ML14349A793

From kanterella
Revision as of 19:34, 31 October 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search

FW: Request for Additional Information (RAI) Regarding Browns Ferry Units 1, 2, and 3 Alignment of Inservice Inspection (ASME Section XI) Intervals (MF4854, MF4855, and MF4856)
ML14349A793
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 12/15/2014
From: Farideh Saba
Plant Licensing Branch II
To: Gerald Williams
Tennessee Valley Authority
References
TAC MF4854, TAC MF4855, TAC MF4856
Download: ML14349A793 (2)


Text

NRR-PMDAPEm Resource From: Saba, Farideh Sent: Monday, December 15, 2014 12:59 PM To: Williams, Gordon Robert (grwilliams1@tva.gov)

Cc: Pfefferkorn, Candace

Subject:

FW: Request for Additional Information (RAI) Regarding Browns Ferry Units 1, 2, and 3 Alignment of Inservice Inspection (ASME Section XI) Intervals (MF4854, MF4855, and MF4856)

Importance: High

Gordon, By letter Dated September 12, 2014 (Agency Wide Document Access and Management System (ADAMS)

Accession Number ML14260A365), the Tennessee Valley Authority (the licensee) submitted relief request ISI-

45. The licensee is requesting an alternative, pursuant to Title 10 of the U.S. Code of Federal Regulations (CFR) Part 50, Section 55a, Paragraph (a)(3)(i), from inservice inspection (ISI) requirements pertaining to Section XI of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, so as to align the three separate ISI interval dates of the three Browns Ferry Nuclear Plant units to a single ten-year inspection interval date.

The U.S. Nuclear Regulatory Commission staff requests that the licensee provide the following additional information to support the relief request by January 30, 2015, as agreed to during the clarification conference call on December 15, 2014.

RAI-1 Describe the process for rescheduling the remaining in-service inspections for each unit to meet the proposed modified end of the current ten-year inspection intervals. As examples, show the original schedule for the Category R-A item number 1.16 and Augmented Exam Category D inspections for Browns Ferry Unit 2 for the next two refueling outages and how they would be rescheduled if the inspection interval is modified.

Thanks, Farideh Farideh E. Saba, P.E.

Senior Project Manager NRC/ADRO/NRR/DORL 301-415-1447 Mail Stop O-8G9A Farideh.Saba@NRC.GOV 1

Hearing Identifier: NRR_PMDA Email Number: 1761 Mail Envelope Properties (36CF286628C20846A68047F2463233090125EF720A3B)

Subject:

FW: Request for Additional Information (RAI) Regarding Browns Ferry Units 1, 2, and 3 Alignment of Inservice Inspection (ASME Section XI) Intervals (MF4854, MF4855, and MF4856)

Sent Date: 12/15/2014 12:59:11 PM Received Date: 12/15/2014 12:59:13 PM From: Saba, Farideh Created By: Farideh.Saba@nrc.gov Recipients:

"Pfefferkorn, Candace" <Candace.Pfefferkorn@nrc.gov>

Tracking Status: None "Williams, Gordon Robert (grwilliams1@tva.gov)" <grwilliams1@tva.gov>

Tracking Status: None Post Office: HQCLSTR02.nrc.gov Files Size Date & Time MESSAGE 1576 12/15/2014 12:59:13 PM Options Priority: High Return Notification: No Reply Requested: Yes Sensitivity: Normal Expiration Date:

Recipients Received: