MONTHYEARDCL-24-075, Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, “Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React2024-08-0808 August 2024 Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, “Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React IR 05000275/20240022024-08-0606 August 2024 Integrated Inspection Report 05000275/2024002 and 05000323/2024002 DCL-24-070, License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2024-07-31031 July 2024 License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies DCL-24-071, Core Operating Limits Report for Unit 2 Cycle 252024-07-22022 July 2024 Core Operating Limits Report for Unit 2 Cycle 25 DCL-2024-523, Submittal of Report on Discharge Self-Monitoring2024-07-18018 July 2024 Submittal of Report on Discharge Self-Monitoring ML24187A1352024-07-16016 July 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of June 2024 Audit Related to the License Renewal Application Severe Accident Mitigation Alternatives Review IR 05000275/20240142024-07-11011 July 2024 Age-Related Degradation Inspection Report 05000275/2024014 and 05000323/2024014 IR 05000275/20243012024-07-10010 July 2024 NRC Initial Operator Licensing Examination Approval 05000275/2024301; 05000323/2024301 IR 05000275/20244012024-07-0808 July 2024 Security Baseline Inspection Report 05000275/2024401 and 05000323/2024401 (Full Report) IR 05000323/20240112024-07-0303 July 2024 License Renewal Phase Report 05000323/2024011 DCL-2024-527, Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant2024-07-0101 July 2024 Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant DCL-24-066, Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL2024-06-27027 June 2024 Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL ML24155A2182024-06-18018 June 2024 OEDO-23-00350-NRR - (LTR-23-0228-1) - Closure Letter - 10 CFR 2.206 Petition from Mothers for Peace and Friends of the Earth Regarding Diablo Canyon ML24129A1762024-06-14014 June 2024 National Historic Preservation Act Section 106 Consultation – Results of Identification and Evaluation (Docket Number: 72-026) ML24200A2052024-06-0707 June 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project for Diablo Canyon License Renewal ML24099A2192024-05-29029 May 2024 Plants, Units 1 and 2 Issuance of Amendment Nos. 245 and 247 Revision to TSs to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24117A0132024-05-20020 May 2024 Letter to Paula Gerfen-Diablo Canyon Units 1 and 2-Regulatory Audit Regarding Severe Accident Mitigation Alternatives for the License Renewal Application DCL-24-052, Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report2024-05-16016 May 2024 Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report DCL-24-051, One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage2024-05-0808 May 2024 One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage ML24127A2042024-05-0202 May 2024 02May2024 Ltr - California Coastal Commission to Pg&E, Coastal Development Permit Needed for Pg&E’S Proposed Relicensing of Diablo Canyon Nuclear Power Plant DCL-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Radiological Environmental Operating Report DCL-24-047, 2023 Annual Non-radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Non-radiological Environmental Operating Report DCL-24-048, O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 20232024-04-30030 April 2024 O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 2023 L-24-004, Independent Spent Fuel Storage Installation - Responses to NRC Requests for Additional Information on the Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Application (Cac/Epid 001028/L-2022-RNW-0007)2024-04-30030 April 2024 Independent Spent Fuel Storage Installation - Responses to NRC Requests for Additional Information on the Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Application (Cac/Epid 001028/L-2022-RNW-0007) DCL-24-027, 2023 Annual Radioactive Effluent Release Report2024-04-28028 April 2024 2023 Annual Radioactive Effluent Release Report DCL-24-045, Annual Report of Occupational Radiation Exposure for 20232024-04-24024 April 2024 Annual Report of Occupational Radiation Exposure for 2023 IR 05000275/20240012024-04-23023 April 2024 Integrated Inspection Report 05000275/2024001 and 05000323/2024001 ML24114A2032024-04-22022 April 2024 Request for Information for EP Program and Performance Indicator Verification Inspection (Wolf Creek Nuclear Generating Station) Inspection Report 05000482/2024003 ML24106A2892024-04-18018 April 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of March 2024 Audit Regarding the Environmental Review of the License Renewal Application ML24106A2882024-04-18018 April 2024 License Renewal Application Environmental Review RCIs and RAIs DCL-24-042, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-04-17017 April 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24108A1122024-04-15015 April 2024 License Amendment Request 24-02 Request for Approval of DCPP Early Warning System to Meet 10 CFR 73.55(i)(2) and 10 CFR 73.55(e)(9)(vi)(A) DCL-24-023, Revised Certification of Permanent Cessation of Power Operations2024-04-0202 April 2024 Revised Certification of Permanent Cessation of Power Operations DCL-24-022, Notification of Changes to Decommissioning Schedule2024-04-0202 April 2024 Notification of Changes to Decommissioning Schedule DCL-24-031, Decommissioning Funding Report2024-03-27027 March 2024 Decommissioning Funding Report DCL-24-032, 2024 Annual Statement of Insurance for Pacific Gas and Electric Company’S Diablo Canyon Power Plant2024-03-27027 March 2024 2024 Annual Statement of Insurance for Pacific Gas and Electric Company’S Diablo Canyon Power Plant ML24082A2592024-03-25025 March 2024 Notice of Enforcement Discretion for Diablo Canyon Power Plant, Unit 2 (EPID L-2024-LLD-0002) - March 25, 2024 ML24081A0462024-03-22022 March 2024 Audit Summary in Support of the License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b DCL-24-028, Request for Enforcement Discretion Regarding Compliance with Technical Specification 3.0.3, Limiting Condition for Operation Applicability2024-03-21021 March 2024 Request for Enforcement Discretion Regarding Compliance with Technical Specification 3.0.3, Limiting Condition for Operation Applicability ML24081A4052024-03-21021 March 2024 Request for Enforcement Discretion Regarding Compliance with Technical Specification 3.0.3, Limiting Condition for Operation Applicability ML24065A1312024-03-20020 March 2024 ISFSI Renewal RAI Transmittal Letter IR 05000275/20244032024-03-12012 March 2024 Cyber Security Inspection Report 05000275/2024403 and 05000323/2024403 (Cover Letter) ML24065A3662024-03-0404 March 2024 Notification of Site Inspection for License Renewal and Request for Information Inspection (05000323/2024011) ML24071A1742024-03-0404 March 2024 Email - (External_Sender) Shutdown Petition to NRC Commissioners DCL-24-018, License Amendment Request 24-01 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)2024-02-28028 February 2024 License Amendment Request 24-01 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) IR 05000275/20230062024-02-28028 February 2024 Annual Assessment Letter for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2023006 and 05000323/2023006) ML24056A0022024-02-27027 February 2024 – License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application DCL-2024-507, 2023 Annual Report on Discharge Self-Monitoring2024-02-27027 February 2024 2023 Annual Report on Discharge Self-Monitoring ML24058A2552024-02-22022 February 2024 Formal Acceptance from Sy Chumash Re Regarding Consultation on the DC NPP ML24058A2562024-02-22022 February 2024 Santa Ynez Band or Chumash Tribe - Consultation Request Diablo Canyon NPP Units 1 and 2 2024-08-08
[Table view] |
Text
June 11, 2008 John T. Conway Senior Vice President - Station Generation and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 770000 San Francisco, CA 94177-0001
SUBJECT:
DIABLO CANYON POWER PLANT, UNITS 1 AND 2 - NRC INITIAL OPERATOR LICENSING EXAMINATION APPROVAL 05000275/2008301; 05000323/2008301
Dear Mr. Conway:
The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing examinations at Diablo Canyon Power Plant.
The NRC has completed its review of the operator license applications submitted in connection with this examination and separately provided a list of approved applicants to David Burns, Simulator Supervisor. Note that any examination waivers and applications denials have been addressed in separate correspondence.
The NRC has approved the subject examinations and hereby authorizes you to administer the written examination in accordance NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," Revision 9, Supplement 1, on June 13, 2008. The NRC staff will administer the operating tests during the weeks of June 16 and June 23, 2008. This examination has undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this review, I have concluded that the examination meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG-1021 guidelines, and is appropriate for measuring the qualifications of licensed operator applicants at your facility. If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at (817) 860-8159.
Please contact your Chief Examiner, Steve Garchow, at (817) 276-4426, if you have any questions or identify any errors or changes in the license level (RO or SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant.
Sincerely,
/RA/ Ryan E. Lantz, Chief Operations Branch Division of Reactor Safety UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV612 EAST LAMAR BLVD, SUITE 400ARLINGTON, TEXAS 76011-4125 Pacific Gas and Electric Company Dockets: 50-275; 50-323 Licenses: DPR-80; DPR-82
Enclosure:
ES-201-4 cc w/enclosure:
David Burns, Simulator Supervisor Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 56 Avila Beach, CA 93424
cc w/o enclosure: Sierra Club San Lucia Chapter ATTN: Andrew Christie P.O. Box 15755 San Luis Obispo, CA 93406
Nancy Culver San Luis Obispo Mothers for Peace P.O. Box 164 Pismo Beach, CA 93448
Chairman San Luis Obispo County Board of Supervisors 1055 Monterey Street, Suite D430 San Luis Obispo, CA 93408 Truman Burns\Robert Kinosian California Public Utilities Commission 505 Van Ness Ave., Rm. 4102 San Francisco, CA 94102 Diablo Canyon Independent Safety Committee Attn: Robert R. Wellington, Esq. Legal Counsel 857 Cass Street, Suite D Monterey, CA 93940 Director, Radiological Health Branch State Department of Health Services P.O. Box 997414 (MS 7610) Sacramento, CA 95899-7414
City Editor The Tribune 3825 South Higuera Street P.O. Box 112 San Luis Obispo, CA 93406-0112 Pacific Gas and Electric Company.
James D. Boyd, Commissioner California Energy Commission 1516 Ninth Street (MS 31) Sacramento, CA 95814
James R. Becker, Site Vice President Diablo Canyon Power Plant P.O. Box 56 Avila Beach, CA 93424
Jennifer Tang Field Representative United States Senator Barbara Boxer 1700 Montgomery Street, Suite 240 San Francisco, CA 94111 Chief, Radiological Emergency Preparedness Section National Preparedness Directorate Technological Hazards Division Department of Homeland Security 1111 Broadway, Suite 1200 Oakland, CA 94607-4052 Pacific Gas and Electric Company.
Electronic distribution by RIV: Regional Administrator (Elmo.Collins@nrc.gov) DRP Director (Dwight.Chamberlain@nrc.gov) DRS Director (Roy.Caniano@nrc.gov) DRS Deputy Director (Troy.Pruett@nrc.gov) Senior Resident Inspector (Michael.Peck@nrc.gov) Branch Chief, DRP/B (Vincent.Gaddy@nrc.gov) Senior Project Engineer, DRP/B (Rick.Deese@nrc.gov) Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov) RITS Coordinator (Marisa.Herrera@nrc.gov) Licensing Assistant (Laura.Hurley@nrc.gov)
SUNSI Review Completed: lah ADAMS No Initials: _rel_____ Publicly Available Non-Publicly Available Sensitive Non-Sensitive ES201 REV9 diablo exam approval letter.doc RIV:OB:LA CE:OB C:OB LAHurley SMGarchow RELantz /RA/ /RA/ /RA/ 06/02/08 06/02/08 06/09/08 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax