E-Mail from Meyer to Blough, Previous Carper Answers on Salem on Tritium IssueML062700182 |
Person / Time |
---|
Site: |
Salem |
---|
Issue date: |
10/21/2003 |
---|
From: |
Meyer G NRC/RGN-III |
---|
To: |
Barber G, Blough A, Boska J, Clifford J, Robert Fretz, Holden C, Brian Holian, John Jolicoeur, Madden P, Diane Screnci, Vito D, Walker T, Jason White NRC Region 1 |
---|
References |
---|
FOIA/PA-2005-0194 |
Download: ML062700182 (3) |
|
Similar Documents at Salem |
---|
Category:E-Mail
MONTHYEARML24277A0812024-10-0303 October 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon Collected on 10/02/2024 ML24269A0362024-09-24024 September 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 9/24/2024 ML24248A0452024-09-0303 September 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 9/3/2024 ML24229A0422024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Implement Optimized ZIRLO Fuel Rod Cladding ML24229A0432024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Exemption from 10 CFR 50.46 and 10 CFR 50 Appendix K to Allow the Use of Optimized ZIRLO Fuel Rod Cladding ML24228A1942024-08-14014 August 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form for a Live - Atlantic Sturgeon 8/14/2024 ML24227A5092024-08-14014 August 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 8/13/2024 ML24250A0562024-07-11011 July 2024 PSEG to NMFS, Regarding Processing of Fin Clips ML24219A2472024-07-0909 July 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Shortnose Sturgeon 7/9/2024 ML24123A0522024-05-0101 May 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - One Deceased Sturgeon 4/30/2024 ML24106A0542024-04-12012 April 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - One Alive Atlantic Sturgeon 4/12/2024 ML24101A2192024-04-0909 April 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 4/8/24 ML24093A1222024-04-0101 April 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - One Atlantic Sturgeon 4/1/2024 ML24075A1862024-03-14014 March 2024 NRR E-mail Capture - (External_Sender) Biological Opinion Gar 2020-02842 - PSEG Salem and Hope Creek Generating Station Annual Incidental Take Report - 2023 ML24060A0492024-02-28028 February 2024 NRR E-mail Capture - Final Exhb RAI for Hope Creek, Salem 1 and 2 Amendment to Modify Exclusion Area Boundary ML24030A8432024-01-30030 January 2024 NRR E-mail Capture - (External_Sender) 2023 PSEG Sturgeon Pit Tag Data ML24016A1612024-01-10010 January 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms - Two Atlantic Sturgeon 1/9/2024 ML24002A7222023-12-29029 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - 2023 Annual Report - Inspection of the Circulating Water Intake Structure (Cwis) Trash Rack Bars ML24002A7242023-12-28028 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - Sturgeon 12/28/2023 ML23355A2732023-12-21021 December 2023 NRR E-mail Capture - (External_Sender) PSEG Response to Questions Associated with Supplement to Salem-Hope Creek Eab Reduction LAR ML24002A7252023-12-21021 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Shortnose Sturgeon 12/21/23 ML23346A0962023-12-0606 December 2023 NRR E-mail Capture - Reminder - Final Report - Completion of Required Additional Protocol (AP) Information in Accordance with the U.S. - IAEA Treaty Obligations ML23311A0792023-11-0101 November 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Atlantic Sturgeon Collected on 10/31/2023 ML23277A0482023-10-0404 October 2023 NRR E-mail Capture - 10/4/2023 Email: Acceptance Review - Hope Creek and Salem 1 and 2 - LAR to Modify Exclusion Area Boundary ML23277A0732023-09-29029 September 2023 NRR E-mail Capture - (External_Sender) 9/29/2023 Email from PSEG: Supplement to Proposed Amendment to PSEG Master Decommissioning Trust Amendment ML23226A0702023-08-11011 August 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form for Sturgeon Collected on 8/10/2023 ML23226A0732023-08-10010 August 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Submittal of Necropsy Reports Regarding Sea Turtles Collected on 06/12/2022 ML23201A0132023-07-20020 July 2023 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Permanent Extension of Type a and Type C Containment Leak Rate Test Frequencies ML23172A0982023-06-21021 June 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 06/20/2022 ML23164A2062023-06-13013 June 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 06/12/2023 ML23163A0442023-06-0606 June 2023 NRR E-mail Capture - (External_Sender) Biological Opinion GAR-2020-02842; FIN Clip Analysis Facilities ML24250A0572023-06-0606 June 2023 PSEG to NMFS, Request for Sturgeon Fin Clip Analysis Facilities ML23153A1552023-06-0202 June 2023 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 6/1/2023 ML23151A6582023-05-31031 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms Sturgeon 5/30/2023 ML23137A2632023-05-17017 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms Sturgeon 5/16/2023 ML23135A0102023-05-11011 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report Sturgeon 5/11/2023 ML23136B2832023-05-0404 May 2023 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 5/3/2023 ML23122A1982023-05-0202 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms for Atlantic Sturgeon 5/1/2023 ML23122A1672023-05-0202 May 2023 NRR E-mail Capture - Acceptance Review - Hope Creek and Salem 1 and 2 - Revise TS to Delete TS Section 5.5 - Meteorological Tower Location ML23117A2722023-04-17017 April 2023 NRR E-mail Capture - (External_Sender) Salem Generating STATION-INCIDENTAL Take of Atlantic Sturgeon Collected on 04/14/2023 ML23079A0032023-03-17017 March 2023 NRR E-mail Capture - Hope Creek, Salem 1 and 2 - Evacuation Time Estimate Review ML23065A0452023-02-23023 February 2023 NRR E-mail Capture - (External_Sender) Salem & Hope Creek Generating STATIONS-ANNUAL Incidental Take REPORT-STATION & REMP ML23033A0302023-02-0808 February 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report Sturgeon 1/24/2023 ML23010A2882023-01-10010 January 2023 NRR E-mail Capture - (External_Sender) Salem Generating STATION-INCIDENTAL Take of Atlantic Sturgeon Collected on 01/09/2023 ML23003A2412023-01-0303 January 2023 NRR E-mail Capture - Final Nvib RAI - Salem Unit 2 Relief Request S2-I4R-211, Fourth Inservice Inspection (ISI) Interval Limited Examinations ML22357A0102022-12-21021 December 2022 NRR E-mail Capture - Final Nphp RAI - Salem Unit 2 Relief Request S2-I4R-211, Fourth Inservice Inspection (ISI) Interval Limited Examinations ML23003A2402022-12-21021 December 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form for Atlantic Sturgeon Collected on 12/20/2022 ML23003A2392022-12-20020 December 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms for Atlantic Sturgeons Collected 12/19/2022 ML22333A9022022-11-29029 November 2022 NRR E-mail Capture - Final Iolb RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22291A3702022-10-18018 October 2022 NRR E-mail Capture - Acceptance Review - Salem 2 - Relief Request Associated with the Fourth Inservice Inspection (ISI) Interval Limited Examinations (L-2022-LLR-0066) 2024-09-03
[Table view] |
Text
Pri~icifw:Eeviou~s Carper Answers on Salem Tritium Issue Pg From: Glenn Meyer To: A. Randolph Blough; Brian Holian; Cornelius Holden; David Vito; Diane Screnci; James Clifford; John Boska; John Jolicoeur; John White; Robert Fretz; Scott Barber; Thomas Madden; Tracy Walker; Wayne Lanning Date: 10/21/03 9:35AM
Subject:
Fwd: Previous Carper Answers on Salem Tritium Issue Bob Fretz's attached file has answers to Sen. Carper in February. The two questions related to:
- 1. Timeliness of public notification on tritium leak
- 2. Responsibility of licensee to find the problem and address it.
CC: Daniel Orr; Mel Gray; Theodore Wingfield 4\
I Davi Vito-- What We Said Last Time Re: Salemi Tritium Issue Paae 14 W From: Robert Fretz olue To: Meyer, Glenn Date: 10/21103 6:30AM
Subject:
What We Said Last Time Re: Salem Tritium Issue Glenn, Attached is the letter sent to Sen. Voinovich that addressed Sen. Carper's two questions on the Salem tritium issue (pages 2-52). Below are excerpts of our answers:
Bob Answer to Question 1:
On September 18, 2002, Public Service Electric and Gas (PSEG) identified contaminated water leakage into the Unit 1 Auxiliary Building and initiated an investigation. On November 20, 2002, PSEG informed the Salem NRC resident inspectors that the identified water leakage into the Unit I auxiliary building appeared, based on chemical and radiological analyses, to be similar to Unit 1 spent fuel pool water.
Earlier, on October 1, PSEG had mentioned leakage evaluations to the Headquarters Project Manager as part of discussions on outage activities, and that the September 18 problem identification document was within the PSEG corrective action system.
When notified, the NRC resident inspectors initiated a review of PSEG's actions and evaluations regarding the characterization of the leak. Senior regional specialists were sent to the site in early December 2002, to provide additional expertise in evaluating PSEG's actions relative to characterization of this leakage and its potential impact on workers, the public, and the environment. NRC resident and regional specialist oversight continued over the next several months through direct inspection by resident staff, as well as periodic visits and discussions by the regional specialists with PSEG and State of New Jersey representatives. No immediate health or safety concerns were identified for workers, the public, or the environment.
On February 6, 2003, the initial inspection activities were documented on pages 25-26 of the enclosed quarterly resident inspection report (50-272/02-09) for the period ending December 28, 2002. Also, on February 6, 2003, PSEG formally reported to the State of New Jersey its identification of tritium in two onsite wells near the facility. This identification was the first discovery of tritium, external to plant structures, above the State's reporting requirement of 1000 pCi/l.
Consistent with NRC regulations outlined in 10 CFR 50.72, on that same day, PSEG reported to the NRC, in an Event Notification (39566) (enclosed) that it had formally notified the State of New Jersey regarding "a spill of radioactive material, specifically, tritium."
Answer to Question 2:
The licensee has the responsibility to identify and correct problems at its facilities. Licensees are required to have a problem identification and resolution program that provides for: 1) identification of problems; 2) reporting of problems in accordance with established criteria (e.g., NRC, State, and/or internal); 3) implementation of mitigating actions as necessary; 4) evaluation of any consequences of the problem (e.g., effect on workers, public, or the environment); 5) evaluation and determination of causes; 6) determination of risk significance; and 7) implementation of corrective actions commensurate with that risk significance. The basic requirements for these activities are outlined in 10 CFR 50, Appendix B.
Specifically in this case, when the problem was identified, the licensee documented it in its corrective action program, initiated a review of the issue consistent with its understanding of the safety significance of the problem, implemented various mitigation activities to reduce or eliminate potential effects, and reported the issue to the State and the NRC when reporting criteria were met.
'David Vito.-. What We Said Last Time Re: Salem Tritiumn IssuePae2 PSEG has taken actions to identify the source and extent of the leakage, including the drilling of a number of sample wells and evaluating sample data. PSEG has also taken action to collect any further leakage and is directing it into plant waste systems. The licensee is closely monitoring the issue consistent with its corrective action program, and is also undertaking a number of activities associated with identifying permanent repair options to the spent fuel pool. The NRC will continue to evaluate PSEG's activities regarding the root cause for the leak and corrective actions. Further, the NRC has maintained close coordination with the State of New Jersey and will continue to interact frequently with appropriate State officials.
CC: Barber, Scott