MONTHYEARNL-23-0930, Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-09-11011 September 2024 Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program NL-24-0337, Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program2024-09-0909 September 2024 Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program NL-24-0334, 0 to the Updated Final Safety Analysis Report, Technical Specifications Bases Changes, Technical Requirements Manual Changes, License Renewal 10 CFR 54 .37(b) Changes, 10 CFR 50.59 Summary Report & Revised Nrc2024-09-0303 September 2024 0 to the Updated Final Safety Analysis Report, Technical Specifications Bases Changes, Technical Requirements Manual Changes, License Renewal 10 CFR 54 .37(b) Changes, 10 CFR 50.59 Summary Report & Revised Nrc NL-24-0313, Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint Response to Request for Additional Information2024-08-23023 August 2024 Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint Response to Request for Additional Information NL-24-0290, Response to Request for Additional Information Related to Request for Specific Exemption2024-07-26026 July 2024 Response to Request for Additional Information Related to Request for Specific Exemption NL-24-0276, Post-Audit Supplement to License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components2024-07-26026 July 2024 Post-Audit Supplement to License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components NL-24-0261, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20232024-07-19019 July 2024 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2023 NL-24-0260, Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R312024-07-0909 July 2024 Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R31 NL-24-0240, Reactor Core Isolation Cooling (RCIC) System Inoperable Due to Mispositioned Link2024-07-0303 July 2024 Reactor Core Isolation Cooling (RCIC) System Inoperable Due to Mispositioned Link NL-24-0237, Incorrectly Installed Temporary Modification Results in Multiple Conditions Prohibited by Plant Technical Specifications2024-07-0303 July 2024 Incorrectly Installed Temporary Modification Results in Multiple Conditions Prohibited by Plant Technical Specifications NL-24-0143, Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in2024-06-27027 June 2024 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in NL-24-0239, Response to Apparent Violation in NRC Inspection Report 05000321, 366/2024090: EA-23-1392024-06-17017 June 2024 Response to Apparent Violation in NRC Inspection Report 05000321, 366/2024090: EA-23-139 NL-24-0148, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-06-0404 June 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-24-0202, SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations2024-05-24024 May 2024 SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations NL-24-0191, Annual Radiological Environmental Operating Reports for 20232024-05-10010 May 2024 Annual Radiological Environmental Operating Reports for 2023 NL-24-0166, Manual Reactor Trip Due to Loss of Feedwater2024-05-0909 May 2024 Manual Reactor Trip Due to Loss of Feedwater NL-24-0195, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water.2024-05-0707 May 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water. NL-24-0064, Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.52024-05-0303 May 2024 Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.5 NL-24-0165, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20232024-04-25025 April 2024 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2023 NL-24-0157, Incorrectly Installed Temporary Modification Results in a Condition Prohibited by Plant Technical Specifications2024-04-24024 April 2024 Incorrectly Installed Temporary Modification Results in a Condition Prohibited by Plant Technical Specifications NL-24-0026, Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint2024-04-19019 April 2024 Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint NL-24-0144, Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La)2024-04-0909 April 2024 Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La) NL-24-0115, Response to Request for Additional Information Exemption Requests for Physical.2024-04-0404 April 2024 Response to Request for Additional Information Exemption Requests for Physical. NL-24-0116, Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred.2024-03-29029 March 2024 Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred. NL-24-0062, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-03-12012 March 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-24-0089, Correction of Technical Specification Omission2024-03-0909 March 2024 Correction of Technical Specification Omission NL-24-0061, Cycle 32 Core Operating Limits Report Version 12024-03-0101 March 2024 Cycle 32 Core Operating Limits Report Version 1 NL-24-0067, 10 CFR 72.48(d)(2) Biennial Report2024-02-26026 February 2024 10 CFR 72.48(d)(2) Biennial Report NL-24-0051, License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components2024-02-20020 February 2024 License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components NL-24-0042, Response to Request for Additional Information Exemption Requests for Physical Barriers2024-02-13013 February 2024 Response to Request for Additional Information Exemption Requests for Physical Barriers NL-24-0033, Response to Question for Withholding Information from Public Disclosure Exemption Requests for Physical Barriers2024-02-0505 February 2024 Response to Question for Withholding Information from Public Disclosure Exemption Requests for Physical Barriers NL-24-0014, Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical.2024-01-30030 January 2024 Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical. NL-23-0889, Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems2023-12-0606 December 2023 Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems NL-23-0879, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation NL-23-0841, Update to Notice of Intent to Pursue Subsequent License Renewal2023-11-20020 November 2023 Update to Notice of Intent to Pursue Subsequent License Renewal NL-23-0658, Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal2023-08-11011 August 2023 Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal NL-23-0542, CFR 50.46 ECCS Evaluation Model Annual Report for 20222023-08-0909 August 2023 CFR 50.46 ECCS Evaluation Model Annual Report for 2022 NL-23-0624, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2023-08-0404 August 2023 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-23-0566, ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use2023-07-13013 July 2023 ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use NL-23-0555, Request for Exemption from Physical Barrier Requirement2023-07-0707 July 2023 Request for Exemption from Physical Barrier Requirement NL-23-0444, Quality Assurance Topical Report Submittal2023-06-15015 June 2023 Quality Assurance Topical Report Submittal NL-23-0457, ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use2023-06-12012 June 2023 ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use NL-23-0422, Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R272023-05-30030 May 2023 Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R27 NL-23-0383, SNC Response to Regulatory Issue Summary 2023-01:Preparation And.2023-05-19019 May 2023 SNC Response to Regulatory Issue Summary 2023-01:Preparation And. NL-23-0372, Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 20222023-05-10010 May 2023 Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 2022 NL-23-0310, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20222023-04-25025 April 2023 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2022 NL-23-0019, GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2023-04-12012 April 2023 GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI NL-23-0263, Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report2023-04-0505 April 2023 Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report NL-23-0014, Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding2023-03-29029 March 2023 Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding NL-23-0208, Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update2023-03-29029 March 2023 Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update 2024-09-09
[Table view] Category:Status Report
MONTHYEARML24047A2092024-02-22022 February 2024 Calendar Year 2023 Baseline Inspection Completion NL-23-0014, Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding2023-03-29029 March 2023 Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding NL-18-0870, Eighth Six-Month Status Report of the Implementation of the Commission Order with Regard to Requirements for Reliable Hardened Containment Vents (EA-13-109)2018-06-27027 June 2018 Eighth Six-Month Status Report of the Implementation of the Commission Order with Regard to Requirements for Reliable Hardened Containment Vents (EA-13-109) NL-17-1888, Seventh Six-Month Status Report of the Implementation of the Commission Order with Regard to Requirements for Reliable Hardened Containment Vents (EA-13-109)2017-12-0505 December 2017 Seventh Six-Month Status Report of the Implementation of the Commission Order with Regard to Requirements for Reliable Hardened Containment Vents (EA-13-109) NL-17-0778, Sixth Six-Month Status Report of the Implementation of the Commission Order with Regard to Requirements for Reliable Hardened Containment Vents (EA-13-109)2017-06-12012 June 2017 Sixth Six-Month Status Report of the Implementation of the Commission Order with Regard to Requirements for Reliable Hardened Containment Vents (EA-13-109) NL-16-1897, Fifth Six-Month Status Report of the Implementation of the Commission Order with Regard to Requirements for Reliable Hardened Containment Vents (EA-13-109)2016-12-14014 December 2016 Fifth Six-Month Status Report of the Implementation of the Commission Order with Regard to Requirements for Reliable Hardened Containment Vents (EA-13-109) NL-16-1050, Seventh Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049)2016-08-0808 August 2016 Seventh Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049) NL-16-0726, Fourth Six-Month Status Report of the Implementation of the Commission Order with Regard to Requirements for Reliable Hardened Containment Vents (EA-13-109)2016-06-13013 June 2016 Fourth Six-Month Status Report of the Implementation of the Commission Order with Regard to Requirements for Reliable Hardened Containment Vents (EA-13-109) NL-16-0025, Sixth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Reliable Spent Fuel Pool Instrumentation (EA-12-051)2016-02-25025 February 2016 Sixth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Reliable Spent Fuel Pool Instrumentation (EA-12-051) NL-16-0023, Sixth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049)2016-02-25025 February 2016 Sixth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049) NL-15-2121, Third Six-Month Status Report of the Implementation of the Commission Order with Regard to Requirements for Reliable Hardened Containment Vents (EA-13-109)2015-12-23023 December 2015 Third Six-Month Status Report of the Implementation of the Commission Order with Regard to Requirements for Reliable Hardened Containment Vents (EA-13-109) NL-15-1154, Fifth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Reliable Spent Fuel Pool Instrumentation (EA-12-051)2015-08-27027 August 2015 Fifth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Reliable Spent Fuel Pool Instrumentation (EA-12-051) NL-15-1157, Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049)2015-08-27027 August 2015 Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049) NL-15-0698, Second Six-Month Status Report of the Implementation of the Commission Order with Regard to Requirements for Reliable Hardened Containment Vents (EA-13-109)2015-06-26026 June 2015 Second Six-Month Status Report of the Implementation of the Commission Order with Regard to Requirements for Reliable Hardened Containment Vents (EA-13-109) NL-15-0244, Fourth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049)2015-02-26026 February 2015 Fourth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049) NL-15-0240, Fourth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Reliable Spent Fuel Pool Instrumentation (EA-12-051)2015-02-26026 February 2015 Fourth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Reliable Spent Fuel Pool Instrumentation (EA-12-051) NL-14-1839, E. I. Hatch, Units 1 and 2, First Six-Month Status Report of the Implementation of the Commission Order with Regard to Requirements for Reliable Hardened Containment Vents (EA-13-109)2014-12-30030 December 2014 E. I. Hatch, Units 1 and 2, First Six-Month Status Report of the Implementation of the Commission Order with Regard to Requirements for Reliable Hardened Containment Vents (EA-13-109) NL-14-1110, Third Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Reliable Spent Fuel Pool Instrumentation (EA-12-051)2014-08-26026 August 2014 Third Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Reliable Spent Fuel Pool Instrumentation (EA-12-051) NL-13-1763, First Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049)2013-08-27027 August 2013 First Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049) NL-13-1766, First Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Reliable Spent Fuel Pool Instrumentation (EA-12-051)2013-08-27027 August 2013 First Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Reliable Spent Fuel Pool Instrumentation (EA-12-051) NL-12-2144, Southern Nuclear Operating Company'S Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents (Order Number EA-12-050)2012-10-23023 October 2012 Southern Nuclear Operating Company'S Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents (Order Number EA-12-050) NL-12-2151, Southern Nuclear Operating Company'S Initial Status Report in Response to 3/12/2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)2012-10-23023 October 2012 Southern Nuclear Operating Company'S Initial Status Report in Response to 3/12/2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) NL-12-2146, Southern Nuclear Operating Company'S Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2012-10-23023 October 2012 Southern Nuclear Operating Company'S Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events NL-09-0442, Updated Request for Extension of 10 CFR 50 Appendix R Enforcement Discretion2009-03-20020 March 2009 Updated Request for Extension of 10 CFR 50 Appendix R Enforcement Discretion 2024-02-22
[Table view] |
Text
Southern Nuclear Operating Company, Inc.
Post Office Box 1295 Birmll1fJllarn, Alabarlld 352011295 rei 20~)992S000 March 20, 2009 SOUTHERN'\.
COMPANY E1Iergy to Serve ~our World Docket Nos.: 50-321 NL-09-0442 50-366 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Edwin I. Hatch Nuclear Plant Updated Request for Extension of 10 CFR 50 Appendix R Enforcement Discretion Ladies and Gentlemen:
This letter supersedes the March 6, 2009 Southern Nuclear Operating Company (SNC) letter on this topic to provide additional information on interim compensatory operator manual actions and to update the status of modifications being made to eliminate these manual actions.
Regulatory Issue Summary (RIS) 2006-10, "Regulatory Expectations with Appendix R Paragraph III.G.2 Operator Manual Actions" was issued on June 30, 2006 to clarify NRC expectations with regard to compliance with 10 CFR 50 Appendix R, III.G.2 requirements. NRC has been exercising enforcement discretion over the use of operator manual actions in order to allow licensees to come into compliance, as described in Enforcement Guidance Memoranda EGM 98-02, Rev. 2 (February 2,2000) and EGM-07-004 (June 30,2007), with March 6, 2009 specified as the date for the completion of corrective actions.
Non-compliant operator manual actions were first identified at Units 1 & 2 of the Edwin I. Hatch Nuclear Plant (HNP) during the 2003 Triennial Fire Protection Inspection. SNC initiated a condition report (CR 2003110070) on this issue, which the resultant inspection reports, (05000321/2003006 and 0500036612003006, September 1, 2003) characterized as a non-cited violation (NCV 50-366/03-06-04).
SNC initially disputed this NCV in a letter dated October 1, 2003 but in early 2006 the NRC denied the request to withdraw the NCV. As a result of the denial, SNC reopened CR 2003110070 to complete root cause and corrective action (RCCA) determination, including a broadness review which identified additional manual action issues.
SNC originally planned to submit exemption requests addressing these manual actions, as provided by EGM-07-004. However, based on SNC's monitoring of industry and NRC enforcement actions, including revised guidance on manual actions, a more conservative approach was established. SNC initiated design
U. S. Nuclear Regulatory Commission NL-09-0442 Page 2 modifications to eliminate all non-compliant operator manual actions. These design modifications (described in Enclosure 1) involve physical modifications to the plant, including inside the Main Control Room, which require a unit outage for implementation.
While the Unit 2 changes will be completed during the refueling outage now in progress on that unit, the timing of design change development with respect to the 24 month HNP operating cycle did not permit change implementation during the 2008 Unit 1 refueling outage. These changes can not be completed until the next Unit 1 refueling outage, in spring 2010.
The interim compensatory manual operator actions to be eliminated by design modifications at HI\JP Unit 1 are listed in Enclosure 1, which has been revised from the March 6, 2009 letter to reflect completion of the design modifications to eliminate manual actions in Fire Areas 1104 and 1205 and the expected spring 2010 completion for the design modifications to eliminate manual actions in Fire Area 0014, as well as to provide additional descriptive information. Each of the remaining five compensatory manual operator actions has been walked down to assure its feasibility and the operator manual actions are contained in plant procedures.
Accordingly, SNC requests an extension of enforcement discretion with respect to the requirements of 10 CFR 50, Appendix R, III.G.2 for the five pending interim compensatory operator manual actions for HNP Unit 1 identified in Enclosure 1, to encompass a period of approximately 12 months, i.e. to the end of the next Unit 1 outage, currently scheduled for March 17, 2010. This extension would allow the continued use of operator manual actions, as described in Enclosure 1, to achieve and maintain hot shutdown conditions in lieu of compliance with the cable separation criteria of Section III.G.2.
The NRC commitments contained in this letter are unchanged from the March 6, 2009 letter and are provided as a table in Enclosure 2. If you have any questions, please advise.
Sincerely,
~9r M. J. Ajluni Manager, Nuclear Licensing MJAlDWD/phr
Enclosures:
- 1. HNP Unit 1 - Status of App. R Operator Manual Action Elimination
- 2. NRC Commitments - List of Regulatory Commitments
- u. S. Nuclear Regulatory Commission NL-09-0442 Page 2 cc: Southern Nuclear Operating Company Mr. J. T. Gasser, Executive Vice President Mr. D. R. Madison, Vice President - Hatch Mr. D. H. Jones, Vice President - Engineering RTYPE: CHA02.004 U. S. Nuclear Regulatory Commission Mr. L. A. Reyes, Regional Administrator Mr. R. E. Martin, NRR Project Manager - Hatch Mr. J. A. Hickey, Senior Resident Inspector - Hatch
Edwin I. Hatch Nuclear Plant Request for Extension of 10 CFR 50 Appendix R Enforcement Discretion Enclosure 1 HNP Unit 1 - Status of App. R Operator Manual Action Elimination
Enclosure 1 HNP Unit 1 Status of App. R Operator Manual Action Elimination Fire Operator Description of Modification Area Manual Action DesiQn Modification Status Generic Close the 3 AC supply breakers to the Install control switches in the Implement battery charger switches on 600V Main Control Room Spring 2010 switchgear control panel 1H21-P245, Outage per procedure 34AB-X43-001-1. Enforcement Access through Fire Area 0014 is discretion required within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. requested Generic Close the 3 AC supply breakers to the Install control switches in the Implement battery charger switches on 600V Main Control Room Spring 2010 switchgear control panel 1H21-P246, Outage per procedure 34AB-X43-001-1. Enforcement Access through Fire Area 0014 is discretion required within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. requested 0014 Open breaker 21 in 1R25-S002 and Reroute cables out of Implement verify closed or close the breakers in unprotected trays in area. Spring 2010 Frames 8B, 8M and 8T of 1R23-S004, Outage per procedure 34AB-X43-001-1. No Enforcement access through a fire-affected area is discretion required. reauested 0014 Open 30-A breaker SA in -I R23-S004, Reroute cables out of Implement Frame 8, and verify closed or close unprotected trays in area. Spring 2010 1R23-S004 Frame 4B, per procedure Outage 34AB-X43-001-1. No access through Enforcement a fire-affected area is required. discretion requested 1101 If unable to close or verify position, Install interposing relay to isolate Implement use handwheel to manually close circuit. Spring 2010 valve 1P41-F31 OB per procedure Outage 34AB-X43-001-1. No access through Enforcement a fire-affected area is required. discretion requested 1104 Rack out breaker 17B in MCC 1R24 Install new cable in dedicated S012 and manually reopen E51-F105 conduit. Complete prior to RCIC restart. (No longer needed since new cable installed.)
1205 Rack out breaker in 1R23-S004 Install new cable in dedicated Frame 6M and manually reopen E51 conduit. Complete F105 prior to RCIC restart. (No longer needed since new cable installed.)
E1-1
Edwin I. Hatch Nuclear Plant Request for Extension of 10 CFR 50 Appendix R Enforcement Discretion Enclosure 2 NRC Commitments - List of Regulatory Commitments
Enclosure 2 NRC Commitments List of Regulatory Commitments The following table identifies the regulatory commitments in this document. Any other statements in this submittal represent intended or planned actions. They are provided for information purposes and are not considered to be regulatory commitments.
REGULATORY COMMITMENTS DUE DATE I EVENT
[1.] SNC will implement design changes End of HNP Unit 1 to eliminate operator manual spring 2010 outage, actions not in compliance with 10 currently scheduled for CFR 50 Appendix R, III.G.2 March 17,2010.
requirements, as described in Enclosure 1 of this submittal.
E2-1