L-15-193, Submittal of the 2015 Silicone Sealant Report Pursuant to License Commitment 17
ML15168A011 | |
Person / Time | |
---|---|
Site: | Perry |
Issue date: | 06/12/2015 |
From: | Harkness E FirstEnergy Nuclear Operating Co |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
L-15-193 | |
Download: ML15168A011 (3) | |
Similar Documents at Perry | |
---|---|
Category:Letter type:L
MONTHYEARL-24-178, License Renewal Application Revision O - Supplement 42024-08-0808 August 2024
[Table view]License Renewal Application Revision O - Supplement 4 L-24-189, License Renewal Application for Revision O - Supplement 12024-08-0707 August 2024 License Renewal Application for Revision O - Supplement 1 L-24-171, Spent Fuel Storage Cask Registration2024-07-30030 July 2024 Spent Fuel Storage Cask Registration L-24-108, License Renewal Application, Revision 0 - Supplement 32024-07-24024 July 2024 License Renewal Application, Revision 0 - Supplement 3 L-24-036, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2024-06-27027 June 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-24-020, License Renewal Application for the Perry Nuclear Power Plant Revision 0, Supplement 22024-06-27027 June 2024 License Renewal Application for the Perry Nuclear Power Plant Revision 0, Supplement 2 L-24-116, Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification2024-05-16016 May 2024 Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification L-24-085, Nudear Power Plant, Submittal of Emergency Plan, Revision 622024-05-0606 May 2024 Nudear Power Plant, Submittal of Emergency Plan, Revision 62 L-24-103, Response to NRC Regulatory Issue Summary 2024-01, Preparation & Scheduling of Operator Licensing Exams2024-05-0202 May 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation & Scheduling of Operator Licensing Exams L-24-096, Submittal of Annual Radiological Environmental Operating Report2024-04-22022 April 2024 Submittal of Annual Radiological Environmental Operating Report L-24-097, Submittal of 2023 Annual Radiological Effluent Release Report2024-04-22022 April 2024 Submittal of 2023 Annual Radiological Effluent Release Report L-24-066, Response to Request for Additional Information Regarding 10 CFR 50.55a Request Number VR-9, Feedwater Check Valve Exercising Test Frequency2024-04-15015 April 2024 Response to Request for Additional Information Regarding 10 CFR 50.55a Request Number VR-9, Feedwater Check Valve Exercising Test Frequency L-24-083, Response to License Renewal Environmental Report Requests for Additional Information and Request for Clarification2024-04-15015 April 2024 Response to License Renewal Environmental Report Requests for Additional Information and Request for Clarification L-24-017, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2024-01-24024 January 2024 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative L-23-207, License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2024-01-24024 January 2024 License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs L-23-171, CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency2023-12-0808 December 2023 CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency L-23-244, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation L-23-238, Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 202023-11-10010 November 2023 Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 20 L-23-052, Submittal of the Updated Safety Analysis Report, Revision 232023-10-27027 October 2023 Submittal of the Updated Safety Analysis Report, Revision 23 L-23-206, Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD2023-09-12012 September 2023 Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual L-23-001, License Amendment Request to Remove the Table of Contents from the Technical Specifications2023-08-0707 August 2023 License Amendment Request to Remove the Table of Contents from the Technical Specifications L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-174, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2023-07-19019 July 2023 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative L-23-146, License Renewal Application for the Perry Nuclear Power Plant2023-07-0303 July 2023 License Renewal Application for the Perry Nuclear Power Plant L-23-051, Plan, Nineteenth Inservice Inspection Summary Report2023-06-22022 June 2023 Plan, Nineteenth Inservice Inspection Summary Report L-23-050, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-06-22022 June 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-22-249, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener2023-06-0505 June 2023 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener L-23-134, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-23023 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report L-23-121, Annual Radiological Effluent Release Report2023-04-26026 April 2023 Annual Radiological Effluent Release Report L-23-122, Annual Radiological Environmental Operating Report2023-04-26026 April 2023 Annual Radiological Environmental Operating Report L-23-061, Submittal of the Decommissioning Funding Status Reports2023-03-31031 March 2023 Submittal of the Decommissioning Funding Status Reports L-23-049, Core Operating Limits Report for Operating Cycle 202023-03-30030 March 2023 Core Operating Limits Report for Operating Cycle 20 L-23-037, and Perry Nuclear Power Plant - Independent Spent Fuel Storage Installation Changes, Tests, and Experiments2023-03-29029 March 2023 and Perry Nuclear Power Plant - Independent Spent Fuel Storage Installation Changes, Tests, and Experiments L-23-066, Annual Notification of Property Insurance Coverage2023-03-21021 March 2023 Annual Notification of Property Insurance Coverage L-23-085, 1 to Emergency Plan2023-03-10010 March 2023 1 to Emergency Plan L-23-057, Energy Harbor Nuclear Corp Retrospective Premium Guarantee2023-02-20020 February 2023 Energy Harbor Nuclear Corp Retrospective Premium Guarantee L-23-017, Mid-Cycle Revisions to the Core Operating Limits Report for Operating Cycle 192023-01-31031 January 2023 Mid-Cycle Revisions to the Core Operating Limits Report for Operating Cycle 19 L-22-271, Emergency Plan2022-12-20020 December 2022 Emergency Plan L-22-272, Supplement to License Amendment Request to Revise the Methodology Used for Flood Hazard Analysis (EPID L-2021-LLA-0067) and Withdrawal of Exemption Requests (EPIDs L-2021-LLE-0022 and L-2021-LLE-0023)2022-12-16016 December 2022 Supplement to License Amendment Request to Revise the Methodology Used for Flood Hazard Analysis (EPID L-2021-LLA-0067) and Withdrawal of Exemption Requests (EPIDs L-2021-LLE-0022 and L-2021-LLE-0023) L-22-263, Spent Fuel Storage Cask Registration2022-12-12012 December 2022 Spent Fuel Storage Cask Registration L-22-254, Emergency Plan for Perry Nuclear Power Plant, Including EAL Matrix Revision 222022-11-18018 November 2022 Emergency Plan for Perry Nuclear Power Plant, Including EAL Matrix Revision 22 L-22-250, Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 192022-11-0808 November 2022 Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 19 L-22-221, Supplement to Application to Revise the Technical Specifications to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2022-10-18018 October 2022 Supplement to Application to Revise the Technical Specifications to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position L-22-201, Submittal of Evacuation Time Estimates2022-09-12012 September 2022 Submittal of Evacuation Time Estimates L-22-050, Summary of Changes to the Energy Harbor Nuclear Corp. Quality Assurance Program Manual2022-08-0909 August 2022 Summary of Changes to the Energy Harbor Nuclear Corp. Quality Assurance Program Manual L-20-239, Application to Revise the Technical Specifications to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2022-08-0505 August 2022 Application to Revise the Technical Specifications to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position L-22-171, Response to Request for Additional Information Regarding Proposed Inservice Inspection Alternative IR-0632022-07-14014 July 2022 Response to Request for Additional Information Regarding Proposed Inservice Inspection Alternative IR-063 2024-08-08 Category:Report MONTHYEARL-23-171, CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency2023-12-0808 December 2023
[Table view]CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-21-045, 10 CFR 50.55a Request Number VR-4, Revision 0, Exercising Test Frequency, VR-6, Revision 0, Position Verification Testing, and VR-8, Revision 0, Valve Test Frequency Extension2021-02-0808 February 2021 10 CFR 50.55a Request Number VR-4, Revision 0, Exercising Test Frequency, VR-6, Revision 0, Position Verification Testing, and VR-8, Revision 0, Valve Test Frequency Extension L-18-186, Proposed Alternative to Use ASME Code Case N-8312018-09-0707 September 2018 Proposed Alternative to Use ASME Code Case N-831 L-17-234, High Frequency Supplement to Seismic Hazard Screening Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(0 Regarding Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the ...2017-08-11011 August 2017 High Frequency Supplement to Seismic Hazard Screening Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(0 Regarding Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the ... L-17-229, Mitigating Strategies Assessment (MSA) for Flooding2017-07-24024 July 2017 Mitigating Strategies Assessment (MSA) for Flooding L-17-039, 2016 Annual Report of Emergency Core Cooling System Errors and Model Changes2017-04-0505 April 2017 2016 Annual Report of Emergency Core Cooling System Errors and Model Changes L-17-088, Independent Spent Fuel Storage Installation Changes, Tests and Experiments2017-03-27027 March 2017 Independent Spent Fuel Storage Installation Changes, Tests and Experiments ML21106A0222016-05-31031 May 2016 Enclosure a - Evaluation Attachment 5 - FLO-2D Verification Report (Report Attachment 2) L-16-091, Revision of Flood Hazard Reevaluation Report in Response to NRC Request for Additional Information, Per 10CFR50.54(f) Regarding the Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the Fukush2016-03-24024 March 2016 Revision of Flood Hazard Reevaluation Report in Response to NRC Request for Additional Information, Per 10CFR50.54(f) Regarding the Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the Fukush L-15-281, Submittal of Report of Facility Changes, Tests and Experiments2015-10-23023 October 2015 Submittal of Report of Facility Changes, Tests and Experiments ML15208A0342015-08-0303 August 2015 Staff Assessment of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f), Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force L-15-193, Submittal of the 2015 Silicone Sealant Report Pursuant to License Commitment 172015-06-12012 June 2015 Submittal of the 2015 Silicone Sealant Report Pursuant to License Commitment 17 L-15-108, ISFSI - Summary Report of Changes, Tests and Experiments for the Period of January 1, 2013 Through December 31, 20142015-04-0303 April 2015 ISFSI - Summary Report of Changes, Tests and Experiments for the Period of January 1, 2013 Through December 31, 2014 L-14-401, First Energy Nuclear Operating Company (FENOC) Expedited Seismic Evaluation Process (ESEP) Reports Response to NRC Request for Information Pursuant to 10 CFR50.54(f) Regarding Recommendation.1 of the Near-Term Task Force (NTTF) Review of In2014-12-19019 December 2014 First Energy Nuclear Operating Company (FENOC) Expedited Seismic Evaluation Process (ESEP) Reports Response to NRC Request for Information Pursuant to 10 CFR50.54(f) Regarding Recommendation.1 of the Near-Term Task Force (NTTF) Review of In L-14-259, Firstenergy Nuclear Operating Company'S (Fenoc'S) Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-08-28028 August 2014 Firstenergy Nuclear Operating Company'S (Fenoc'S) Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) L-14-254, 10 CFR 71.95 Report on the TN-RAM Package2014-08-15015 August 2014 10 CFR 71.95 Report on the TN-RAM Package ML14141A4602014-06-30030 June 2014 Staff Assessment of the Flooding Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima DAI-ICHI Nuclear Power Plant Accident ML14176A9612014-06-24024 June 2014 Submittal of Non-Proprietary BWROG Technical Product, BWROGTP-11-006 - ECCS Containment Walkdown Procedure, Rev 1 (January 2011), as Formally Requested During the Public Meeting Held on April 30, 2014 L-14-198, Report of Changes and Errors Pursuant to 10 CFR 50.462014-06-18018 June 2014 Report of Changes and Errors Pursuant to 10 CFR 50.46 ML14115A2342014-05-30030 May 2014 Staff Assessment of the Seismic Walkdown Report Supporting Implementation of Near-term Task Force Recommendation 2.3 Related to the Fukushima DAI-ICHI Nuclear Power Plant Accident ML13338A4602014-01-22022 January 2014 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 - Mitigation Strategies ML14014A2092014-01-14014 January 2014 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Perry Nuclear Power Plant, Unit 1, TAC No.: MF0962 (Revision 1) ML13340A1472013-11-26026 November 2013 Davis-Besse Nuclear Power Station & Perry Nuclear Power Plant - Response to RAI Associated with Seismic Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident (TAC Nos. MF0116 & MF0 L-13-358, Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report Revision 1, Appendix B (2 of 2)2013-10-0909 October 2013 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report Revision 1, Appendix B (2 of 2) ML13340A1572013-10-0909 October 2013 Perry Nuclear Power Plant Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report Revision 1, Appendix B (1 of 2) ML13340A1562013-10-0909 October 2013 Perry Nuclear Power Plant Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report Revision 1, Appendix a ML13340A1552013-10-0909 October 2013 Perry Nuclear Power Plant Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report Revision 1 L-13-300, Submittal of 10 CFR 71.95 Report on the 8-120B Cask2013-10-0101 October 2013 Submittal of 10 CFR 71.95 Report on the 8-120B Cask L-13-164, Addendum to Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report2013-06-18018 June 2013 Addendum to Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report L-12-347, FENOC Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Flooding Aspects of Recommendation 2.3 of Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident2012-11-27027 November 2012 FENOC Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Flooding Aspects of Recommendation 2.3 of Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident ML13008A0542012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B: Seismic Walkdown Checklists, Page B-1, Sheet 482 of 513 Through Appendix C: Area Walk-by Checklists, Sheet 85 of 212 ML13135A2512012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B - Seismic Walk-Down Checklists (Swcs), Sheet 204 of 461 Through Sheet 461 of 461 ML13135A2492012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B - Seismic Walk-Down Checklists (Swcs), Sheet 1 of 461 Through Sheet 203 of 461 ML13135A2482012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix a - Resumes and Qualifications ML13135A2472012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Cover Through Page 153 ML13135A2292012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendices C Through End ML13008A0502012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B: Seismic Walkdown Checklists, Page B-1, Sheet 1 of 513 Through Sheet 122 of 513 ML13008A0512012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B: Seismic Walkdown Checklists, Page B-1, Sheet 123 of 513 Through Sheet 247 of 513 ML13008A0492012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Cover Through Appendix a, Resumes and Qualifications, Page A-36 ML13008A0552012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix C: Area Walk-by Checklists, Sheet 86 of 212 Through End ML13008A0522012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B: Seismic Walkdown Checklists, Page B-1, Sheet 248 of 513 Through Sheet 367 of 513 ML1127000692011-09-26026 September 2011 Enclosure 2, Mfn 10-245 R4, Description of the Evaluation and Surveillance Recommendations for BWR/2-5 Plants L-11-017, State of Ohio Water Withdrawal Report2011-01-24024 January 2011 State of Ohio Water Withdrawal Report ML1012704392010-05-0505 May 2010 Y020100187 - List of Historical Leaks and Spills at U.S. Commercial Nuclear Power Plants ML0919400712009-06-29029 June 2009 Semi-Annual Sewage Isotopic Report ML0904007952009-02-0404 February 2009 GSI-189 Action Plan, Feb. 09 Update, Publicly Available Version ML0821900132008-08-0707 August 2008 Monthly Operating Reports Second Quarter 2008 ML0705902852007-02-20020 February 2007 Semiannual Fitness-For-Duty Report for Period of July 1, 2006 Through December 31, 2006 ML0700902662007-01-0808 January 2007 Final Transition Letter and Attachment, Revision 1 (1-8-07) 2023-08-07 Category:Miscellaneous MONTHYEARL-23-171, CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency2023-12-0808 December 2023
[Table view]CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-18-186, Proposed Alternative to Use ASME Code Case N-8312018-09-0707 September 2018 Proposed Alternative to Use ASME Code Case N-831 L-17-229, Mitigating Strategies Assessment (MSA) for Flooding2017-07-24024 July 2017 Mitigating Strategies Assessment (MSA) for Flooding L-17-039, 2016 Annual Report of Emergency Core Cooling System Errors and Model Changes2017-04-0505 April 2017 2016 Annual Report of Emergency Core Cooling System Errors and Model Changes L-17-088, Independent Spent Fuel Storage Installation Changes, Tests and Experiments2017-03-27027 March 2017 Independent Spent Fuel Storage Installation Changes, Tests and Experiments L-16-091, Revision of Flood Hazard Reevaluation Report in Response to NRC Request for Additional Information, Per 10CFR50.54(f) Regarding the Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the Fukush2016-03-24024 March 2016 Revision of Flood Hazard Reevaluation Report in Response to NRC Request for Additional Information, Per 10CFR50.54(f) Regarding the Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the Fukush L-15-281, Submittal of Report of Facility Changes, Tests and Experiments2015-10-23023 October 2015 Submittal of Report of Facility Changes, Tests and Experiments ML15208A0342015-08-0303 August 2015 Staff Assessment of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f), Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force L-15-193, Submittal of the 2015 Silicone Sealant Report Pursuant to License Commitment 172015-06-12012 June 2015 Submittal of the 2015 Silicone Sealant Report Pursuant to License Commitment 17 L-15-108, ISFSI - Summary Report of Changes, Tests and Experiments for the Period of January 1, 2013 Through December 31, 20142015-04-0303 April 2015 ISFSI - Summary Report of Changes, Tests and Experiments for the Period of January 1, 2013 Through December 31, 2014 L-14-401, First Energy Nuclear Operating Company (FENOC) Expedited Seismic Evaluation Process (ESEP) Reports Response to NRC Request for Information Pursuant to 10 CFR50.54(f) Regarding Recommendation.1 of the Near-Term Task Force (NTTF) Review of In2014-12-19019 December 2014 First Energy Nuclear Operating Company (FENOC) Expedited Seismic Evaluation Process (ESEP) Reports Response to NRC Request for Information Pursuant to 10 CFR50.54(f) Regarding Recommendation.1 of the Near-Term Task Force (NTTF) Review of In L-14-259, Firstenergy Nuclear Operating Company'S (Fenoc'S) Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-08-28028 August 2014 Firstenergy Nuclear Operating Company'S (Fenoc'S) Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) L-14-254, 10 CFR 71.95 Report on the TN-RAM Package2014-08-15015 August 2014 10 CFR 71.95 Report on the TN-RAM Package ML14141A4602014-06-30030 June 2014 Staff Assessment of the Flooding Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima DAI-ICHI Nuclear Power Plant Accident L-14-198, Report of Changes and Errors Pursuant to 10 CFR 50.462014-06-18018 June 2014 Report of Changes and Errors Pursuant to 10 CFR 50.46 ML14115A2342014-05-30030 May 2014 Staff Assessment of the Seismic Walkdown Report Supporting Implementation of Near-term Task Force Recommendation 2.3 Related to the Fukushima DAI-ICHI Nuclear Power Plant Accident ML13340A1472013-11-26026 November 2013 Davis-Besse Nuclear Power Station & Perry Nuclear Power Plant - Response to RAI Associated with Seismic Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident (TAC Nos. MF0116 & MF0 ML13340A1562013-10-0909 October 2013 Perry Nuclear Power Plant Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report Revision 1, Appendix a L-13-358, Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report Revision 1, Appendix B (2 of 2)2013-10-0909 October 2013 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report Revision 1, Appendix B (2 of 2) ML13340A1572013-10-0909 October 2013 Perry Nuclear Power Plant Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report Revision 1, Appendix B (1 of 2) ML13340A1552013-10-0909 October 2013 Perry Nuclear Power Plant Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report Revision 1 L-13-300, Submittal of 10 CFR 71.95 Report on the 8-120B Cask2013-10-0101 October 2013 Submittal of 10 CFR 71.95 Report on the 8-120B Cask L-13-164, Addendum to Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report2013-06-18018 June 2013 Addendum to Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report L-12-347, FENOC Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Flooding Aspects of Recommendation 2.3 of Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident2012-11-27027 November 2012 FENOC Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Flooding Aspects of Recommendation 2.3 of Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident ML13135A2512012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B - Seismic Walk-Down Checklists (Swcs), Sheet 204 of 461 Through Sheet 461 of 461 ML13008A0492012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Cover Through Appendix a, Resumes and Qualifications, Page A-36 ML13008A0502012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B: Seismic Walkdown Checklists, Page B-1, Sheet 1 of 513 Through Sheet 122 of 513 ML13008A0512012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B: Seismic Walkdown Checklists, Page B-1, Sheet 123 of 513 Through Sheet 247 of 513 ML13008A0542012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B: Seismic Walkdown Checklists, Page B-1, Sheet 482 of 513 Through Appendix C: Area Walk-by Checklists, Sheet 85 of 212 ML13135A2492012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B - Seismic Walk-Down Checklists (Swcs), Sheet 1 of 461 Through Sheet 203 of 461 ML13135A2482012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix a - Resumes and Qualifications ML13135A2472012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Cover Through Page 153 ML13008A0522012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B: Seismic Walkdown Checklists, Page B-1, Sheet 248 of 513 Through Sheet 367 of 513 ML13008A0552012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix C: Area Walk-by Checklists, Sheet 86 of 212 Through End ML13135A2292012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendices C Through End ML1127000692011-09-26026 September 2011 Enclosure 2, Mfn 10-245 R4, Description of the Evaluation and Surveillance Recommendations for BWR/2-5 Plants L-11-017, State of Ohio Water Withdrawal Report2011-01-24024 January 2011 State of Ohio Water Withdrawal Report ML1012704392010-05-0505 May 2010 Y020100187 - List of Historical Leaks and Spills at U.S. Commercial Nuclear Power Plants ML0919400712009-06-29029 June 2009 Semi-Annual Sewage Isotopic Report ML0705902852007-02-20020 February 2007 Semiannual Fitness-For-Duty Report for Period of July 1, 2006 Through December 31, 2006 ML0700902662007-01-0808 January 2007 Final Transition Letter and Attachment, Revision 1 (1-8-07) ML0700902622007-01-0303 January 2007 Transition Letter and Attachment (1/3/07) L-06-071, Revised Financial Information Associated with an Order Approving Transfer of Licenses to Firstenergy Nuclear Generation Corp2006-05-30030 May 2006 Revised Financial Information Associated with an Order Approving Transfer of Licenses to Firstenergy Nuclear Generation Corp ML0608804422006-03-24024 March 2006 GE Evaluation of OPRM Performance During Instability Events at Nine Mile Point, Unit 2 and Perry Nuclear Power Plant ML0606105272006-02-21021 February 2006 Semiannual Fitness-for-Duty Report for the Period July 1, 2005 Through December 31, 2005 ML0526304912005-09-0909 September 2005 Report of 10 CFR 50.59 Evaluations for 2003-2005 ML0523604432005-08-18018 August 2005 Semiannual Fitness-For-Duty Report Covering Time Period January 1, 2005 Through June 30, 2005 ML0522802442005-08-0808 August 2005 Response to NRC Inspection Procedure 95003 Supplemental Inspection, Inspection Report 05000440/2005003 ML0522803542005-08-0808 August 2005 Report of Changes Pursuant to 10 CFR 50.46 2023-08-07 |
Text
Perry Nuclear Power Plant FENOC- O. Box 97 F10 Center Road FirstEnergy Nuclear Operating Company Perry, Ohio 44081 Ernest J. Harkness 440-280-5382 Vice President Fax: 440-280-8029 June 12, 2015 L-15-193 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
SUBJECT:
Perry Nuclear Power Plant Docket No. 50-440, License Number NPF-58 2015 Silicone Sealant Report Pursuant to License Commitment 17 Attached is the 2015 Silicone Sealant Report for the Perry Nuclear Power Plant (PNPP). This report fulfills ongoing commitments associated with License Commitment 17 contained in the PNPP Updated Safety Analysis Report, Appendix 1 B.There are no new regulatory commitments contained in this letter. If there are any questions or if additional information is required please contact Mr. Nicola Conicella, Manager -Regulatory Compliance, at (440) 280-5415.Sincerely, Ernest J. Harkness
Attachment:
2015 Silicone Sealant Report Pursuant to License Commitment 17 cc: NRC Region III Administrator NRC Resident Inspector Office NRC Project Manager REIRS Project Manager A --
Attachment L-15-193 Page 1 of 2 Attachment L-1 5-193 FIRSTENERGY NUCLEAR OPERATING COMPANY PERRY NUCLEAR POWER PLANT DOCKET NUMBER: 50-440 LICENSE NUMBER: NPF-58 Silicone Sealant Report Pursuant to License Commitment 17 Contents Silicone Sealant Inspections and Testing Attachment L-1 5-193 Page 2 of 2 Silicone Sealant Inspections and Testing Background License Commitment 17 contained in the Perry Nuclear Power Plant (PNPP) Updated Safety Analysis Report, Appendix 1 B, contains an ongoing commitment to: a) PNPP will place the ductwork test specimens used for qualification testing of silicone sealant into the plant in an area environmentally approximate to the ESF ventilation systems. During each refueling outage, PNPP will leak test these test specimens to determine if any degradation of the silicone has occurred.b) PNPP will perform an engineering walkdown of the ESF ventilation systems during each refueling outage. This walkdown will consist of a visual inspection of a representative portion of exposed ductwork to check for indication of sealant degradation.
c) The results of "a" and "b" above, will be briefly summarized and reported to the NRC for years in which refueling outages occur.During 2015, the PNPP completed the fifteenth refueling outage (1R15). The maintenance plan to inspect duct sealant degradation and to test duct samples was satisfactorily completed in 1 R1 5. This report fulfills the ongoing commitment associated with Licensing Commitment 17 (L01090) of the PNPP Updated Safety Analysis Report, Appendix 1 B, "Silicone Sealant".Results The duct specimens were individually leak tested at rated pressure, in place, in the Intermediate Building 585 feet pipe chase. The thermoluminescent dosimeter (TLD)s were removed during the refueling outage and analyzed after their respective identification numbers were recorded.
The resulting dose (reported in millirem (mrem))recorded for specimen I on TLD S/N 8903010313 is 82,596 mrem (Deep) and for specimen 2 on TLD S/N 8903000313 is 120,679 mrem (Deep). New dosimetry was installed during 1R15, specimen 1, TLD S/N 1746, and specimen 2, TLD S/N 1747.The results of the duct specimen leak test for the General Electric Silpruf and Foster 30-02 sealants showed no degradation in air leakage at the sealant connections.
The Engineered Safety Features (ESF) ventilation systems (i.e., the Annulus Exhaust Gas Treatment (M15) system, the Control Room HVAC [Heating, Ventilation, and Air Conditioning] (M25/26) system, and the Fuel Handling Building Ventilation (M40)system), were walked down and a representative portion of the exposed exterior silicone sealants were inspected.
The exposed exterior sealant on the ductwork inspected during this walkdown was found to be in good condition with no observable degradation or leakage.