the requirements of 10 CFR Part 50 that are authorized by law, will not present an undue risk to public health and safety, and are consistent with the common defense and security. The Commission, however, pursuant to 10 CFR 50.12(a)(2), will not consider granting an exemption unless special circumstances are present. Under 10 CFR 50.12(a)(2)(ii), special circumstances are present when application of the regulation in the particular circumstances would not serve the underlying purpose of the rule or is not necessary to achieve the underlying purpose of the rule. Under 10 CFR 50.12(a)(2)(v), special circumstances are present whenever the exemption would provide only temporary relief from the applicable regulation and the licensee or applicant has made good faith efforts to comply with the regulation.
3.0 DISCUSSION The underlying purpose for conducting a biennial exercise is to ensure that emergency organization personnel are familiar with their duties and to test the adequacy of emergency plans. In order to accommodate the scheduling of exercises, the NRC has allowed licensees to schedule the exercises at any time during the calendar biennium. Conducting the WBN exercise in calendar year 2006 places the exercise past the previously scheduled biennial calender year of 2005.
Since the last exercise conducted at WBN on November 5, 2003, WBN has conducted four training drills, a full scale plume phase off-year exercise on November 3, 2004, and an integrated training drill on September 28, 2005. The NRC staff considers the intent of this requirement is met by having conducted these series of exercises and drills. The NRC staff
considers that these measures are adequate to maintain an acceptable level of emergency preparedness during this period, satisfying the underlying purpose of the rule. Therefore, the special circumstances of 10 CFR 50.12(a)(2)(ii) are satisfied.
Only temporary relief from the regulation is provided by the requested exemption since WBN will resume their normal biennial exercise schedule in 2007. The licensee has made a good faith effort to comply with the regulation. The exemption is being sought by the licensee in response to a request by TEMA to postpone the exercise. TEMA was unable to support the original schedule for the exercise due to a series of severe weather events. FEMA stated, Based on the impact that the response to Hurricane Katrina had on the State of Tennessee, we are agreeing to the postponement of the Watts Bar Nuclear Plant exercise until June 2006.
The NRC staff, having considered the schedule and resource issues with those agencies that participate in and evaluate the offsite portion of the exercises, concludes that the licensee made a good faith effort to meet the requirements of the regulation. The NRC staff, therefore, concludes that the exemption request meets the special circumstances of 10 CFR 50.12(a)(2)(v) and should be granted.
4.0 CONCLUSION
Accordingly, the Commission has determined that, pursuant to 10 CFR 50.12(a), the exemption is authorized by law, will not present an undue risk to the public health and safety, and is consistent with the common defense and security. Also, special circumstances are present. Therefore, the Commission hereby grants TVA an exemption from the requirements of 10 CFR Part 50, Appendix E, Sections IV.F.2.b and c for WBN, Unit 1.
Pursuant to 10 CFR 51.32, the Commission has determined that the granting of this exemption will not have a significant effect on the quality of the human environment
(70 FR 76470).
This exemption is effective upon issuance.
Dated at Rockville, Maryland, this 20th day of December 2005.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
Catherine Haney, Director Division of Operating Reactor Licensing Office of Nuclear Reactor Licensing