MONTHYEARIR 05000397/20240052024-08-22022 August 2024 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2024005) IR 05000397/20230062024-02-28028 February 2024 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2023006) ML24032A2182023-09-0101 September 2023 Information Request, Security IR 2024401 IR 05000397/20230052023-08-22022 August 2023 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2023005) - Mid Year Letter IR 05000397/20220062023-03-0101 March 2023 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2022006) ML23019A2482023-01-19019 January 2023 Inservice Inspection Request for Information ML22242A1082022-08-30030 August 2022 Information Request, Information Request, Security IR 2022404 ML22230C7392022-08-23023 August 2022 2022 Mid-Cycle Planning Letter IR 05000397/20210062022-03-0202 March 2022 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2021006) ML21277A3572021-10-12012 October 2021 CGS Brq RFI Letter, Columbia Generating Station - Notification of Inspection (NRC Inspection Report 05000397/2021004) and Request for Information ML21230A3892021-09-0101 September 2021 Mid-Cycle Inspection Plan Transmittal Letter 2021 ML21111A0282021-04-21021 April 2021 _ Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000397/2021011) and Request for Information ML21104A3032021-04-0808 April 2021 Inspection Report 05000397/2021010, Information Request Biennial Problem Identification and Resolution Inspection ML21082A3042021-03-23023 March 2021 Request for Information: Columbia Generating Station, Dated March 11, 2021, Inspection Report 05000397/2021-002, Occupational Radiation Safety Inspection-1,2,3,PI IR 05000397/20200062021-03-0303 March 2021 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2020006) ML20353A1822020-12-18018 December 2020 Notification of NRC Triennial Heat Exchanger/Heat Sink Performance Inspection (05000397/2021001) and Request for Information IR 05000397/20200052020-09-0101 September 2020 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2020005) IR 05000397/20190062020-03-0303 March 2020 CGS2019006 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2019006) ML20049H2622020-02-18018 February 2020 Notification of Cyber Security Inspection (NRC Inspection Report 05000397/2020401) and Request for Information ML19266A5922019-09-23023 September 2019 Notification of Inspection (NRC Inspection Report 05000397/2019004) and Request for Information IR 05000397/20190052019-08-30030 August 2019 Updated Inspection Plan for Columbia Generating Station, Report 05000397/2019005 ML19100A4242019-04-10010 April 2019 Columba - Notification of NRC Design Bases Assurance Inspection Report (Teams) (05000397/2019011) and Initial Request for Information IR 05000397/20180062019-03-0404 March 2019 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2018006 ML18313A0942018-11-0808 November 2018 Notification of NRC Triennial Heat Sink Performance Inspection Report 05000397/2018004) and Request for Information IR 05000397/20180052018-08-31031 August 2018 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2018005) IR 05000397/20170062018-03-0101 March 2018 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2017006) IR 05000397/20170052017-08-28028 August 2017 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2017005) IR 05000397/20160062017-03-0101 March 2017 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2016006) ML16256A2682016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for Columbia Generating Station (Report 05000483/2016005) ML16251A1342016-09-0707 September 2016 Notification of Inspection (NRC Integrated Inspection Report 05000397/2016004) and Request for Information ML16239A2412016-08-31031 August 2016 Mid-Cycle Assessment Letter for Columbia Generating Station (Report 05000483/2016005) IR 05000397/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for Columbia Generating Station (NRC Physical Security Inspection Report Number 05000397/2016401) IR 05000397/20150062016-03-0202 March 2016 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2015006) ML16061A5662016-03-0101 March 2016 Notification of Design Bases Inspection (Programs)(Inspection Report 05000397/2016008) and Initial Request for Information ML16061A5542016-03-0101 March 2016 Notification of NRC Design Bases Inspection (05000397/2016007) and Initial Request for Information IR 05000397/20154012015-09-0101 September 2015 Non-Public Security Inspection Plan for Columbia Generating Station (NRC Physical Security Inspection Report Number 05000397/2015401) IR 05000397/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Columbia Generating Station (Report 05000397/2015005) IR 05000397/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for Columbia Generating Station (NRC Physical Security Inspection Report Number 05000397/2014402) IR 05000397/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Columbia Generating Station (Report 05000397/2014006) ML14219A7512014-08-0707 August 2014 Notification of Evaluations of Changes, Tests, and Experiments, and Permanent Plant Modifications Inspection (05000397-14-005) and Request for Information IR 05000397/20130012014-03-0404 March 2014 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2013001) IR 05000397/20130062013-09-0303 September 2013 Mid-Cycle Assessment Letter Columbia Generating Station (Report 05000397-13-006) IR 05000397/20128012013-03-0404 March 2013 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2012801) IR 05000397/20120062012-09-0404 September 2012 Mid-Cycle Assessment Letter for Columbia Generating Station (Report 05000397/2012006) IR 05000397/20120012012-03-0505 March 2012 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2012001) ML1124306472011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan - Columbia Generating Station ML1112907052011-05-0606 May 2011 Notification of Inspection (IR 05000397-11-004) and Request for Information ML1024403712010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Columbia Generating Station IR 05000397/20100012010-03-0303 March 2010 Annual Assessment Letter - Columbia Generating Station (Report 05000397-10-001) ML0924000972009-09-0101 September 2009 9/1/2009 Columbia 2009 Midcycle Performance Review and Inspection Plan 2024-08-22
[Table view] Category:Letter
MONTHYEARML24290A1142024-10-17017 October 2024 CGS FPTI 2024011 IR 05000397/20244032024-10-0101 October 2024 Cybersecurity Inspection Report 05000397/2024403 Public GO2-24-088, Supplement to Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan2024-09-24024 September 2024 Supplement to Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan GO2-24-051, Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements2024-09-23023 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML24247A1572024-09-12012 September 2024 Withholding Determination Letter for Presentation Materials for Energy Northwest Pre-application Meeting 8-9-2024 ML24255A1012024-09-12012 September 2024 Request for Withholding Information from Public Disclosure Energy Northwest Regulatory Engagement Plan, Revision 0 GO2-24-082, Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan2024-09-10010 September 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan IR 05000397/20240052024-08-22022 August 2024 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2024005) IR 07200035/20244012024-08-19019 August 2024 Security Baseline Inspection Report 07200035/2024401 IR 05000397/20244022024-08-13013 August 2024 Security Baseline Inspection Report 05000397/2024402 IR 05000397/20240022024-08-0909 August 2024 Integrated Inspection Report 05000397/2024002 GO2-24-060, Reply to a Notice of Violation, EA-21-170 and EA-23-0542024-07-30030 July 2024 Reply to a Notice of Violation, EA-21-170 and EA-23-054 GO2-24-070, Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program2024-07-29029 July 2024 Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program GO2-24-063, Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan2024-07-15015 July 2024 Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan IR 05000397/20240122024-07-10010 July 2024 – Safety Conscious Work Environment Issue of Concern Follow-up Inspection 05000397/2024012 ML24180A1482024-06-28028 June 2024 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000397/2024011) and Request for Information IR 05000397/20244202024-06-27027 June 2024 – Security Baseline Inspection Report 05000397 2024420 Cover Letter GO2-24-057, Notice of Readiness for Supplemental Inspection2024-06-19019 June 2024 Notice of Readiness for Supplemental Inspection ML24099A2232024-06-12012 June 2024 Issuance of Amendment No. 275 to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling GO2-24-056, Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing2024-06-11011 June 2024 Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing ML24128A2242024-05-31031 May 2024 Issuance of Amendment No. 274 to Revise Technical Specifications to Adopt TSTF-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-13013 May 2024 2023 Annual Radiological Environmental Operating Report GO2-24-050, Annual Environmental Operating Report2024-04-30030 April 2024 Annual Environmental Operating Report IR 05000397/20240012024-04-24024 April 2024 Integrated Inspection Report 05000397/2024001 GO2-24-042, 2023 Annual Radioactive Effluent Release Report2024-04-22022 April 2024 2023 Annual Radioactive Effluent Release Report ML24089A2282024-04-15015 April 2024 – Acceptance of Requested Licensing Action License Amendment Request to Revise Columbia Generating Station Emergency Plan ML24074A4532024-04-11011 April 2024 Request for Withholding Information from Public Disclosure GO2-24-044, Voluntary Response to Regulatory Issue Summary 2024-012024-04-11011 April 2024 Voluntary Response to Regulatory Issue Summary 2024-01 IR 05000397/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000397/2024401 (Cover Letter Only) GO2-24-034, Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan2024-03-20020 March 2024 Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan ML24058A0692024-03-14014 March 2024 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Emergency Plan ML24044A0492024-03-12012 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0064 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) GO2-24-041, Level of Financial Protection - Annual Reporting Requirement2024-03-12012 March 2024 Level of Financial Protection - Annual Reporting Requirement GO2-24-036, Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate2024-03-11011 March 2024 Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate GO2-24-039, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462024-03-11011 March 2024 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 ML24047A0422024-03-0707 March 2024 Issuance of Amendment No. 273 Renewed Facility Operating License and Technical Specification Clean Up IR 05000397/20230062024-02-28028 February 2024 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2023006) IR 05000397/20253012024-02-14014 February 2024 Notification of NRC Initial Operator Licensing Examination 05000397/2025301 GO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan IR 05000397/20230042024-01-29029 January 2024 Integrated Inspection and Independent Spent Fuel Storage Installation Report 05000397/2023004 and 07200035/2023001 GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing GO2-24-014, Independent Spent Fuel Storage Installation, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2024-01-15015 January 2024 Independent Spent Fuel Storage Installation, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML24011A1522024-01-10010 January 2024 March 2024 Emergency Preparedness Exercise Inspection-Request for Information GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-105, Licensing Basis Document Update and Biennial Commitment Change Report2023-12-12012 December 2023 Licensing Basis Document Update and Biennial Commitment Change Report ML23288A0002023-12-0707 December 2023 Issuance of Amendment No. 272 to Adopt TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation 2024-09-24
[Table view] |
Text
ust 30, 2019
SUBJECT:
UPDATED INSPECTION PLAN FOR COLUMBIA GENERATING STATION, REPORT 05000397/2019005
Dear Mr. Sawatzke:
The enclosed inspection plan lists the inspections scheduled through June 30, 2021, for Columbia Generating Station. The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the Reactor Oversight Process (ROP), including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections), and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule, beginning in January 2020. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
Additionally, as reflected in the enclosure, during this period the NRC staff will complete Temporary Instruction 2515/194, Inspection of the Licensee's Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerabilities in Electric Power Systems (NRC Bulletin 2012-01). Further, in early 2020, at a date to be established with your staff, the NRC staff will complete Temporary Instruction 2515/193, Inspection of the Implementation of EA-13-109: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions.
In accordance with Title 10 of the Code of Federal Regulations (CFR) 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (817) 200-1148 with any questions you have regarding this letter.
Sincerely,
/RA/
Jeffrey A. Josey, Chief Project Branch A Division of Reactor Projects Docket No. 50-397 License No. NPF-21 Enclosure:
Inspection Plan
ML19234A058 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:
By: RDA Yes No Publicly Available Sensitive NRC-002 OFFICE PBA:SPE PBA:C NAME RAlexander JJosey SIGNATURE /RA/ /RA/
DATE 08/19/19 08/30/19
IP 22 Inspection Activity Plan Report Columbia Generating Station 07/01/2019 - 06/30/2021 Unit Start End Activity CAC Title Staff Count Security Access Control .02 1 2 07/08/2019 07/19/2019 IP 71130.02 000734 Access Control 2 07/08/2019 07/19/2019 IP 71151 001338 Performance Indicator Verification COLUMBIA DBA TEAMS INSPECTION 8 2 08/05/2019 08/23/2019 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
Security Protective Strategy .05 2 2 09/30/2019 10/11/2019 IP 71130.05 000737 Protective Strategy Evaluation RP TEAM INSPECTION 4 2 11/04/2019 11/08/2019 IP 71124.05 000729 Radiation Monitoring Instrumentation 2 11/04/2019 11/08/2019 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 2 11/04/2019 11/08/2019 IP 71124.07 000731 Radiological Environmental Monitoring Program 2 11/04/2019 11/08/2019 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation MC&A - MAT'L CONTROL & ACCOUNTING 1 2 11/04/2019 11/08/2019 IP 71130.11 000742 Material Control and Accounting (MC&A)
TI 2515/194 - CGS 1 2 11/18/2019 11/22/2019 TI 2515/194 000512 Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)
CGS 2019 BRQ 2 2 12/01/2019 12/07/2019 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance EP Exercise and PI Inspection 4 2 03/23/2020 03/27/2020 IP 71114.01 000716 Exercise Evaluation 2 03/23/2020 03/27/2020 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 2 03/23/2020 03/27/2020 IP 71151 001397 Performance Indicator Verification Columbia Generating Station - Evaluations of Changes, Tests, and Experiments 3 2 04/13/2020 04/17/2020 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments This report does not include INPO and OUTAGE activities. Page 1 of 3 This report shows only on-site and announced inspection procedures.
8/23/2019 9:48:25 AM
IP 22 Inspection Activity Plan Report Columbia Generating Station 07/01/2019 - 06/30/2021 Unit Start End Activity CAC Title Staff Count RS13PI Radiation Safety 2 2 04/13/2020 04/17/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 2 04/13/2020 04/17/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation Security Access Control .02 1 2 05/23/2020 05/27/2020 IP 71130.02 000734 Access Control 2 05/23/2020 05/27/2020 IP 71151 001338 Performance Indicator Verification Cyber Security Inspection - CGS 4 2 06/22/2020 06/26/2020 IP 71130.10P 000741 Cyber Security 2 07/06/2020 07/10/2020 IP 71130.10P 000741 Cyber Security RS24 Radiation Safety 2 2 07/27/2020 07/31/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls 2 07/27/2020 07/31/2020 IP 71124.04 000728 Occupational Dose Assessment Columbia Generating Station - Heat Sink Performance (Triennial) 2 2 08/17/2020 08/21/2020 IP 71111.07T 000700 Heat Sink Performance Security Equipment .04 and Training .07 2 2 08/17/2020 08/21/2020 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 2 08/17/2020 08/21/2020 IP 71130.07 000739 Security Training CGS 2021 INITIAL EXAM 4 2 01/10/2021 01/16/2021 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
2 02/21/2021 02/27/2021 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
Security FFD .08 1 2 03/08/2021 03/12/2021 IP 71130.08 000740 Fitness For Duty Program EP Program Inspection 1 2 04/26/2021 04/30/2021 IP 71114.02 000717 Alert and Notification System Testing Inservice Inspection RF25 - CGS 1 2 05/10/2021 05/14/2021 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
This report does not include INPO and OUTAGE activities. Page 2 of 3 This report shows only on-site and announced inspection procedures.
8/23/2019 9:48:25 AM
IP 22 Inspection Activity Plan Report Columbia Generating Station 07/01/2019 - 06/30/2021 Unit Start End Activity CAC Title Staff Count RP 1,2,PI 2 2 05/17/2021 05/21/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 2 05/17/2021 05/21/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls RP 5,6,7,8 PS Team 4 2 06/28/2021 07/02/2021 IP 71124.05 000729 Radiation Monitoring Instrumentation 2 06/28/2021 07/02/2021 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 2 06/28/2021 07/02/2021 IP 71124.07 000731 Radiological Environmental Monitoring Program 2 06/28/2021 07/02/2021 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation This report does not include INPO and OUTAGE activities. Page 3 of 3 This report shows only on-site and announced inspection procedures.
8/23/2019 9:48:25 AM