2010-10-Draft Outline Comments
ML102070183
Person / Time
Site: Waterford Entergy icon.png
Issue date: 07/26/2010
From: Apger G
Operations Branch IV
To:
Entergy Operations
References
50-382/10-302 50-382/10-302
Download: ML102070183 (2)


Text

DRAFT OUTLINE COMMENTS Facility: Waterford 3 First Exam Date: October 4, 2010 (OP)

Written Exam Outline (7-13-10)

Comment Resolution RO T2G1 KA reselected 1 System 062: Generic 2.2.17 is not in the list of KAs in ES-401 D.1.b. Reselect.

RO T1G2 KA reselected 2 EAPE 076: Generic 2.1.14 is not in the list of KAs in ES-401 D.1.b. Reselect.

SRO T2G2 KA reselected 3 System 076: Generic 2.4.22 is not in the list of KAs in ES-401 D.1.b. Reselect.

Administrative JPM Outline (7-12-10)

Comment Resolution Every exam has had an EP classification No action required. Note to facility only.

1 (back to 2006). Ensure this is unique when submitting the draft JPM.

Control Room / In-Plant System JPM Outline (7-12-10)

Comment Resolution 1 S1-Used on 2009 Exam (P) Comment only. No action required.

2 S4-Used on 2009 Exam (P) Comment only. No action required.

3 S6-Used on 2010 Re-take (P) Comment only. No action required.

4 P3-Modified from 2010 Retake JPM Comment only. No action required.

Simulator Scenario Outline Comments (7-13-10)

Comment Resolution A) Event 5 should be split out. The SEE MARKUP pdf file.

component malfunction is a Comments incorporated separate event.

Sc1 B) Events 8 and 9 are not events (component malfunctions). They are actions required by OBDI 202 - IOLE Process

procedure for the 2nd major event. One is a critical task. The other annotates the wrong generator.

C) Second critical task depends on break size. Need to maintain pressure above 945psig or this is no longer a CT.

A) Post trip events are the same as Did not use this in 2009.

scenario 2 on the 2009 exam as Scenario OK as is.

well as the initial conditions.

Swap out-of-service train and Sc2 faulted EDG. Change the starting power.

B) Missing horizontal borders between events 2,3 and 4,5.

A) Change this to start at the critical LOW POWER MODE 3 hold (1E-8 [Westinghouse Events changed and comments incorporated parlance]), and require rods to be bumped out to establish SUR and bring Rx to POAH; then hold Sc3 at Mode 2 power.

B) Once there, fail a steam dump, TDAFWP or something to give a positive reactivity excursion, requiring action to prevent transition to Mode 1.

A) Can we let the condition in event Comments incorporated 5 degrade until tripping the pump is required? After SPTA has been entered, initiate event 6.

Sc4 B) Horizontal borders missing.