Revision of Schedule for the Conduct of Review of the Susquehanna Electric Station, Units 1 & 2, License Renewal Application
ML080850119
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 05/01/2008
From: Gettys E
NRC/NRR/ADRO/DLR
To: Mckinney B
Susquehanna
Gettys Evelyn, NRR/DLR/RLRA 415-4029
References
Download: ML080850119 (6)


Text

May 1, 2008 Mr. Britt T. McKinney Sr. Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION

Dear Mr. McKinney:

Enclosed is a revised schedule for the review of the Susquehanna Steam Electric Station, Units 1 and 2, license renewal application. If you have any questions on the revised schedule, please contact me by telephone at 301-415-4029 or via e-mail at ehg2@nrc.gov.

Sincerely,

/RA/

Evelyn Gettys, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388

Enclosure:

As stated cc w/encl: See next page

ML080580119 OFFICE PM:RPB1:DLR LA:DLR BC:RPB1:DLR BC:RPB1:DLR NAME EGettys SFigueroa DStuyvenberg LLund DATE 03/26/08 03/26/08 03/31/08 05/01/08

SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION REVISION OF SCHEDULE Milestone Schedule Actual Receive license renewal application (LRA) 09/15/06 09/13/06 Publish Federal Register Notice (FRN) - LRA receipt and availability 09/25/06 09/26/06 Publish FRN - LRA acceptability, environmental scoping period, and 10/30/06 10/30/06 opportunity for hearing Public Meeting - license renewal process and environmental scoping 11/15/06 11/15/06 Audit - scoping and screening methodology 12/11-15/06 12/11-15/06 Environmental scoping periods ends 01/02/07 01/02/07 Audit - aging management 05/05/08 Audit - environmental 05/14-18/07 05/15-17/07 Audit - aging management (optional) 6/23/08 Issue environmental requests for additional information (RAIs) 07/13/07 07/13/07 Issue safety RAIs 07/13/08 Receive responses for environmental RAIs 08/13/07 08/01/2007 Receive responses for safety RAIs 08/12/08 Inspection - scoping, screening, and AMPs 08/11/08 Inspection (optional) TBD Issue draft supplemental environmental impact statement (SEIS) 04/25/08 04/25/08 Publish FRN - availability and comment on draft SEIS 05/07/08 Public Meeting - draft SEIS 05/28/08 Issue safety evaluation report (SER) with open item(s) 03/03/09 End of comment period for the draft SEIS 07/21/08 Advisory Committee on Reactor Safeguards (ACRS) subcommittee 04/09 meeting on SER with open item(s)

Issue final SEIS 03/11/09 Issue SER 08/28/09 Publish FRN - availability of final SEIS 03/18/09 ACRS full committee meeting on SER 10/09 NRR decision 12/07/09 ENCLOSURE

Letter to B. McKinney from E. Gettys, dated May 1, 2008 DISTRIBUTION:

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION HARD COPY:

DLR RF E-MAIL:

PUBLIC SSmith (srs3)

SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSrxb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter


EGettys FJaxheimer

Susquehanna Steam Electric Station, Units 1 and 2 cc:

Cornelius J. Gannon Luis A. Ramos Vice President - Nuclear Operations Community Relations Manager, PPL Susquehanna, LLC Susquehanna 769 Salem Blvd., NUCSB3 PPL Susquehanna, LLC Berwick, PA 18603-0467 634 Salem Blvd., SSO Berwick, PA 18603-0467 Robert M. Paley General Manager - Plant Support Bryan A. Snapp, Esq.

PPL Susquehanna, LLC Associate General Counsel 769 Salem Blvd., NUCSB2 PPL Services Corporation Berwick, PA 18603-0467 Two North Ninth Street, GENTW3 Allentown, PA 18101-1179 Rocco R. Sgarro Manager - Nuclear Regulatory Affairs Supervisor - Document Control Services PPL Susquehanna, LLC PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Allentown, PA 18101-1179 Supervisor - Nuclear Regulatory Affairs Richard W. Osborne PPL Susquehanna, LLC Allegheny Electric Cooperative, Inc.

769 Salem Blvd., NUCSA4 212 Locust Street Berwick, PA 18603-0467 P.O. Box 1266 Harrisburg, PA 17108-1266 Michael H. Crowthers Supervising Engineer Director, Bureau of Radiation Protection Nuclear Regulatory Affairs Pennsylvania Department of PPL Susquehanna, LLC Environmental Protection Two North Ninth Street, GENPL4 Rachel Carson State Office Building Allentown, PA 18101-1179 P.O. Box 8469 Harrisburg, PA 17105-8469 Ronald E. Smith General Manager - Site Preparedness Senior Resident Inspector and Services U.S. Nuclear Regulatory Commission PPL Susquehanna, LLC P.O. Box 35, NUCSA4 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0035 Berwick, PA 18603-0467 Regional Administrator, Region 1 Manager - Quality Assurance U.S. Nuclear Regulatory Commission PPL Susquehanna, LLC 475 Allendale Road 769 Salem Blvd., NUCSB2 King of Prussia, PA 19406 Berwick, PA 18603-0467

Susquehanna Steam Electric Station, Units 1 and 2 cc:

Board of Supervisors Salem Township P.O. Box 405 Berwick, PA 18603-0035