MONTHYEARML24277A0812024-10-0303 October 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon Collected on 10/02/2024 ML24269A0362024-09-24024 September 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 9/24/2024 ML24248A0452024-09-0303 September 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 9/3/2024 ML24229A0422024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Implement Optimized ZIRLO Fuel Rod Cladding ML24229A0432024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Exemption from 10 CFR 50.46 and 10 CFR 50 Appendix K to Allow the Use of Optimized ZIRLO Fuel Rod Cladding ML24228A1942024-08-14014 August 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form for a Live - Atlantic Sturgeon 8/14/2024 ML24227A5092024-08-14014 August 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 8/13/2024 ML24250A0562024-07-11011 July 2024 PSEG to NMFS, Regarding Processing of Fin Clips ML24219A2472024-07-0909 July 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Shortnose Sturgeon 7/9/2024 ML24123A0522024-05-0101 May 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - One Deceased Sturgeon 4/30/2024 ML24106A0542024-04-12012 April 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - One Alive Atlantic Sturgeon 4/12/2024 ML24101A2192024-04-0909 April 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 4/8/24 ML24093A1222024-04-0101 April 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - One Atlantic Sturgeon 4/1/2024 ML24075A1862024-03-14014 March 2024 NRR E-mail Capture - (External_Sender) Biological Opinion Gar 2020-02842 - PSEG Salem and Hope Creek Generating Station Annual Incidental Take Report - 2023 ML24060A0492024-02-28028 February 2024 NRR E-mail Capture - Final Exhb RAI for Hope Creek, Salem 1 and 2 Amendment to Modify Exclusion Area Boundary ML24030A8432024-01-30030 January 2024 NRR E-mail Capture - (External_Sender) 2023 PSEG Sturgeon Pit Tag Data ML24016A1612024-01-10010 January 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms - Two Atlantic Sturgeon 1/9/2024 ML24002A7222023-12-29029 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - 2023 Annual Report - Inspection of the Circulating Water Intake Structure (Cwis) Trash Rack Bars ML24002A7242023-12-28028 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - Sturgeon 12/28/2023 ML23355A2732023-12-21021 December 2023 NRR E-mail Capture - (External_Sender) PSEG Response to Questions Associated with Supplement to Salem-Hope Creek Eab Reduction LAR ML24002A7252023-12-21021 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Shortnose Sturgeon 12/21/23 ML23346A0962023-12-0606 December 2023 NRR E-mail Capture - Reminder - Final Report - Completion of Required Additional Protocol (AP) Information in Accordance with the U.S. - IAEA Treaty Obligations ML23311A0792023-11-0101 November 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Atlantic Sturgeon Collected on 10/31/2023 ML23277A0482023-10-0404 October 2023 NRR E-mail Capture - 10/4/2023 Email: Acceptance Review - Hope Creek and Salem 1 and 2 - LAR to Modify Exclusion Area Boundary ML23277A0732023-09-29029 September 2023 NRR E-mail Capture - (External_Sender) 9/29/2023 Email from PSEG: Supplement to Proposed Amendment to PSEG Master Decommissioning Trust Amendment ML23226A0702023-08-11011 August 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form for Sturgeon Collected on 8/10/2023 ML23226A0732023-08-10010 August 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Submittal of Necropsy Reports Regarding Sea Turtles Collected on 06/12/2022 ML23201A0132023-07-20020 July 2023 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Permanent Extension of Type a and Type C Containment Leak Rate Test Frequencies ML23172A0982023-06-21021 June 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 06/20/2022 ML23164A2062023-06-13013 June 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 06/12/2023 ML23163A0442023-06-0606 June 2023 NRR E-mail Capture - (External_Sender) Biological Opinion GAR-2020-02842; FIN Clip Analysis Facilities ML24250A0572023-06-0606 June 2023 PSEG to NMFS, Request for Sturgeon Fin Clip Analysis Facilities ML23153A1552023-06-0202 June 2023 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 6/1/2023 ML23151A6582023-05-31031 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms Sturgeon 5/30/2023 ML23137A2632023-05-17017 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms Sturgeon 5/16/2023 ML23135A0102023-05-11011 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report Sturgeon 5/11/2023 ML23136B2832023-05-0404 May 2023 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 5/3/2023 ML23122A1982023-05-0202 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms for Atlantic Sturgeon 5/1/2023 ML23122A1672023-05-0202 May 2023 NRR E-mail Capture - Acceptance Review - Hope Creek and Salem 1 and 2 - Revise TS to Delete TS Section 5.5 - Meteorological Tower Location ML23117A2722023-04-17017 April 2023 NRR E-mail Capture - (External_Sender) Salem Generating STATION-INCIDENTAL Take of Atlantic Sturgeon Collected on 04/14/2023 ML23079A0032023-03-17017 March 2023 NRR E-mail Capture - Hope Creek, Salem 1 and 2 - Evacuation Time Estimate Review ML23065A0452023-02-23023 February 2023 NRR E-mail Capture - (External_Sender) Salem & Hope Creek Generating STATIONS-ANNUAL Incidental Take REPORT-STATION & REMP ML23033A0302023-02-0808 February 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report Sturgeon 1/24/2023 ML23010A2882023-01-10010 January 2023 NRR E-mail Capture - (External_Sender) Salem Generating STATION-INCIDENTAL Take of Atlantic Sturgeon Collected on 01/09/2023 ML23003A2412023-01-0303 January 2023 NRR E-mail Capture - Final Nvib RAI - Salem Unit 2 Relief Request S2-I4R-211, Fourth Inservice Inspection (ISI) Interval Limited Examinations ML22357A0102022-12-21021 December 2022 NRR E-mail Capture - Final Nphp RAI - Salem Unit 2 Relief Request S2-I4R-211, Fourth Inservice Inspection (ISI) Interval Limited Examinations ML23003A2402022-12-21021 December 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form for Atlantic Sturgeon Collected on 12/20/2022 ML23003A2392022-12-20020 December 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms for Atlantic Sturgeons Collected 12/19/2022 ML22333A9022022-11-29029 November 2022 NRR E-mail Capture - Final Iolb RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22291A3702022-10-18018 October 2022 NRR E-mail Capture - Acceptance Review - Salem 2 - Relief Request Associated with the Fourth Inservice Inspection (ISI) Interval Limited Examinations (L-2022-LLR-0066) 2024-09-03
[Table view] |
Text
1<~
Conte, Richard From: OHara, Timothy Sent: Tuesday, May 04, 2010 9:21 AM To: Tsao, John Cc: Conte, Richard
Subject:
RE: Salem--PSEG caics John, Presently, PSEG has committed to inspecting Unit 2 in the next outage, spring 2011. However, we did inform them last week that they need a structural integrity evaluation for Unit 2, not just an operability evaluation.
We will probably just debrief from the ISI tomorrow and leave the inspection open for several specific items which PSEG has not addressed. At present I believe there will be a violation for not performing the IWA-5244 required pressure tests for both Unit 1 and 2. We are evaluating several other issues for enforcement.
Tim OHara From: Tsao, John Sent: Tuesday, May 04, 2010 6:52 AM To: OHara, Timothy
Subject:
Salem--PSEG calcs Tim, Thanks. By the way, what is the status of your inspection for the Salem units? When is your exit meeting?
You are going to give the licensee some sort of violation for Unit 2? Do you think the licensee will dig up some portion of unit 2 buried AFW piping and inspect in the next refueling outage?
John From: OHara, Timothy X Sent: Monday, May 03, 2010 3:42 PM To: Manoly, Kamal; Tsao, John Cc: Lupold, Timothy; Conte, Richard
Subject:
FW:
Kamal & John, Attached is the PSEG calc. which goes with the SAI analysis.
Tim OHara From: Berrick, Howard G. [1]
Sent: Monday, May 03, 2010 3:26 PM To: OHara, Timothy
Subject:
FW:
Calculation 6S0-1882 R1 attached Howard Berrick PSEG Nuclear LLC Salem Regulatory Assurance ftwlamat K"J inthis recod w,. delete in 1
- aolvnce n4th A t.0 r .o. Ir,.matm Act FOtA/PA -- (O - ".'2 '-
PSEG Nuclear - Salem Generating Stations (W) 856-339-1862 (Fax) R ,-139-144 (Bpr) (b)(6) (4 2