MONTHYEARML24031A6432023-12-20020 December 2023 Independent Spent Fuel Storage Installation (ISFSI) - Nuclear Liability Insurance Coverage ML23341A0222023-11-15015 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23192A0612023-06-14014 June 2023 Possession-Only License DPR-45 - Formal Announcement of New ISFSI Manager ML23192A1082023-06-14014 June 2023 Possession-Only License DPR-45 - New Chief Nuclear Officer Selected ML23130A1202023-05-0202 May 2023 Transmittal of Financial Statement and Auditors' Report ML23137A1552023-05-0202 May 2023 Possession-Only License DPR-45 - Financial Statement and Auditors' Report ML23115A1712023-04-0404 April 2023 ISFSI - Nuclear Liability Insurance Coverage ML23115A1742023-04-0303 April 2023 Independent Spent Fuel Storage Installation, Adoption of Amendment 7 of NAC MPC Certificate of Compliance No. 72-1025 and Canister Registration ML23074A0552023-03-13013 March 2023 Decommissioning Funding Status Report for Shutdown Reactor ML23076A0402023-03-0606 March 2023 Notification of License Transfer Date from Lacrossesolutions, LLC to Dairyland Power Cooperative ML23060A0732023-02-27027 February 2023 Annual Radiological Environmental Operating Report ML23055A0282023-02-24024 February 2023 Completion of License Termination Activities and Release of Remaining Class 1 Survey Units from Possession Only License No. DPR-45 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML23024A0122023-01-26026 January 2023 Letter to Energysolutions Transmitting Threshold Determination for Merger/Restructuring ML23033A0682023-01-26026 January 2023 Proof of Financial Protection IR 05000409/20220012022-12-27027 December 2022 NRC Inspection Report No. 05000409/2022001(DRSS) ML22321A3132022-12-0808 December 2022 LACBWR License Transfer Order Fifth Extension Letter ML22335A0852022-11-23023 November 2022 Request for Extension of Order Approving Transfer of the License for the La Crosse Boiling Water Reactor from Lacrossesolutions, LLC, to Dairyland Power Cooperative ML22297A0042022-10-20020 October 2022 Response to October 14, 2022 Request for Additional Information for Class 1 Excavation and Basement Survey Units ML22285A0782022-10-13013 October 2022 NRC Analysis of Energy Solutions' Decommissioning Funding Status Report Docket No. 50-409 ML22278A0282022-10-12012 October 2022 Request for Confirmatory Information Letter Re to the Review of the Class 1 Survey Units ML22269A3902022-09-0707 September 2022 Response to July 5, 2022 Request for Additional Information for Class 1 Excavation and Basement Survey Units ML22230A8012022-08-16016 August 2022 Request for Extension of Order Approving Transfer of the License for the La Crosse Boiling Water Reactor from Lacrossesolutions, LLC, to Dairyland Power Cooperative ML22223A0712022-07-28028 July 2022 Response to June 5, 2022 Request for Additional Information for Class 1 Survey Areas ML22224A1172022-07-14014 July 2022 Possession-Only License DPR-45 Chief Nuclear Officer Selected ML22224A1372022-07-12012 July 2022 Quality Assurance Program Description (Oapd), Revision 31 ML22203A0932022-07-11011 July 2022 Changes to the La Crosse Boiling Water Reactor (LACBWR) ISFSI Physical Security Plan IR 07200046/20224012022-06-0101 June 2022 (Decommissioning) - Independent Spent Fuel Storage Installation Security Inspection Report 07200046/2022401 ML22122A2302022-05-24024 May 2022 Approval to Release Class 2 and Class 3 Survey Units from the Part 50 License ML22146A2002022-05-24024 May 2022 Submittal of Quality Assurance Program Changes ML22123A0822022-04-25025 April 2022 Possession-Only License DPR-45 - Financial Statement and Auditors' Report ML22068A2102022-04-20020 April 2022 Issuance of Amendment No. 77 Approving Independent Spent Fuel Storage Installation Emergency Plan, Revision 40 ML22108A0562022-03-28028 March 2022 Decommissioning Funding Plan for Independent Spent Fuel Storage Installation ML22084A0092022-03-22022 March 2022 Annual Property Insurance Status Report ML22077A0132022-03-15015 March 2022 Report on Status of Decommissioning Funding for Shutdown Reactor ML22069A1282022-03-0808 March 2022 Lacrossesolutions, LLC, La Crosse Boiling Water Reactor (LACBWR) Annual Radiological Environmental Operating Report, Supplemental Letter ML22062B0362022-02-28028 February 2022 Annual Radiological Environmental Operating Report ML22031A1162022-01-26026 January 2022 CFR 50.59 I 10 CFR 72.48 Report of Changes, Tests, and Experiments ML22033A1472022-01-26026 January 2022 Submittal of Decommissioning Plan and Post-Shutdown Decommissioning Activities Report, and License Termination Plan Changes IR 05000409/20210012022-01-0707 January 2022 NRC Inspection Report No. 05000409/2021-001 La Crosse Boiling Water Reactor ML22010A0862022-01-0505 January 2022 Proof of Financial Protection ML21235A1212021-09-0303 September 2021 EPA Phase 2 Closure Letter to B. Lowery, EPA from P. Holahan ML21228A0682021-09-0202 September 2021 Request for Additional Information Related to the ISFSI-Only Emergency Plan ML21228A1062021-08-30030 August 2021 LACBWR License Transfer Order Third Extension Letter ML21230A3302021-08-17017 August 2021 Lacrossesolutions, LLC, Request for Extension of Order Approving Transfer of the License for the La Crosse Boiling Water Reactor ML21131A0852021-04-26026 April 2021 Financial Statement and Auditors' Report ML21126A2152021-04-13013 April 2021 Changes to and Biennial Review of the La Crosse Boiling Water Reactor (LACBWR) ISFSI Physical Security Plan ML21067A3052021-04-0707 April 2021 DFP Close-out Letter for La Crosse ML21084A2172021-03-23023 March 2021 Report on Status of Decommissioning Funding for Shutdown Reactor ML21084A2192021-03-22022 March 2021 Annual Property Insurance Status Report 2023-06-14
[Table view] |
Text
October 20, 2008 Mr. W. L. Berg General Manager Dairyland Power Cooperative 3200 East Avenue S.
P.O. Box 817 La Crosse, WI 54602-0817
SUBJECT:
LA CROSSE BOILING WATER REACTOR (LACBWR) MASTER INSPECTION PLAN - FISCAL YEAR (FY) 2009
Dear Mr. Berg:
In accordance with U.S. NRC Inspection Manual Chapter 2561, Decommissioning Power Reactor Inspection Program, the NRC Region III staff and management have developed a Master Inspection Plan (MIP) for LACBWR. The plan is based on your current performance and schedule of significant decommissioning activities planned for the site from October 2008 through September 2009 (FY2009). The plan outlines how we intend to focus our Regional inspection resources to address significant ongoing decommissioning activities.
Because the FY2009 MIP is based, in part, on your proposed schedule of significant decommissioning activities for FY2009, the plan and the focus of NRC inspection activities may change to reflect a change in your planned decommissioning activities or your performance. In order to ensure that the FY2009 MIP remains current, we request that you keep the Materials Control, ISFI, and Decommissioning Branch staff informed of any significant changes in your proposed schedule of decommissioning activities. You will be informed of any significant changes to the LACBWR FY2009 MIP.
We currently project the Region will conduct an inspection at LACBWR during FY2009 to evaluate spent fuel pool safety and related routine decommissioning activities. Additional inspections will be scheduled as necessary regarding the construction of a large tank in the reactor cavity that will hold the dry fuel storage casks for off-loading the fuel. The Region will also conduct an inspection to evaluate the design and construction of the dry fuel storage pad.
This may involve several onsite observations in addition to in-office review. Following is a list of the inspection procedures we expect to use during our inspections. The specific procedures used during each inspection will depend on the specific decommissioning activities being conducted. Additional inspection procedures may be used or inspections conducted if decommissioning activities warrant.
Security-related inspection activities will be addressed in a separate MIP.
W. Berg Inspection Procedure Inspection Procedure Title IP 36801 Organization, Management and Cost Controls IP 37801 Safety Reviews, Design Changes, and Modifications IP 40801 Self-Assessment, Auditing, and Corrective Action IP 60801 Spent Fuel Pool Safety IP 62801 Maintenance and Surveillance IP 60856 Review of 72.212(b) Evaluations IP 60853 Onsite Fabrication of Components and Construction of an Independent Spent Fuel Storage Installation IP 71801 Decommissioning Performance and Status Review IP 83750 Occupational Radiation Exposure IP 84750 Radioactive Waste Treatment, and Effluent and Environmental Monitoring IP 86750 Solid Radioactive Waste Management and Transportation of Radioactive Materials In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). The NRCs document system is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.
We will gladly discuss any questions you may have regarding these inspection plans. If you have questions, please contact William Snell of my staff at (630) 829-9871.
Sincerely,
/RA/
Christine Lipa, Chief Materials Control, ISFSI, and Decommissioning Branch Docket No. 50-409 License No. DPR-45 cc : Roger Christians, Plant Manager B. D. Burks, P.E., Director, Bureau of Field Operations Spark Burmaster, Coulee Region Energy Coalition State Liaison Officer Chief, Radiation Protection Section, WI Department of Health Social Services, Division of Health DISTRIBUTION:
See next page
Letter to W. L. Berg from Christine Lipa dated October 20, 2008
SUBJECT:
LA CROSSE BOILING WATER REACTOR (LACBWR) MASTER INSPECTION PLAN - FISCAL YEAR (FY) 2009 DISTRIBUTION:
Docket File RIII PRR T. Smith, FSME K. Banovac, FSME N. Orlando, FSME S. Reynolds, RIII S. Barker, RIII RIII PRR DOCUMENT NAME: G:\SEC\Work in progress\LACBWR MIP FY09 Draft.doc X Publicly Available Non-Publicly Available Sensitive X Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME WGSnell:mb PJLee CALipa DATE 10/16/08 10/16/08 10/20/08 OFFICIAL RECORD COPY